Cabazon Elementary School Construction Schedule Activity Description MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL Off-Site Utilities & Street Work On-Site Rough & Finish Grading Building A, Classrooms Building B, Administive Offices & Cafateria Building C, Library Relocatable Classrooms & Restroom Buildings Parking Lot Lighting, Pavement & Signage Landscape & Irrigation Work SUB-TOTAL BASED ON ORIGINAL CONTRACT 243 DAYS TIME EXTENTION DUE TO CHANGES IN SCOPE OF WORK 109 DAYS TOTAL DURATION 352 DAYS 2000 2001
Transcript of Cabazon E.S.
Cabazon Elementary School Construction ScheduleActivity Description MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL
Off-Site Utilities & Street Work
On-Site Rough & Finish Grading
Building A, Classrooms
Building B, Administive Offices & Cafateria
Building C, Library
Relocatable Classrooms & Restroom Buildings
Parking Lot Lighting, Pavement & Signage
Landscape & Irrigation Work
SUB-TOTAL BASED ON ORIGINAL CONTRACT 243 DAYS
TIME EXTENTION DUE TO CHANGES IN SCOPE OF WORK 109 DAYS
TOTAL DURATION 352 DAYS
2000 2001