C P 650 E L U PROJECT
Transcript of C P 650 E L U PROJECT
CALPECO 625 AND 650 ELECTRICAL LINE UPGRADE PROJECT
PRESENTATION TO THE TRPA GOVERNING BOARD APRIL23, 2015
THE NORTH LAKE TAHOE TRANSMISSION SYSTEM A loop that runs between Truckee, Squaw Valley, Tahoe City, and Kings Beach Multiple Lines, 132, 609, 625, 629,
650
Loop operates at 60 kV
Some lines, or line segments, have capacity for 120 kV
Kings Beach Diesel Generation Station provides backup capacity
PROPOSED PROJECT
Primary Components: rebuild the 650 Line; rebuild the 625; rebuild the Northstar substation
connection; and upgrade, modify, and/or
decommission six substations.
Upgrade 625 and 650 Lines and substations from 60 kV to 120 kV
EIS/EIS/EIR LEAD AGENCIES
USDA Forest Service EIS pursuant to NEPA
Tahoe Regional Planning Agency EIS pursuant to the TRPA Compact
California Public Utilities Commission EIR pursuant to CEQA
PHASE 2 Substation
Improvements North Truckee
Northstar
Initiate Kings Beach
Decommission Brockway Substation
PHASE 3 Rebuild/Reconductor 625 Line
Substation Improvements Tahoe City
Squaw Valley
Complete Kings Beach
STATUS OF USFS REVIEW/APPROVAL
Draft Record of Decision (ROD) released with Final EIS/EIS/EIR in Sept. 2014
Received one objection triggering objection review/resolution process
Objection resolution meeting held on Jan. 5, 2015
Objection resolution letter from USFS provided on Jan. 15, 2015, closing the objection process – No modifications to the document were directed.
USFS may issue final ROD and authorize project
CPUC ACTION
ALJ Proceeding Written Testimony
Extensive Briefing
CPUC Approved Decision on March 26, 2015 Certifies EIR as CEQA compliant
Grants Permit to Construct with conditions: May construct Phase 1 now
Construction of Phase 2 (89 MW) and 3 (100 MW) subject to approval of new load growth model and verification of approaching trigger points
CPUC Energy Division will review and verify (Tier 2 Advice Letter process)
SCOPE AND FOCUS OF THE EIS/EIS/EIR Land Use Forestry Resources Scenic Resources Geology, Soils, and Land
Capability and Coverage Hydrology and Water Quality Biological Resources Recreation Heritage and Cultural
Resources
Hazards and Hazardous Materials
Public Services and Utilities Traffic and Transportation Air Quality, Greenhouse Gas
Emissions, and Climate Change
Noise Socioeconomics and
Environmental Justice Growth Inducing Impacts
Effects Found Not Significant • Land Use • Forestry Resources • Scenic Resources • Geology, Soils, and Land Capability
Coverage
• Hydrology and Water Quality • Recreation • Hazards and Hazardous Materials • Public Services and Utilities • Traffic and Transportation • Noise
Significant and Unavoidable Effects in Lake Tahoe Basin
Proposed Alternative • Cultural Resources – Potential to encounter previously unrecorded subsurface sites
during construction
ENVIRONMENTAL REVIEW HISTORY
March/April, 2012
November 2013
December 2013
December 2013
January 7, 2014
Scoping Notices and Meetings
Draft EIS/EIS/EIR published
GB & APC Public Hearings
2 Public Workshops
End of Public Comment Period
FINAL EIS/EIS/EIR
Final EIS/EIS/EIR distributed in September 2014
Evaluated four Alternatives plus the No Action/No Project Alternative
Alternative 4 (Proposed Alternative) identified as the Environmentally Preferable/Environmentally Superior Alternative
One Significant and Unavoidable Impact for Alternative 4 in TRPA Jurisdiction: Potential discovery/damage of unrecorded subsurface cultural
resources
ALTERNATIVE 4: ARTICLE 6.16 FINDINGS The Final EIS/EIS/EIR is in compliance, procedurally and
substantively, with Article VII of the Compact, Chapter 3 of the Code and these Rules of Procedure
For all significant impacts in the basin (except one), the finding was made that “changes or alterations have been required in or incorporated into the project which avoid or reduce the potentially significant adverse effects to a less than significant level”
For the potentially significant related to the possible discovery/damage of unrecorded subsurface cultural resources, the finding was made that “specific considerations, such as economic, social or technical, make infeasible the mitigation measures or project alternatives discussed in the EIS on the project”
PLAN AREA STATEMENT 019, MARTIS PEAK
• Existing Kings Beach Substation is a legally existing non-conforming use
• Upgrade constitutes expansion, intensification, or modification of a nonconforming use
• PAS Amendment adds Public Utility Center as a permissible use in Martis 019
PAS 019, MARTIS PEAK AMENDMENT
Creation of Special Area #1
Addition of “public utility centers” to the list of permissible uses.
BROCKWAY ABANDONMENT • Upgrade of Kings
Beach Substation allows removal of Brockway Substation
• Distribution lines would be moved from currently above ground to underground
REQUESTED GOVERNING BOARD ACTION
Certification of the Final EIS
Adoption of the proposed amendments to Plan Area Statement 019-Martis Peak
Approval of Phase 1 & 2 of the proposed project
625/650 Electrical Line Upgrade Project
Submitted by California Pacific
Electric Company (CalPeco) “Liberty Utilities”
25
• Purchased NV Energy’s California service territory effective Jan. 1, 2011
• Approx. 1,476 square miles, 7 counties and 49,000 customers
• Legal name is Liberty Utilities (CalPeco Electric) LLC
• Two office locations: South Lake Tahoe
and Tahoe Vista • Regulated by the Calif. Public Utilities
Commission (CPUC)
Service Territory Overview
Purpose: Improves reliability • allows greater load transfer and switching ability
of loop system in case of single-contingency outage (N-1)
Scope: Upgrades existing lines and associated substations through a phased construction schedule
• 60 kilovolt (kV) to 120 kV • entire transmission loop to operate at 120 kV
(some rerouting for access)
Environment: Minimizes Impacts • FINAL EIS/EIS/EIR September 2014 • Collaborative effort
– TRPA, USFS, CPUC – Counties, Cities, other stakeholders – Extensive public review process
26
625/650 Electrical Line Upgrade Project
625/650 Electrical Line Upgrade Project Phase 1 – 650 Line Rebuild from Truckee to Kings Beach
Phase 2 – Upgrades at North Truckee, Northstar and Kings Beach Substations to Allow a portion of the system to operate at 120kV (All work inside existing substations; no work on power lines)
Phase 3 – 625 Line Rebuild from Tahoe City to Kings Beach to allow full system operation at 120kV. (Also completes Substation work)
27
Project Goals (EIS/EIS/EIR)
1. Provide normal capacity for current and projected loads. 2. Provide reliable capacity to assure adequate service to all
customers during single-contingency outages. 3. Reduce dependence on the Kings Beach Diesel Generation
Station. 4. Reduce the risk of fire hazards and outage durations
associated with wooden poles and encroaching vegetation. 5. Provide more reliable access to the 625 Line for operation
and maintenance activities.
FINAL EIS/EIS/EIR dated September 2014 (DRAFT dated November 2013)
28
CALPECO 625 AND 650 ELECTRICAL LINE UPGRADE PROJECT
PRESENTATION TO THE TRPA GOVERNING BOARD APRIL23, 2015
ALTERNATIVES
Alternative 1: PEA Alternative 2: Modified Alternative 3: Road Focused Alternative 4: Proposed Alternative 5: No Action Alternative
Alternative 1: PEA Alternative • Developed in the
Proponent’s Environmental Assessment
• Greatest potential for
ground disturbance
Alternative 2: Modified Alternative
• Similar to Alternative 1, PEA Alternative, but some modified segments
• Double circuit reduces
visibility, but increases potential disturbance in the ROW
Alternative 3: Road Focused Alternative • Re-routes 625 Line to more
closely follow the “Fiberboard Freeway”
• Places more of the 650 Line along SR 267
• Minimizes ground disturbance, but increases visibility
• Greatest potential to conflict with the Truckee-Tahoe Airport
Alternative 4: Proposed Alternative • Elements of Road
Focused and PEA Alternatives
• Places facilities in proximity to existing roadways while maximizing the use of existing 650 Line
ALTERNATIVES CONSIDERED BUT REJECTED 12 additional alternatives were screened
Addressed issues such as: implementing only part of the project,
improving other parts of the system,
submarine cable,
using more locally generated power from diesel generators,
undergrounding,
managing demand.
ALL ALTERNATIVES CONSIDERED BUT REJECTED (CONT.)
Vetted alternatives based on three criteria: Would the alternative meet project purpose/need/objectives Is the alternative feasible (i.e., legal, regulatory, technical) Does the alternative avoid or substantially lessen any significant effects of
the proposed project
For example--Undergrounding Does not consistently meet objective of increased access
Winter snow coverage over vaults, pump groundwater from vaults before work
Feasibility can be influenced by cost Would not reduce overall environmental effects
Excavation—potential effects on cultural resources, air, noise, traffic Must keep vegetation removed over line Construction beside existing ROW to keep existing line operating during construction
FORESTRY IMPACT DATA Data in various tables on pages 4.3-12 through 4.3-18 Forest removal correlated closely with overall ground disturbance. Highest for Alt. 1, slightly less for Alt. 2, least for Alts 3 and 4. Generally follows this trend for acres of forest land conversion, number
of trees removed, volume of timber removed, and SEZ effects For example, trees greater than 1” diameter Alt. 1 – 58,000 trees removed; 25,600 net loss (harvest of roughly 350
houses of merchantable timber) Alt. 2 – 56,800 trees removed, 22,450 net loss (harvest of roughly 345
houses of merchantable timber) Alt. 3 – 47,450 trees removed, 23,300 net loss (harvest of roughly 285
houses of merchantable timber) Alt. 4 – 47,100 trees removed, 23,050 net loss (harvest of roughly 284
houses of merchantable timber)
UNDERGROUNDING Does not consistently meet objective of increased access Winter snow coverage over vaults, pump groundwater from
vaults before work
Feasibility can be influenced by cost
Would not reduce overall environmental effects Excavation—potential effects on cultural resources, air, noise,
traffic
Must keep vegetation removed over line
Construction beside existing ROW to keep existing line operating during construction