C ommissioning plan for UED@ASTA
description
Transcript of C ommissioning plan for UED@ASTA
Commissioning plan for UED@ASTA
Renkai Li
5/20/2014
ALD UED@ASTA Review
2
Outline
• Pre-operation preparation
• Commissioning plan
- Machine operation and e-beam characterization
- Transverse overlap of laser and e-beam
- Temporal overlap of laser and e-beam
• Summary
3
Pre-operation preparation
• Checklist
- Safety
- Training
- Trigger and timing
- Equipment protection
- Modulator, klystron, LL and high power rf
- Alignment
- rf gun
- Laser
- Magnets and power suppliers
- Motors/actuators
- Cameras
- Diagnostics
- Data management
- Software
UED@ASTA preparation checklist
4
Pump-probe control and data acquisition
control
delay stage
Shutter S1/S2
acquire
photodiode D1/D2
Virtual pump Camera C2
EMCCD
Computertransfer
To be built and tested off-line.
Sample holder
control trigger
1D1
S1
e-beam
BS1D2
sample
1C2S2
delay stage
EMCCD
Computer
> 100 M/s
gun
5
Commissioning plan
• Laser optics installed by July 15th
• Beamline installation July 15th – July 31th
• Aim to run e-beams starting from August 1st w/o sample chamber
6
Machine operation and e-beam characterization
• Most tasks ready by August 1st
- Safety
- Training
- Trigger and timing
- Equipment protection
- Modulator, klystron, LL and high power rf
- Alignment
- rf gun
- Laser
- Magnets and power suppliers
- Motors/actuators
- Cameras
- Diagnostics
- Data management
- Software
August 1st – 15th
• Operation of the machine
• e-beam energy, charge, spot size
• Stability of e-beam parameters
• shot-to-shot fluctuation
• long-term (a few hours) stability
August 15th -
• Sample holder control
• laser and e-beam transverse overlap
• laser and e-beam temporal overlap
7
Transverse laser and e-beam overlap
aperture (4-5 mm diameter)
steering coils
He-Ne
laser
e-beam
screencamera
stage
Sample holder at UCLA
screen
SiN window (broken)
SiN window
8
Temporal laser and e-beam overlap
Steps to find time-zero
1) Fast photodiode D1 and D2 (< 100 ps or 3 cm)
2) Measure the rest of optical path length (~1 cm)
3) time-of-flight of the e-beam (from simulation)
4) Ultrafast plasma lensing effect (<1 ps)
400 fs step size
J. R. Dwyer et al., Phil. Trans. R. Soc. A 364, 741 (2006)H. Park et al., RSI 76, 083905 (2005)
2000 mesh TEM Grid-8 ps -4 ps 0 ps
4 ps 8 ps 12 ps
16 ps 20 ps 28 ps3 MeV beam up to ~50 J/cm2 L0
LC. M. Scoby et al., dx.doi.org/10.1016/j.ultramic.2012.07.015
9
Summary
• Pre-operation preparation (checklist, now – August 1st)
• Machine operation / e-beam characterization (August 1st - )
• Transverse overlap of laser and e-beam
• Temporal overlap of laser and e-beam
• Experiment using samples with ultrafast (100 fs) response
Thank you!