By Electronic Mail ([email protected])
Transcript of By Electronic Mail ([email protected])
PO Box 383
Madison, CT 06443
Voice: 646-734-8768
Email: [email protected]
Web: renew-ne.org
July 31, 2020
By Electronic Mail ([email protected])
Mariah Winkler, Chair
NEPOOL Markets Committee
ISO New England, Inc.
1 Sullivan Road
Holyoke, MA 01040
Subject: RENEW Report on FCA 16 ORTP Calculation Assumptions
Chair Winkler:
At the July 14-15, 2020, Markets Committee (MC) meeting, Concentric Energy Advisors (CEA)
and Mott MacDonald (MM) on behalf of the ISO presented more details regarding their proposed
assumptions for calculating the Offer Review Trigger Price (ORTP) and net Cost of New Entry (CONE)
values for Forward Capacity Auction 16 (FCA 16). While ISO, CEA, and MM have addressed some of
the feedback RENEW Northeast (RENEW) had previously provided, RENEW finds several flawed
assumptions still exist that significantly deviate from current market conditions for planned new clean
energy resources in the Capacity Commitment Period 2025-26.1
The accompanying report prepared by RENEW’s consultant Boreas Renewables with
contributions from Daymark Energy Advisors provides RENEW’s feedback on the ISO’s assumptions
presented at the July 14-15 MC meeting that RENEW believes require adjustment. It is paired with a
worksheet containing the analysis performed for RENEW’s July 15 presentation on implied capital costs
from recently signed offshore wind power purchase agreements and the proposed Renewable Energy
Certificate price forecast methodology.
RENEW believes several of the flawed assumptions will have significant negative effects on the
final ORTP values for clean energy technologies. They will create an unnecessary barrier to entry for
these resources when they attempt to enter the market. One example of a flawed assumption, which also
might be the most significant, is the ISO’s offshore wind capital cost input due to its having roughly
double the prevailing commercial expectation. RENEW projects this one difference in the assumed
project cost will raise the offshore wind ORTP by approximately $45/kW-month and preclude creation of
an ORTP for this technology.
RENEW’s consultants at Boreas Renewables interviewed market participants and non-market
participant developers and turbine manufacturers to verify the ISO’s assumptions against their real-world
experiences. The accompanying report contains information, including publicly available documentation,
from these interviews and RENEW’s recommendations based on them. RENEW respectfully requests the
1 The comments expressed herein represent the views of RENEW and not necessarily those of any particular
RENEW member.
Mariah Winkler, NEPOOL Markets Committee Chair
July 31, 2020
Page Two
ISO use this report and the worksheet to inform its decisions regarding the assumptions to be used in the
final ORTP calculations to make the final ORTP values accurately reflect prevailing commercial
activities.
Thank you for considering RENEW’s positions on the proposed assumptions. I stand ready to
continue this discussion prior to the next MC meeting to clarify RENEW’s recommendations in the
memo. If that continues not be an option for the ISO, I welcome the opportunity for RENEW and the ISO
with our consultants to review information after the next MC meeting.
Sincerely,
Francis Pullaro
Executive Director
Enclosures
copy: Debbie Cooke. Principal Analyst, Market Development, ISO New England Inc.
Danielle Powers, Concentric Energy Advisors
Offer Review Trigger Price Calculation Assumptions
Prepared for RENEW Northeast
July 31, 2020
Summary of Recommendations
ISO Assumption RENEW Recommendation
General
Project lifetime 20-year lifetime, no value
beyond this
25-year lifetime for onshore and
offshore wind, 30 years for
solar. In year 20 of the model,
include expected revenues from
later years net of ongoing O&M
costs, appropriately discounted.
REC Price $21.79/MWh (2025$) based on
average trading prices for 2017-
2019, escalated to 2025$
Use a broader range of years as
the basis for this assumption
rather than selectively using
only the lowest price historical
period.
Day Ahead Market Participation 50% of wind, solar offered in
DAM
ISO should provide assumptions
representative of actual market
offers by DNE Dispatchable
wind with CSOs. We expect this
to be approximately 90%.
Onshore wind production profile Monthly average 24-hour
production profile (12 total)
based on ME and NH historical
data, scaled to assumed capacity
factor
Use the hourly production time
series data for onshore wind
project(s) in a similar location
for the same time period as the
LMP data (2017-2019) created
by DNV-GL for ISO-NE, scaled
to the assumed capacity factor
Offshore wind production
profile
The onshore wind profile, scaled
to the offshore wind capacity
factor
Use the hourly offshore wind
production time series data for
the same period as the LMP data
(2017-2019) created by DNV-
GL for ISO-NE, scaled to the
assumed capacity factor
Stand-alone solar production
profile
Monthly average 24-hour
production profile (12 total)
based on MA and CT projects
Use the hourly solar production
time series data for Connecticut,
for the same period as the LMP
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 2
installed since January 2016,
scaled to assumed capacity
factor
data (2017-2019), created by
DNV-GL for ISO-NE, scaled to
the assumed capacity factor
Solar plus Storage: solar
production profile
Monthly average 24-hour
production profile (12 total)
based on MA and CT projects
installed since January 2016,
scaled to assumed capacity
factor
Use the hourly solar production
time series data for SEMA, for
the same period as the LMP data
(2017-2019), created by DNV-
GL for ISO-NE, scaled to the
assumed capacity factor
Offshore Wind
Capital Cost $5,876/kW (2019$) $2,900/kW (2019$) based on
RENEW’s analysis of recent
offshore wind PPA contracts
Project size Gross: 800 MW
Net: Not included in past
presentations
Gross: 820.5 - 840 MW
Net: 800 MW
Based on System Impact Studies
of offshore wind projects
currently in the interconnection
Queue
Onshore Wind
Location Northern NH (POI on Coos loop
near Berlin)
Central NH (south of
Whitefield) to avoid congestion
and interconnection issues
present in Northern NH
Curtailment, localized
congestion
Not included in past
presentations
Provide more detail on
congestion and curtailment
embedded in historical LMP
data and technology efficiency
factor
Interconnection Costs $7M transmission owner
interconnection facilities (new
3-breaker ring bus) + $38M
network upgrade to 25-mi of
115 kV line from Berlin to
Whitefield
Reconsider POIs with lower
interconnection costs. If POI
remains unchanged, revise
$38M upgrade cost to reflect
prior estimate of $4.5M-$6.75M
for this same upgrade.
Solar
Fixed vs Single Axis Tracking Fixed Create a separate ORTP model
for fixed solar arrays and single
axis tracking solar arrays
O&M LTSA Cost $15.77/kW-yr (2025$) $9.40/kW-yr (2025$) Based on
recent Woods Mackenzie
findings and conversations with
current NE solar developers
Battery Storage
E&AS Revenue (without FRM
including scarcity adjustment)
$2.40/kW-mo (2025$) based on
simplified, suboptimal dispatch
methodology
ISO should hire an outside firm
specializing in battery revenue
modeling to provide the battery
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 3
dispatch optimization, just as
IMM has done for FCA 15. We
would expect revenues to be
greater than $3.83/kW-mo from
EMM baseline analysis.
Major Equipment Capital Costs $677/kW (2019$) $600/kW based on recent NREL
findings on battery capital costs
Fixed O&M - Augmentation
plan
Included, but details unknown Should reflect level of battery
cycling in model. Unclear if
augmentation costs reflect the
minimal level of cycling in
ISO’s model.
Variable O&M – Augmentation
cost
Unclear what is included in
$10/MWh assumption
VOM should not include cost of
augmentation if that is already
included in fixed O&M
Solar + Battery
AC vs DC Coupling AC coupled DC coupled based on efficiency
and cost advantages
Solar DC:AC ratio 1.4 Closer to 2.0, corresponding to a
DC coupled system
Inverter rating Two 5 MW inverters One 6-7 MW inverter,
corresponding to a DC coupled
system
Battery dispatch First 10 MWh produced by solar
each day used to charge battery,
discharged in Hours Ending 18-
20
“Clipped” solar energy stored in
battery, used for reserves and
discharged for energy to make
room for upcoming clipped
energy. Energy and reserves
optimization should be
performed by same battery
revenue modeling expert as
stand-alone storage.
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 4
General
While much of our feedback is specific to a technology, there were several assumptions that are relevant
for multiple technologies.
• Project Lifetime
• REC Pricing
• Day-Ahead (DA) Market Participation
• Wind and solar production profiles
Project Lifetime
Two recently published reports1 regarding project lifetimes by Lawrence Berkeley National Laboratory
reveal that both solar and wind professionals currently anticipate project lifetimes far longer than the
ISO’s standard assumption in previous ORTP calculations of 20 years. The Berkeley Lab wind report
notes that not a single of the wind industry professional surveyed anticipates a lifetime of a project less
than 25 years, and most wind developers anticipate project lifetimes of 30 years. Of the solar industry
professionals surveyed, only 2 anticipate lifetimes less than 30 years and most anticipate lifetimes greater
than 30 years with 42% of respondents anticipating lifetimes greater than 35 years. Understanding the
ISO is limited by the Tariff to 20 years of real-dollar cash flows2, RENEW highly recommends the ISO
include a merchant tail in the twentieth year of its model of the energy revenue that a project would
receive beyond its contracted lifetime net of ongoing O&M costs.
This will ensure the ISO more fully captures the expected revenues of these projects over their projected
lifetimes and reflects the full economic value of the resources, consistent with the assumptions used by
developers making commercial commitments. RENEW understands this is a departure from past
methodology but strongly believe that this is well within the spirit of developing an accurate offer floor
price and permissible by the Tariff, which does not specify the term over which capital costs, expected
non-capacity revenue, and operating costs are to be calculated.
REC Pricing
We believe the ISO’s approach for Renewable Energy Credit (REC) price forecasting for the
recalculation of the ORTP values is unreasonable based on historic trends in REC prices and forward
trading data. ISO is proposing averaging three historic years of REC prices (2017-2019) and escalating
that number to 2025$, resulting in an assumption of $21.79/MWh (2025$). However, this does not
capture longer term REC price trends or current forward trading, and it is unlikely to predict trends in the
future. Available REC prices for the years 2015, 2016, 2020, and 2021 appear to average roughly
$40/MWh, approximately double the value from the period chosen by ISO for its analysis. Picking the
three lowest-priced years as the basis for the REC price forecast is inappropriate. If a historical period is
to be used as the basis for this assumption, a broader range of years should be used as the basis rather than
selectively using only the lowest priced historical period.
1 Lawrence Berkeley National Laboratory, “Benchmarking Anticipated Wind Project Lifetimes,” https://eta-
publications.lbl.gov/sites/default/files/wind_useful_life_report.pdf and Lawrence Berkeley National Laboratory,
“Benchmarking Utility-Scale PV Operational Expenses and Project Lifetimes,” https://eta-
publications.lbl.gov/sites/default/files/solar_life_and_opex_report.pdf 2 III.A.21.1.2.(b) Includes the following provision for the ORTP calculation: “The model looks at 20 years of real-
dollar cash flows discounted at a rate (Weighted Average Cost of Capital) consistent with that expected of a project
whose output is under contract (i.e., a contract negotiated at arm’s length between two unrelated parties).”
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 5
RENEW presented an analysis of REC pricing trends at the July MC meeting. A further explanation of
that analysis and our REC pricing recommendation is included at the end of this memo.
DA Market Participation
ISO proposed to use the same strategy for all renewable energy technologies (onshore wind, offshore
wind, solar): offer half of their generation in DA and the remaining in RT. However, beginning June 1,
2019 all DNE Dispatchable Generators with a capacity supply obligation must submit an offer into the
DA market equal to their expected generation for the next day.3
We believe that this certainly should apply to the wind projects proposed by ISO for the ORTP
calculations, but also for the solar projects which ISO has stated its intention to make DNE dispatchable
under equivalent terms well in advance of 2025. Therefore, we suggest that these projects should be
offering approximately 90% of their output in the DA markets (to account for some uncertainty in DA
forecasts) and the remaining 10% in RT. However, we encourage the ISO to look at actual market offers
and provide a reasonable assumption to CEA on an appropriate value for a project to be offering in the
DA markets. From the market pricing assumptions ISO has shared so far, we do not believe that this will
cause a large difference in the settlements that these resources receive but believe it is important to
accurately capture current market rules in these models and should be a fairly easy change to make.
Wind and Solar Production Profiles
We strongly encourage the ISO to use the hourly power production time series data created by DNV-GL
for ISO and presented by Steven Judd at the February and July 2020 Planning Advisory Committee
(PAC) meetings.4 The currently-available datasets that ISO has available in-house contain modeled
hourly historical power production between the years 2012 and 2019 for all existing onshore and offshore
wind sites as well as all currently planned offshore wind sites. The ISO has publicly posted an aggregated
data set representing the full onshore wind fleet, normalized to nameplate capability, and the full planned
offshore wind fleet, also normalized.5 In addition to this aggregate fleet data, ISO has the production time
series data for each individual onshore and offshore project that it can use internally for a project such as
this.
DNV-GL is currently expanding this existing wind dataset for ISO, to cover the years 2000-2011
(resulting in a 20 year data set) and add an aggregate, normalized solar profile for each of the eight load
zones for the same 20-year period. As of the July 22 PAC meeting, ISO expected to have these data sets
available any day.6
3 III.13.6.1.6.1. Beginning on June 1, 2019, Market Participants with DNE Dispatchable Generators with a Capacity
Supply Obligation must submit offers into the Day-Ahead Energy Market for the full amount of the resource’s
expected hourly physical capability as determined by the Market Participant. Market Participants with DNE
Dispatchable Generators having a Capacity Supply Obligation must submit offers for the Real-Time Energy Market
consistent with the characteristics of the resource. For purposes of calculating Real-Time NCPC Charges, DNE
Dispatchable Generators shall have a generation deviation of zero. 4 February ISO presentation: https://www.iso-ne.com/static-
assets/documents/2020/02/a7a_wind_power_time_series_isone.pdf
February DNV-GL presentation: https://www.iso-ne.com/static-
assets/documents/2020/02/a7b_wind_power_time_series_dnvgl.pdf
July ISO presentation: https://www.iso-ne.com/static-
assets/documents/2020/07/a4_scope_of_work_for_stochastic_time_series_modeling_for_iso.pdf 5 https://www.iso-ne.com/static-assets/documents/2020/05/2020_isone_wind_dataset_2012-2019_rev2.zip 6 Our understanding is that these data sets have been delivered to ISO prior to the date of this memo.
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 6
There are significant differences between offshore and onshore hourly wind profiles, and we encourage
ISO to look to current onshore and offshore wind measurements, forecasts, and modeled data, including
the DNV-GL datasets, for proof of this statement. We do not believe scaling onshore wind profiles to
offshore capacity factors is an appropriate method for modeling offshore wind profiles.
Finally, weather, load, and intermittent generator output are all strongly correlated. Dispatching monthly
averaged generation profiles over hourly load profiles will create a mismatch between weather conditions,
load, and output and would not accurately capture the relationship between available energy and LMPs
that would be expected from these resource types in the ORTP analysis. Instead of using a monthly
average profile, we suggest using the hourly generation profiles from the same time period as the load and
LMP profiles, scaled to the appropriate capacity factor.
We strongly encourage ISO use its existing DNV-GL data for developing both the onshore and offshore
profiles used in the ORTP calculations. When available, the DNV-GL solar profile for the Connecticut
load zone should also be used for the solar project in Windham County in the ORTP model and the solar
profile for SEMA should be used for the hybrid solar + battery project located in Bristol County, MA.
The ISO has (or will imminently have) all of these hourly profiles available in-house and it should not be
difficult to use them in this analysis.
Offshore Wind
For offshore wind specifically, we appreciated the detailed explanation and information provided by MM
at the July 14-15 MC meeting. However, we still have serious concerns with the following two items:
• Capital Costs
• Nameplate
Capital Costs
RENEW provided extensive feedback regarding capital costs both during our meeting with the ISO on
July 2 and at the MC meeting on July 14-157. RENEW explained its methodology for implying capital
cost expectations from recent PPA pricing, which is explained in further detail in this memo’s section
below on PPAs. RENEW determined the expected capital cost of the offshore wind ORTP project is
approximately $2,900/kW. The ISO’s proposed capital cost assumption of $5,876/kW is roughly double
the capital cost expectation for projects currently under development. RENEW estimates this cost
difference alone would cause an approximately $45/kW-mo difference in the final offshore wind
ORTP value. This difference will result in offshore wind not being anywhere close to receiving an
ORTP. ISO-NE has not provided enough evidence of its methodology and due diligence to justify costs
double those current offshore wind developers are expecting.
While RENEW finds many of the individual line items presented by MM to be flawed.8, Interconnection
costs are one example of line-item level benchmarking the ISO should be performing that will show the
large discrepancy between MM’s assumption and currently available data produced by ISO-NE. This
7 Previously, RENEW Northeast provided feedback to ISO’s initial assumptions presented at the June MC meeting
in a memo on June 29th with the subject line “FCA 16 ORTP Calculation Assumption Review” and on a subsequent
call with ISO, Boreas Renewables, RENEW, CEA, and MM on July 2. RENEW also gave a follow up presentation
at the July 14-15 MC meeting on offshore wind capital costs expectations in the Northeastern U.S. Markets based on
recently signed power purchase agreements (PPA) and Renewable Energy Credit (REC) pricing. 8 Though ISO has asked for feedback on the individual line items in its bottom-up model rather than feedback on the
total cost, ISO and its consultant have not provided sufficient information for stakeholders to understand what is
included in each line item, making it impossible at this time to provide further line-item level feedback.
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 7
example illustrates why current industry professionals are questioning MM’s assumptions and perhaps
why ISO-NE should question them. MM’s interconnection cost assumption of $70M does not align with
the cost estimates in the actual offshore wind interconnection studies completed by ISO-NE. The 800
MW (net) interconnection at Brayton point (QP618) studied by ISO had an interconnection cost estimate
of just $15.1M. This is precisely the location and injection level being assumed for this ORTP analysis
yet the interconnection cost assumption used in the ORTP analysis is 464% higher than the actual cost
estimate provided in the interconnection study. A further 288 MW offshore wind injection at Brayton
Point identified an additional cost of just $3.87M (QP669). Of the thirteen offshore wind projects with
interconnection studies completed by ISO, the average interconnection/upgrade cost estimate has been
$35.5M, half of ISO’s assumption. Only three of the thirteen had interconnection costs of $70M or above.
ISO has claimed its consultants have looked at current market data, but participants are struggling to
grasp what data that is. We have not found a single recent publication that indicates expected offshore
wind costs exceeding $4,000/kW, let alone $5,876/kW. The International Renewable Energy Agency9,
the Department of Energy10, NREL11, and Lazard12 all have capital cost ranges that are significantly lower
than ISO’s assumption. While we do not suggest that any one of these reports is precisely representative
of the ISO’s hypothetical project, these reports give a broad range of reasonableness for estimates of
capital costs. Even with this broad range, ISO’s assumption falls well outside expectation whereas
RENEW’s recommended assumption of $2,900/kW based on analysis of recent PPA’s falls within the
ranges reported by all four of these sources.
RENEW requests the ISO thoroughly review all assumptions MM has presented for offshore wind and
contact offshore wind developers and turbine manufacturers (or look at the latest filings with the IMM by
these same firms) to confirm the bottom-up model for the proposed project.
Accounting for Losses between Nameplate Rating of Turbines and Net Injections
As we mentioned in our June 29 memo, the offshore wind projects being planned for the MA offshore
wind lease area are oversizing their gross nameplate rating to account for losses between the turbines and
the Point of Interconnection (POI). In the June 29 memo, we pointed to QP618, QP624, and QP781 which
each had significantly larger gross nameplate values (all by more than 30 MW) than levels of net injection
at their POI’s. Two of these projects have POI injections of 800 MW, which we understand to be the
same as ISO’s intent for the hypothetical ORTP project. At the July 21, 2020 Reliability Committee
meeting, QP624 increased its gross nameplate rating to 840 MW without increasing its POI injection of
800 MW. It was confirmed at the July Reliability Committee meeting that the losses between the turbines
and the POI account for the difference between the gross and net ratings.
Of the thirteen offshore wind projects in the MA offshore lease area for which ISO has completed an
interconnection study (either a Feasibility Study or a System Impact Study)13, all but two explicitly point
9 IRENA, “Renewable Power Generation Costs in 2019,” https://www.irena.org/publications/2020/Jun/Renewable-
Power-Costs-in-2019. $2,800-3,900/kW range of costs for the largest European projects with 2019 CODs (between
400 and 600 MW) and significant cost declines expected as project sizes grow in upcoming years. 10 DOE, “2018 Offshore Wind Market Report,” https://www.energy.gov/eere/wind/downloads/2018-offshore-wind-
market-report. Range of $2,500-$4,000/kW expected between 2020 and 2030. 11 NREL, “2020 Annual Technology Baseline,” https://atb.nrel.gov/electricity/2020/data.php. Class 7 Moderate
(expected) overnight capital cost plus grid connection cost for a 2025 COD project is $3,152/kW with an
Advanced/Conservative (low/high) range of $2,835 - $3,810 (2018$). 12 Lazard, “Lazard’s Levelized Cost of Energy Analysis, Version 13.0,”
https://www.lazard.com/perspective/lcoe2019. $2,350 - $3,550/kW range of offshore wind capital cost 13 Queue positions 618/699/846, 624, 632, 669, 700, 781, 782, 791, 792, 806, 829/922, 830, 909
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 8
to a gross nameplate rating that is higher than the net injection at the POI, with the difference being
similar in magnitude to the three specific projects called out above.
In the creation of their dataset for modeled historical OSW production discussed earlier in this memo,
DNV-GL used a generic assumption of 2.5% electrical losses between the turbines and the POI. If ISO’s
intent is to have a plant capable of injecting 800 MW to the grid, consistent with current projects in the
Queue, then we suggest that the gross nameplate rating of the project should be increased by at least 20.5
MW (matching DNV-GL’s electrical loss assumption) and would encourage a 40 MW increase to match
current, similar OSW projects which have run detailed studies regarding their losses.
This is important to the analysis because the 47% offshore wind capacity factor ISO is using is applied to
the gross nameplate rating of the wind plant to determine the MWh produced. We believe the capital costs
in ISO’s model are intended to be based on the assumption that the project will use two undersea AC
cables to deliver the project’s power to the Point of Interconnection. Those cables are able to deliver
approximately 400 MW each.14 These cables along with the interconnection facilities and network
upgrades are a significant share of the capital cost of the project and must be fully utilized in order to
optimize the project’s economics. That is the reason why nominal 800 MW projects (at the Point of
Interconnection) have gross ratings of approximately 840 MW.
By assuming an 800 MW gross project rating in its ORTP model, ISO is forcing the same fixed capital
costs associated with the undersea cables, interconnection facilities, and network upgrades to be spread
across fewer MWh than if it assumed an 840 MW gross project rating (or even an 820.5 MW gross rating
if basing the number on DNV-GL’s generic loss assumption).
Onshore Wind
At the July 14-15 MC meeting, MM provided additional details regarding the location of the proposed
onshore wind project. As several participants noted at the meeting, the classification of this project as
Central NH lead us to expect an easier and less costly interconnection than the one proposed on the Coos
loop in Northern NH. Given this new information about the project location, we provide feedback on the
following items:
• Location Implications
• Curtailment
• Interconnection
Location Implications
This project is connected to a constrained part of the grid that has historically experienced localized
congestion. We believe this congestion has impacted LMP values at the local nodes on this loop. In the
dispatch model, we are unclear whether ISO is using historical LMPs at a specific node in this loop or if a
zonal LMP is being used. If nodal LMPs are being used, we are concerned that they will be lower than
those seen in other parts of the system (such as Central NH) and that this reduces the energy revenues per
MWh produced by the project. Further, we do not fully understand the dispatch model being used, but are
concerned about whether it has caused the project to be curtailed due to locally depressed LMPs. We
14 See slide 11 of the 2019 Economic Study Offshore Wind Transmission Interconnection Analysis from the May
20, 2020 PAC meeting: https://www.iso-ne.com/static-assets/documents/2020/05/osw-econstudy-
transmission-interconnection-analysis-may-2020-nonceii.pdf
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 9
suggest that a location in Central NH (south of Whitefield), as was originally proposed, would be a more
appropriate location for this ORTP project.
Curtailment
Slide 19 of the July presentation lists an “efficiency factor” of 0.834 used to adjust from the gross to the
net capacity factor. Among the losses it lists as being accounted for in this efficiency factor is “possible
curtailment (i.e., congestion on the transmission system)”. We would like to confirm whether any
curtailment was accounted for in this efficiency factor as well as whether any curtailment was seen in the
dispatch model and if so, how much.
Interconnection
To meet reliability standards in this part of the grid significant system upgrades will need to be
undertaken by the project, including the installation of a new 115 kV 3-breaker ring bus and 25 miles of
transmission line upgrades between Berlin and Whitefield, according to MM at the MC meeting on July
14-15. To fully understand the proposed interconnection, we ask that ISO provides more details on the
rationale for the interconnection process and the selection of the site location and POI, especially since we
believe that these interconnection costs raised the proposed overnight capital costs ($2,097/kW) over the
range ISO presented in June ($1,250-2,000/kW). Of the seven onshore wind projects that have had an
interconnection study completed as part of the serial study process since the beginning of 2018,15 only one
has required the rebuilding of transmission lines and therefore has had significantly higher
interconnection costs (QP641). The remaining six projects all had significantly lower interconnection
costs. Because “transmission to market was the final differentiator” for choosing NH, according to MM’s
June 10 presentation, we would like to know the other locations that were considered in CEA and MM’s
initial analysis. Projects in the Queue indicate that other areas may be more economically attractive.
Should the POI near Berlin be maintained, we would ask ISO to look more closely at the cost of
increasing the rating of the line from Berlin to Whitefield. Queue Position 280 (which withdrew from the
queue after completing its Feasibility Study), a 172 MW project with a similar Point of Interconnection,
would have required the rating of this same transmission line to be increased. That upgrade carried a cost
estimate of $4.5-$6.75M in the project’s Feasibility Study. Though the study is a bit outdated now, it is
hard to believe that the cost of this same upgrade has increased to $38M as shown on slide 20 of the July
presentation.
Solar
For the solar PV ORTP calculation, we want to expand on a suggestion we made at the July 14 MC
meeting regarding having two ORTP values (one for fixed rack and one for single-axis trackers) for solar
projects and highlight one of the cost estimates MM clarified at the July meeting.
• Fixed vs. Tracking Arrays
• O&M LTSA Costs
Fixed vs. Tracking Arrays
As we suggested at the July 14-15 MC meeting, we believe it would be appropriate to have two ORTP
values for solar projects attempting to participate in FCA 16. Based on conversations with NE developers,
we expect to see both single-axis trackers (SAT) and fixed-rack solar arrays with CODs in 2024-25 as
15 Queue positions 649, 655, 760, 555, 641, 420, and 486
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 10
well as the following two years for which this ORTP calculation will apply. Though the ISO does not see
the prevalence of fixed rack versus tracking projects in the queue based on the information collected in
the interconnection process, at least one large solar developer we have spoken with has identified that
they have only tracking projects in the queue at this point. These two types of solar arrays have significant
differences in capital costs and revenues, so much so that a single ORTP value would not be able to be
applied accurately to both technologies. We believe that, where sites with appropriate topography for
trackers is being developed in New England, trackers add about 5% to overall capital costs and O&M
costs and can increase energy production by about 10% and qualified capacity about 50%, as compared
with fixed mount arrays. We strongly encourage the ISO to reach out to multiple developers with SAT
projects in the Queue to better understand the latest costs of this technology if there are concerns with the
economic feasibility of SAT systems. We would be happy to put ISO in touch with these developers. If
there are financial reasons to not include SAT projects in the ORTP calculation process as MM has
implied in our discussions, we would appreciate a detailed cost-benefit based explanation of the reason
for this exclusion.
O&M LTSA Costs
As we suggested in our June 29 memo, we expect O&M costs associated with PV Long Term Service
Agreements (LTSA) to be between $7-11/kW-year for solar projects to be built in 2024-25. This estimate
is based on numerous discussions we have had with current NE solar developers and publicly available
resources. The figure below was taken from an article published in Greentech Media in which Wood
Mackenzie discussed their Global Solar PV Operations & Maintenance 2020 report. It suggests that
LTSA prices near $3.5-5/kW/year are currently being seen but may be too low. Full wrap contracts
(which they have estimated at $9.40/kW/year) are more representative of today’s full solar O&M costs.
Figure 1: Source: https://www.greentechmedia.com/articles/read/solar-om-shortcuts-lead-to-higher-costs-later-per-new-report
Keeping in mind these prices are for contracts signed prior to 2020, this shows a large disparity between
market pricing trends and ISO’s estimate that should reflect prices in 2024-25. If ISO believes that the
$15.77/kW/year is an appropriate value for the LTSA and ongoing maintenance costs for their solar
projects in NE, we ask that they provide a detailed explanation of why the assumed costs for 2024-25 are
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 11
40-125% higher than contracts that have recently been signed. While we recognize that New England
O&M costs may be higher than global averages, we find it hard to believe that local O&M costs would
increase this dramatically especially since New England developers have told us that their current O&M
contract costs fall within these ranges reported by Wood Mackenzie.
Battery Storage
While we realize that the ISO has already received a significant amount of feedback regarding the battery
storage technology, we would like to highlight the following items that we believe are most critical in an
accurate battery storage ORTP value and most likely to cause significant changes in the final ORTP
calculation:
• E&AS Revenue
• Major Equipment Capital Costs
• Fixed O&M
• VOM
E&AS Revenue
We believe that ISO’s E&AS strategy and dispatch methodology vastly over-simplifies the complexity of
potential revenue opportunities for battery storage technologies and represents a fraction of what this type
of technology could earn in the current markets. We strongly encourage the ISO to look at recently filed
requests with the Internal Market Monitor (IMM) for resource-specific offer floor prices for battery
storage projects’ participation in FCA 15. There, we believe you will find many examples of real-world
battery developer strategies that predict revenues far higher than what is currently being assumed.
As another reference to look at, we would encourage you to consider the External Market Monitor’s
methodology found in their November 12, 2019 filing in FERC Docket No. ER20-308. In their analysis
they found that what they called “Approach 3” would have yielded $3.83/kW-mo of energy and
regulation market revenue. They concluded that “although we believe this estimate is a good
representation of the EAS revenues a reasonably competent ESR owner could achieve, we expect that
ESR owners could exceed these levels of EAS revenues.” This is thus a good lower-limit benchmark
against which any analysis should be compared. As the currently proposed $2.40/kW-mo E&AS value
doesn’t even come close to the EMM’s baseline, it implies that the ORTP analysis is modeling what an
incompetent ESR owner would be expected to achieve, to use the EMM’s terminology.
We highly recommend that ISO/CEA contracts with an outside firm that specializes in battery storage
revenue modeling in order to perform the battery dispatch optimization. We understand that this has been
done by the IMM in its review of offer floor price requests for FCA 15, and we believe this would
produce the most reasonable results for this ORTP recalculation process. Given the time constraints of
this process, working with the same outside vendor that the IMM is working with for FCA 15 seems like
it would be a realistic and reasonable option.
Major Equipment Capital Costs
Based on NREL’s 2020 updated report on cost projections for utility-scale battery storage16, we believe
that the ISO’s estimate for major equipment is high for projects with a COD in 2025. The figure below
comes from this report and shows costs that we believe are comparable to the “Major Equipment”
16 NREL, “Cost Projections for Utility-Scale Battery Storage: 2020 Update,”
https://www.nrel.gov/docs/fy20osti/75385.pdf
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 12
category listed by MM in their calculation of overnight capital costs. Here we can see that a 2-hour
battery could be expected to have a capital cost of $600/kW in 2025. The ISO’s estimate of $677/kW is a
13% increase from NREL’s prediction. We request that the ISO adopt NREL’s battery capital cost
prediction for 2025 because we believe that it aligns with current market expectations of developers in
NE. While 13% may not appear significant, we believe that this difference will have a material impact on
the final ORTP value for the battery storage technology.
Figure 2: Cost Projections for 2-, 4-, and 6-hour duration batteries using the mid cost projection. Source:
https://www.nrel.gov/docs/fy20osti/75385.pdf
Fixed O&M
ISO is including augmentation in the Fixed O&M costs; however little detail has been provided on what
this augmentation plan looks like. Under the currently designed revenue model, the battery storage unit
would be primarily providing reserves and therefore not cycle frequently. This is reflected in the 5%
monthly “topping off” procedure ISO is proposing to replenish the parasitic losses from the battery sitting
fully charged. If the battery does not fully cycle frequently then it will experience less degradation than if
it was cycling daily. We want to confirm that this smaller amount of degradation is accounted for in the
fixed O&M number that ISO presented, including the duty cycle of the battery storage unit under the
current dispatch strategy.
VOM
It is our understanding from discussions with battery project developers that VOM should be used as a
dispatch model parameter but is not an actual cost to the project if augmentation is already counted in the
fixed O&M number, as is the case in the fixed O&M costs ISO has presented. VOM is typically used as a
dispatch optimization model parameter to limit the cycling of the battery in the model to avoid cycling the
battery storage unit when the unit would not achieve a certain profit margin. However, because battery
degradation is already accounted for in the fixed O&M costs, the VOM “cost” is then added back to the
model results so that augmentation costs are not double counted. From ISO’s explanation of the proposed
VOM costs at the last MC meeting it appeared that it may be inadvertently double counting the
augmentation costs by treating VOM as a true cost in its model. We ask that ISO review its augmentation
assumptions related to fixed O&M together with the VOM to make sure that they reflect a) the costs of
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 13
the level of cycling performed by the battery in the model and b) that they do not double count these
costs.
Solar + Battery Storage
We object to the proposed configuration and dispatch of the co-located solar + battery storage project
which we believe is inconsistent with optimal project design as well as the logic ISO has provided
regarding the standalone battery revenue opportunities.
• AC vs. DC Coupling
• Battery Dispatch
AC vs. DC Coupling
We believe the configuration of this project should be changed such that the PV and battery are DC
coupled. Of the two coupling methods for co-located facilities (AC or DC), DC-coupling of battery
storage units and solar PV arrays provides significant efficiency and cost advantages over AC-coupled
facilities. In an AC-coupled facility there are losses when energy is converted from DC to AC through the
first inverter from the solar facility and then from AC to DC through the second inverter to the battery
then back from DC to AC through the second inverter again when the battery discharges. In a DC-coupled
facility the energy flows through a single inverter once when either the battery discharges or the PV
array’s energy is flowing to the system. In addition to the loss of efficiency, AC-coupled facilities require
two expensive inverters, sized to the full rated capability of each asset, as well as additional associated
interconnection equipment. Further, because the ISO’s model assumes the solar panels are rated at 140%
of the inverter rating, there will be significant “clipped” solar energy during sunny periods. This energy
can be captured by the battery storage for later discharge to the system if the PV and battery are DC
coupled but is wasted if the two are AC coupled as ISO has proposed. To take advantage of this ability to
store and later discharge the clipped solar energy, recently designed DC-coupled PV + battery projects
typically have a significantly higher DC:AC ratio, with a value of 2.0 or higher appearing to be somewhat
standard.
According to ISO’s current dispatch strategy, the battery and the solar facility would not be producing
their full capacity simultaneously. Therefore, we believe a single inverter slightly oversized to the
capacity of one of the assets (approximately 6-7MW) in a DC-coupled facility would likely provide the
best financial and technological advantage for a co-located facility. Meanwhile, the solar array and battery
storage unit can still be considered separate assets so long as they each have their own DC meters. The
only benefit we see for having an AC-coupled system with 10 MW AC of injection rights would be that
each asset would be able to fully monetize its capacity. However, we believe the cost of increasing the net
injection outweighs the minimal capacity benefit because of the low seasonal qualified capacity of the
solar project. If ISO continues to propose an AC-coupled facility we would expect a detailed explanation
of the financial and technological advantages of this configuration.
Battery Dispatch
In their explanation of their decision to have the standalone battery storage unit provide primarily
reserves, MM explained that a 2-hour battery would not be able to economically provide energy arbitrage.
However, their dispatch methodology for the battery storage unit AC-coupled to the solar facility in the
co-located project (charging on the first 10 MWh of solar production and discharging in hours ending 18-
20) is clearly energy arbitrage. The project would be foregoing the revenue from the first 10 MWh of the
solar facility (equivalent to purchasing 10 MWh of energy during a higher priced period than if it was a
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 14
standalone battery charging in the lowest-priced hours of the day) and selling this energy at a later time
with a theoretically higher price. Because the units are AC-coupled, the battery is receiving no efficiency
benefit from being co-located with the solar facility and is losing approximately 15% of the AC PV
output due to the roundtrip efficiency of the battery, which it would need to overcome to make a profit on
storing this energy. We are wondering where the difference between the battery strategies arises and why
the ISO is justifying an energy arbitrage solution when it clearly stated that this is not a winning strategy
based on their analysis for a standalone battery unit. The only benefit we are aware of that the battery
would receive from ISO’s configuration and operational strategy as compared with a stand-alone battery
is access to the Investment Tax Credit. However, it appears to us that the ITC benefit is not sufficient to
outweigh the reduced revenues that result from the decision to configure and operate the project as
proposed. The ITC could be obtained by DC-coupling the two pieces of the project, gaining capital cost
efficiencies and significantly increased revenue opportunities in addition to the tax credit.
We believe that the dominant, optimal strategy for a battery attached to a solar project would be to DC-
couple the battery and have it store only clipped solar energy. It would then be able to provide reserves
with that stored clipped energy and discharge to provide energy at times that would be most profitable in
order to make room for capturing upcoming expected clipped energy. This would limit the cycling of the
battery, reduce costs, and increase revenues.
We would highly recommend reaching out to developers with co-located facilities in the Queue to
understand how they expect their facilities to perform and hiring a consultant to develop a battery revenue
strategy for such a hybrid project, just as we are proposing with the standalone battery storage unit. We
believe that this will result in a consistent methodology between the ISO’s technologies and accurately
reflect how a co-located facility would participate in the current markets.
Implied Offshore Wind Capital Costs based on Recent PPA Prices
Recently executed power purchase agreements (PPAs) in New England provide the best source of
information for expected offshore wind capital expenditures. They represent actual commercial
expectations and commitments that have been made for projects precisely like the hypothetical ORTP
project being modeled by ISO. As RENEW presented at the July MC meeting, Daymark Energy Advisors
created a financial model to calculate the capital expenditures implied by recent offshore wind power
purchase agreement pricing. The model is a discounted cash flow model which is designed to be
consistent with the model ISO-New England used in the 2016 ORTP calculation. Using this model, we
found that the implied capital costs for the four projects we studied fell between $2,300-$3,700/kW (in
2019$), with a weighted average of $2,900/kW. These costs are 39-62% of ISO’s estimate of $5,876/kW
(in 2019$). The weighted average is 49% of ISO’s estimate. We believe that difference between the
weighted average implied capital cost from our analysis and ISO’s capital cost assumption, will cause an
approximately $45/kW-mo difference in the final ORTP value and will be the difference between
offshore wind projects receiving and not receiving an ORTP value.
Though the Tariff requires ISO to create a bottom-up financial model, if the resulting total costs are out of
line with all indicators of prevailing total costs it indicates that the line-items in the model are not accurate
and needs to be refined. ISO should perform their own similar analysis to benchmark their capital cost
assumption against commercial arrangements being made. In addition to our PPA analysis, we have not
found a single recently published resource that suggests costs even close to $5,000/kW, let alone the
$5,876/kW value proposed by ISO. Attached to this memo we have provided the model we used to imply
project capital costs from PPA pricing. We would be happy to provide additional information on our
modeling methods if this helps ISO understand our methodology or results.
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 15
Projects Studied
Contract pricing is publicly available for four offshore wind PPA’s for projects in New England offshore
lease areas to be built within the next five year. These four PPA’s have been included in our analysis and
are shown in the Table below:
Table 1: Offshore Wind Projects with Publicly Available Pricing
Project Capacity State
RFP
Selection
Date
COD
Expectation at
PPA Execution
First Year PPA
Price
Vineyard Wind
Tranche 1
400 MW MA May 2018 2021 $74/MWh
(Escalating
2.5% Annually)
Vineyard Wind
Tranche 2
400 MW MA May 2018 2022 $65/MWh
(Escalating
2.5% Annually)
Revolution
Wind Tranche
1
400 MW RI May 2018 2023 $98.425/MWh
(Fixed for
contract term)
Mayflower
Wind
804 MW MA October
2019
2024 $77.76/MWh
(Fixed for
contract term)
Three additional offshore wind PPA’s for projects in the same area with similar commercial operation
dates totaling 1104 MW (Park City Wind and Revolution Wind Tranches 2 and 3) have been signed as a
result of Connecticut solicitations. However the pricing for these contracts is not public. Therefore, we
did not include these projects in our analysis.
Project Life
The PPAs for these projects are all for 20-years. However, to model the developers’ expectation that these
projects have lifetimes longer than 20-years, we assumed that the projects would continue to operate for
an additional 5-years as merchant projects. This additional revenue net of O&M costs was incorporated in
our NPV analysis to determine the implied capital costs. This results in a more conservative estimate of
the implied capital costs than assuming the project is to have a NPV of zero over the 20-year contract
lifetime.
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 16
Revenue Assumptions
There are three primary sources of revenue for offshore wind projects: energy, capacity, and renewable
energy certificates (RECs). The PPAs for all the projects were 20-year contracts for energy and RECs.
We used the contract prices for energy and RECs along with an assumed capacity factor of 47 percent to
determine revenue for the first 20-years for those products in the model. The 47 percent net capacity
factor is consistent with ISO-New England’s proposed assumption for the ORTP analysis. Beyond 20-
years, to be conservative, we assumed that the project would continue to get energy revenue by selling
that product at market rates. For the market rates, we assumed an energy value of $40/MWh in 2022,
escalated at 2% annually thereafter.
We assumed that the projects would also participate in and retain any revenue from the ISO-NE capacity
market. We used the actual qualified capacity for the Vineyard Wind Project to calculate an assumed
qualified capacity value for the other projects as shown in the table below, and assumed that each project
cleared its full qualified capacity in the FCA. We developed two capacity price assumptions: $2/kW-
Month based on the FCA 14 clearing price and $6/kW-Month based on a more optimistic view of future
capacity prices that may have been reasonable at the time these PPA bids were made. We assumed 25-
years of capacity revenue. Once again, adding a capacity revenue stream with these assumptions resulted
in a conservative estimate for the implied capital cost.
Table 2: Vineyard Wind Qualified Capacity
Project Nameplate
(MW)
Summer
Qualified
Capacity
(MW)
Summer
Qualified
Capacity as
% of
Nameplate
Winter
Qualified
Capacity
(MW)
Winter
Qualified
Capacity as %
of Nameplate
Vineyard
Wind 800 282.8 35% 522.5 65%
Investment Tax Credit
The Investment Tax Credit for offshore wind will be phased out over the next several years. Projects that
meet both construction start and commercial operation date milestones qualify for declining amounts of
the credit. We used ITC assumptions consistent with the assumed commercial operation date at the time
of each project’s bid into the state procurement. The ITC percentages assumed in the analysis were 18%
for Vineyard Wind and Revolution Wind and 12% for Mayflower Wind.
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 17
Other Assumptions
To complete the model, we needed to make several assumptions regarding the financing and operations
and maintenance of these projects. The financing and operations and maintenance assumptions in our
model came from ISO-NE as shown in the Table below. Where ISO has shared an assumption for the
FCA 16 ORTP calculation, we used that assumption (e.g., fixed O&M costs). Where ISO has not yet
shared an assumption for the FCA 16 ORTP calculation, we used the ISO’s assumption from the 2016
calculation (e.g., After Tax WACC).
Table 3: Financing and O&M Assumptions
Assumption Estimate Source
After Tax WACC 7.29% ISO Estimate
Inflation 2% Daymark Estimate
Federal Tax Rate 21%
State Tax Rate 8%
Fixed O&M Costs $93.47/kW-year ISO Estimate
Site Lease $665/MW ISO Estimate
Insurance 0.3% of installed costs ISO Estimate
Property Tax 1% ISO Estimate
Results
The table below summarizes the results from our PPA analysis. While we do not believe these are the
exact capital costs the projects are expecting, we do believe that this analysis gives a good benchmark for
where capital costs for projects completely analogous to the project ISO has proposed for the ORTP
technology fall as indicated by the contracts that have been signed to actually finance these projects.
In this analysis we have attempted to use ISO’s assumptions wherever possible and when in doubt have
attempted to err on the side of being conservative. We ask that ISO use this data to benchmark their own
offshore wind capital cost assumption, which is currently double the weighted average costs determined
through this analysis.
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 18
Table 4: Results from Daymark Energy Advisor’s PPA analysis to calculate implied capital costs, rounded.
Project Capacity COD
Expectation at
PPA Execution
Implied Capital
Costs ($2/kW -mo
Capacity Revenue)
(2019$)
Implied Capital
Costs ($6/kW-mo
Capacity Revenue)
(2019$)
Vineyard
Wind
Tranche 1
400 MW 2021 $3,100/kW $3,500/kW
Vineyard
Wind
Tranche 2
400 MW 2022 $2,600/kW $3,000/kW
Revolution
Wind
Tranche 1
400 MW 2023 $3,400/kW $3,700/kW
Mayflower
Wind
804 MW 2024 $2,300/kW $2,600/kW
REC Forecasting Methodology
Daymark Energy Advisors created the figure below for the July MC meeting to show trends in MA Class
I REC trading prices from the 2015 vintage year through the latest data on forward trades for vintage
years 2020 and 2021. The data is summarized further in the below table. As can be seen by the yellow
section of the figure and table which highlights the historical period used by ISO for their REC price
assumption, the three years ISO is proposing to use are the three lowest price years in the past five and a
half (the extent of the analysis performed by Daymark).
Table 5: Average REC price for each vintage during the vintage year. Source: Daymark Energy Advisors
2015 2016 2017 2018 2019 2020
$52 $36 $20 $12 $25 $38
RENEW Memorandum on FCA 16 ORTP Calculation Assumptions 7/31/2020
RENEW Northeast 19
Figure 2: Historic REC prices. Source: Daymark Energy Advisors
Unlike the dispatch model in which it is important to use load, weather, and LMP time series data from
the same time period to capture co-dependencies between model variables, there is no similar reason for
the REC price assumption to be based on the same time period as the LMP data. REC prices were more
than double ISO’s proposed value in the two years prior to the ISO’s selected time period and have
rebounded this year to again nearly double the price during ISO’s selected period. Selectively looking at
only the lowest-priced historical period is inappropriate, as would be an assumption based on only a short
highest-priced period.
There are, unfortunately, no good options for up-to-date, publicly available MA Class I REC price
forecasts that could be used instead of this historical approach. We therefor suggest that ISO take a longer
look at historical REC pricing to determine a reasonable assumption that does not appear to selectively
use only the lowest historical pricing data.
<<>>