Building Structures 1

#5

Antonín Lupíšek

Page 2: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

Floor Structures

• monolithic reinforced concrete

• monolithic RC with „lost formwork“

• prefabricated reinforced concrete

• composite reinforced concrete

formwork drawing = homework #3

drawing of layout of precasted structure

= homework #4

Page 3: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

Homework No. 3formwork drawing (scale 1:50)

• it is the view into finished formwork

before pouring concrete in it

• represents a real shape of a concrete

structure with basic dimensions

Page 4: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

What is formwork?

Pictures: http://www.nestservice.cz/realizace-betonovych-konstrukci/

vertical structures (load bearing walls) finished

Page 5: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

What is formwork?

Pictures: http://www.nestservice.cz/realizace-betonovych-konstrukci/

formwork assembly started

Page 6: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

What is formwork?

Pictures: http://www.nestservice.cz/realizace-betonovych-konstrukci/

formwork bottom finished

Page 7: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

What is formwork?

Pictures: http://www.nestservice.cz/realizace-betonovych-konstrukci/

reinforcement laying

Page 8: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

What is formwork?

Pictures: http://www.nestservice.cz/realizace-betonovych-konstrukci/

placing of concrete

Page 9: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

What is formwork?

Pictures: http://www.nestservice.cz/realizace-betonovych-konstrukci/

formwork disassembly

Page 10: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

What is formwork?

Pictures: http://www.nestservice.cz/realizace-betonovych-konstrukci/

formwork disassembly

Page 11: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

What can we find out from FD?

• location of bearing elements

• shapes and dimensions of future floor structures

• locations, dimensions and shapes of hatchways

• type of construction (element type ...)

• specification of used material (concerete type)

Page 12: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

Line types

• visible lines and edges – thin full line

• invisible (hidden under formwork) – thin dashed line

• bearing structures (walls&columns) outlines – thick full

• hatchways or

Page 13: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

Elements signs

Each element (wall, column, floor slab ...) has its own sign

made from big letter and number i.e. C1, W3 etc.

• vertical elements’ signs are in a square: C1 ... column no. 1

• horizontal elements’ signs are in a circle: S2 ... slab no. 2

• the area of slabs is signed with a diagonal crossing

• the element reinforcement orientation is symbolised by

arrows

Page 14: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

bearing structures outlines – full thickcross section outlines – full thick

horizontal elements’

signs – in a circle

vertical elements’

signs – in a rectangle

visible lines and

edges –full thin

slabs – main

reinforcement

orientation

hatchways

column

floor girderslab

(D1)

Page 15: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

column

floor girderslab

(D1)

Page 16: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

Dimensions - girders

Page 17: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

Dimensions – one way slabs

Page 18: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

Dimensions – two way slabs

Page 19: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

Your homework

Choose one of your bearing system schemes

and for its part (about 12 x 10 m) make a

formwork drawing (scale 1:50), including

dimensions pre-design of floor girders and

slabs.

Page 20: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

Example 1

Page 21: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

Example 2

Page 22: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

Example 3

Page 23: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before

Next training (13.11.)

short quiz on floor plan drawing

• walls

• doors

• windows

• tiling

• hatches

Page 24: Building Structures 1 BUS1 Training - cvut.czpeople.fsv.cvut.cz/~lupisant/bus1_5.pdf · Homework No. 3 formwork drawing (scale 1:50) •it is the view into finished formwork before