Builders Margin on Cost
-
Upload
gerry-triaz -
Category
Documents
-
view
10 -
download
1
description
Transcript of Builders Margin on Cost
BUILDER’S MARGIN ON PRIME COST AND PROVISIONAL COST ITEMS UNDER THE HBCA LUMP SUM BUILDING CONTRACT
HIA is often asked about how to claim a builder’s margin on prime cost items and provisional
cost items. This issue can cause some confusion, so to ensure that you are not overcharging
or undercharging on your builder’s margin, HIA suggests you read the information below
before entering into your next HIA HBCA Lump Sum Building Contract.
Provisional Sums
A provisional sum item is used for work (including labour and materials) for which the builder,
after making all reasonable inquiries, cannot give a definite price at the time the contract is
signed. Common examples include landscaping, tiling and concreting.
Your margin for a Provisional Sum (as well as the costs of supervision and overheads) is the
percentage set out in Item 11 of the Schedule of Particulars to the Contract.
What if the actual cost is less than the allowance?
If the actual cost is less than the allowance then the owner is to be given a credit for the
difference. You do not apply a builder’s margin on the difference (as the allowance was
already inclusive of your margin).
Can I be paid more where the actual cost is more than the allowance?
If the actual cost exceeds the allowance then the builder is entitled to charge a margin on
the cost exceeding the allowance.
Prime Cost Items
Prime Cost Items are items that either have not been selected or whose price is not known at
the time the contract is entered into, and for which the cost of supply and delivery the
builder has made allowance for in the contract price. Examples include white-goods, tap-
ware and light fittings.
Your margin for a Prime Cost item is already included in the overall contract price, not in the
amount allowed for in Item 11 of the Schedule of Particulars. Therefore, if there is an
adjustment in the calculation of a Prime Cost item, whether it is an increase or decrease, no
margin would be applied to the difference.
Page 2
You Must Reasonably Estimate the Cost of a Provisional Sum or Prime Cost Item
The builder is required to ensure under the Home Building Contracts Act 1991 (WA) that the
allowance for each PS and PC are calculated with reasonable care and skill taking account
of all the information available to the builder at the date the contract is made including the
nature and location of the building site.
Upon completion of the work the subject of a Provisional Sum or Prime Cost item, or at the
next progress payment notice, the builder is obliged to provide the client with an itemised
statement of the price for the work or the items.
Should you require any further assistance on this or any other contractual matter please call
Michael O’Kane, HIA Workplace Advisor (Western Australia) on 9492 9200.