    5,9 MWe INTEGRATED BIOMASS

    GASIFICATION COGENERATION

    POWER PLANT

    MOVIALSA

    EQTEC Iberia, SL

    c/ Princesa, 2 3 planta E-08401 Granollers (BARCELONA) SPAINTel. +34 938702462 Fax +34 938702650

    email : [email protected]

  • 7/29/2019 Brochure Movialsa Gasification Plant English

    2/6

    2

    NEW TECHNOLOGIES IN ENERGY SAVING, EFFICIENCY AND RENEWABLE ENERGY

    GASIFICATION AND CHP POWER GENERATION PLANT

    RUNNING ON BIOMASS

    General View. Biomass gasification plant 1000 Kg/ h.EQTEC IBERIA IS BUILDING AN INTEGRATED BIOMASS GASIFICATION COGENERATION POWER PLANT(IBGPP), at th e al cohol dist ill ery of th e co mp any M OSTOS, VINOS Y ALCOHOLES, SA (M OVIALSA), locat ed atCampo de Criptana (CIUDAD REAL). CHP plant has an electrical output of 5,9 MW and produces 5600

    Kg/ h of saturated steam at 6 bar(g) and 159 m3 / h of hot water at 9 0 C, which are used by the alcohol

    factory. IBGPP plant w il l gasify 40 00 Kg/ h of waste bagasse from the alcohol factory and wil l al low total

    el imination of the bagasse and l iquid eff luent of t he factory. Bagasse is used as fuel into t he gasif ier plant

    and l iquid eff luent, so cal led vinazas (water with 1 or 2 % of organic matter) is concentrated on a

    mul tist age evaporator using residual heat from syn gas engines.

    IBGPP plant is designed to be extended to a t otal power output of 13 ,8 M We.

  • 7/29/2019 Brochure Movialsa Gasification Plant English

    3/6

    3

    Biomass gasif ication plant buil t by

    EQTEC Iberia is based on a bubb lin g

    fluid bed gasif ication technology.

    The plant under construct ion in

    M OVIALSA is the second order of t his

    gasif ication t echnology, whose k ey

    aspects are i t s high electr ical and

    thermal eff iciency, low operation and

    maint enance costs and low pollutant

    emissions.

    Emissions of the IBGPP plant are

    l imi ted to:

    NOX 500 mg/ Nm3

    CO 1100 mg/ Nm3

    PM10 < 5 mg / Nm3

    and emissions can be more reduced

    by using cat alysers.

    Transport of biomass gasifier.

    Waste bagasse used as biomass at IBGPP plant .

    Biomass gasifier oom under construction.

  • 7/29/2019 Brochure Movialsa Gasification Plant English

    4/6

    4

    Integrated biomass gasif ication power plant under construction is made up of:

    1 . Biomass gasification plant , biomass is gasified obtaining low calorific value synthesis gas, LHV is 5,5

    M J/ Nm3. Plant gasifies 400 0 Kg/ h of biomass and has four gasifiers, each one has an air preheater in

    order to increase thermal effici ency.2 . Synthesis gas cleaning system, m ade up of gas coolers, particle f ilter and ash cooler system .

    3 . Power plant, wit h three Jenbacher 62 0 syn gas engines. Total elect rical power output is 592 2 KWe.

    Jenbacher engines are turbocharged and have a double stage aftercooler in order t o maxim ize its

    mechanical efficiency.

    4 . Heat recovery system from syn gas engines, generating 56 00 Kg/ h of saturated steam at 6 bar(g)

    and 159 m 3/ h of hot water at 90 C, return at 75 C.

    5 . Electrical substation t o connect power plant wit h local electrical grid at 13 2 KV.

    SCADA monit oring & cont rol PC. Plant is running cont inuously on automat ic mode.

  • 7/29/2019 Brochure Movialsa Gasification Plant English

    5/6

    5

    Power plant w it h three 1974 KWe syn gas generator set under construct ion.

  • 7/29/2019 Brochure Movialsa Gasification Plant English

    6/6

    6

    Table shows Integrat ed Biom ass Gasifier Power Plant b alance.

    Table shows high electrical efficiency of more than 30 %. Typical Rankine cycle plant has an electrical

    effic iency of 2 4 % maxim um, in sim ilar pow er range of 5 - 15 M We. Thus IBGPP plant designed by EQTEC

    not only has much more electr ical eff iciency than com bustion plants but also generates steam and hotwat er without any power output reduction as i t happens on Rankine plants.

    A total eff iciency of 63 ,8 % is obtained.

    IBGPP plant is designed to run continuously

    on automat ic mode, 750 0 hours per year, wit h

    minim um operation manpower requirements.

    First 1 00 0 Kg/ hr Gasif ier l ine is alreadyrunning for more than 1500 hours and

    different biom asses have been tested.

    Syn gas engine oom romoutside under construct ion

    NOMINAL OUTPUT

    1. BIOMASS CONSUMPTION (KW) 19600

    (Kg/h) 4000

    2. ENGINES EXHAUST GAS FLOW (Kg/h) 43197

    3. ENGINES EXHAUST GAS TEMPERATURE (C) 456

    4. ENGINES EXHAUST GAS HEAT (KW) 3810

    STEAM GENERATION (6 bar sat) (Kg/h) 5600

    5. ENGINE HT COOLING CIRCUIT HEAT (KW) 2778

    90 C HOT WATER GENERATION (m3/h) 159

    6. TOTAL HEAT OUTPUT (KW) 6.588

    7. ELECTRICAL POWER OUTPUT (KW) 5.922

    8. ELECTRICAL EFFICIENCY (%) 30,2

    9. THERMAL EFFICIENCY (%) 33,6

    10. TOTAL EFFICIENCY (%) 63,8