BRIGHAM CITY– Signal Interconnect Project Type - Operations Signal Interconnect Project Cost – $...
-
Upload
jeffrey-winsor -
Category
Documents
-
view
214 -
download
0
Transcript of BRIGHAM CITY– Signal Interconnect Project Type - Operations Signal Interconnect Project Cost – $...
BRIGHAM CITY– Signal InterconnectProject Type - Operations
Signal Interconnect
Project Cost – $ 400,000
Funds Request – $ 371,000
Connect the signals in Brigham City via fiber or radio; run fiber along length of SR-91 (Main Street) from I-15 to VMS at the mouth of Sardine Canyon. Specifically, connect 500 W and 1300 S on Main Street with fiber. Also, connect 700 S, 200 N, and Forest on 500 W with radios.
BRIGHAM CITY – Box Elder AccessProject Type – Transit Service
Options for Independence
Project Cost – $ 352,000
Funds Request – $ 329,000
An area of significant need for people with disabilities, the elderly, and those with lower incomes is accessing their communities for shopping, doctor appointments, employment, and social activities. OPTIONS seeks support to expand transportation services for disadvantaged persons outside UTA service boundaries.
BOUNTIFUL CITY – 400 North 500 WestProject Type - Intersections
400 North 500 West Dedicated Right Turn Lane
Project Cost – $ 933,000
Funds Request – $ 859,000
400 North is a major on-off ramp. Increased demand along 400 N. and 500 W. (US 89) has resulted in this intersection having a poor LOS,
three of the eight movements currently operating at an LOS F. Adding dedicated right turn lanes in the east bound and north bound directions
will improve the LOS to at least LOS D.
FARR WEST – Variable Message SignProject Type - OperationsInstall Variable Message Sign
Project Cost – $ 328,000
Funds Request – $ 302,000
Install Variable Message Sign northbound I-15 (about Farr West) that would be used to alert traveling
motorists of roadway conditions on I-15 and I-84 to the Utah/Idaho border.
OGDEN CITY – Monroe/North Street SignalProject Type - Intersection
Intersection @ Monroe Blvd. and North Street
Project Cost – $ 1,289,357
Funds Request – $ 1,085,000
Presently a 4 way stop, the intersection creates undo delay and is operating less efficiently compared to a signalized intersection.
Current LOS is B/C. The project would add turn lanes to the west leg and increase (or define) the corner radii to suit large vehicle turning
movements. AADT is expected to increase once Monroe is connected to 1700 North in North Ogden; once that occurs, North
Street will be the next signalized collector to Washington/Wall/Harrisville south of 1700 North.
Project Cost – $ 1,204,000
Funds Request – $ 1,086,000
This project consists of constructing a CNG station at the City's Public Works facility. The city has a small fleet of trucks that have been converted to run on CNG and all future truck purchases will have CNG. The station will also be open to the public.
642 North 400 West, North Salt Lake
NORTH SALT LAKE CITY – CNG Refueling Project Type – Other
Kaysville – I-15 200 North Ramp MeterProject Type - Operations
I – 15 200 North NB On-Ramp
Project Cost – $ 250,000
Funds Request – $ 224,000
Install ramp meter
Communication & Passenger InformationProject Type - Transit
Various Areas in the Ogden/ Layton Urbanized Area
Project Cost – $ 709,000
Funds Request – $ 661,000
This project is a continuation of 2018 project to cover communication enhancements on UTA fleet and
infrastructure to allow UTA to offer real time passenger information to its riders on an incremental
basis. .
OGDEN/WEBER COUNTY - Bus PurchaseProject Type - Transit
Bus Purchase for Service From Ogden into Canyon
Project Cost – $ 1,027,080
Funds Request – $ 958,000
Ogden City, Weber County, Powder Mountain, Snow Basin, and UTA have started pilot seasonal local bus service from Ogden City to ski areas via Ogden Canyon. This now uses
older ski buses from the SLC area that have met the requirements for retirement. New buses are needed if this
service is to be made permanent.
OGDEN/WEBER COUNTY – Service AssistanceProject Type - Transit
Service Assistance From Ogden into Canyon
Project Cost – $ 691,000
Funds Request – $ 644,000
Winter service to Ogden area ski areas is needed to reduce pollution and congestion in the Ogden urbanized area, and in Ogden Canyon (which filters into
the urban area). Bus service is great for those skiing in the area, but is vital for the employees. Operating assistance for 2014-2015 will help establish this service..
UTA – Transportation Demand Management - RideshareProject Type - Transit
Various Areas in the Ogden/ Layton Urbanized Area
Project Cost – $ 40,000
Funds Request – $ 30,000
Provide individuals with carpool, vanpool, and other commuting matches. Educate communities and others
concerning alternative transportation options and promote those options that reduce single occupancy vehicle usage,
improve mobility, enhance air quality, and conserve energy.
Lease Vans Program – Van ExpansionProject Type - Transit
Various Areas in the Ogden/ Layton Urbanized Area
Project Cost – $ 150,000
Funds Request – $ 118,000
Purchase 5 new vans to increase the size of the vanpool fleet. For each additional van available, UTA is able to take an average of 8 SOV off the road and
reduce SOV miles.
Lease Vans Program – ManagementProject Type - Transit
Various Areas in the Ogden/ Layton Urbanized Area
Project Cost – $ 140,000
Funds Request – $ 127,130
Manage the daily logistics and expenses of a 420+ vanpool program which reduces single occupancy vehicle usage. Oversight of the program includes
managing each group's roster, payments, maintenance, and reporting riders and miles traveled
to meet federal guidelines.