Fairfax County Customer and Technical Support Center
September 8, 2016Presentation to NAIOP/NVBIA
![Page 2: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/2.jpg)
Projects Recently Held Up Liability follows Developer named in
the agreement Sale of company or property, and
issuance of RUP and Non-RUP does not release development agreement obligations
Developer defined at VA Code § 15.2-851.1
![Page 3: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/3.jpg)
Why require bonds? Protect public
› Ensure public and proffered improvements are constructed according to standards on the plans
› e.g., streets, walkways, streetlights, sanitary sewer, storm drains, trees
![Page 4: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/4.jpg)
Why require bonds? Requirements defined in PFM
Chapter 2-0600: Bonds & Agreements
Bond is returned to the developer when the public and proffered improvements are completed and accepted
![Page 5: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/5.jpg)
Bonds and Agreements Basics
New bonds for construction plans with public improvements› Bond Estimate Review › Bond and Permit Package Approval
Bond release = goal as soon as project is completed and approved
If the project is not completed by the bond expiration date:› Bond extension› Bond reduction› Bond replacementDetails: http
://www.fairfaxcounty.gov/dpwes/construction/bonds
![Page 6: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/6.jpg)
New bonds paperwork Private developer
› Permit package › Development Agreement› Corporate Surety/Letter of Credit/Set Aside
Letter/Cash› Signature authority – organizational documents and
incumbency certificates› Fees
County reviewDetails: http://www.fairfaxcounty.gov/dpwes/construction/bonds
![Page 7: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/7.jpg)
Practical Tip - Timing Any documents submitted by COB Friday
are reviewed prior to and included in the following Wednesday Bond Committee› Unless submittal is found incomplete
County review: Bond Committee› Department of Finance› Office of the County Attorney› LDS
![Page 8: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/8.jpg)
05/01/2023 8
Extension/Replacement/Reduction
County emails three notices: at 60 days before expiration, at 30 days and at time of Default
Bond reduction allowed when some work complete (at least 30%)
Replacement agreement is required when› Developer changes› Type of Surety changes› New Surety needed because bank has fallen below
rating requirements› Requires the same documents as a new bond
![Page 9: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/9.jpg)
05/01/2023 9
Customer initiates replacement bond
Customers may request a replacement bond at any time› Sale of property› Change of corporate ownership or
membership
![Page 10: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/10.jpg)
Final Bond Release Process(PFM 2-0603)
http://www.fairfaxcounty.gov/dpwes/publications/pfm/chapter2.pdf All improvements installed and required
approvals/acceptances obtained Developer requests bond release via the county
site inspector and passes final inspection Fairfax County Provides Letter 18 to Developer Fairfax County notifies Outside Agencies
› Seven business days for comment Letter 18 signed by Developer & returned to
Fairfax County Bond Released
![Page 11: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/11.jpg)
Shared Goal: Bond Release Before we can release bonds, approvals from:
› Fairfax County Water Authority› Wastewater› Street Lights› VDOT street acceptance› Urban Forestry› All development related proffers and their associated
agencies› Fire Marshal› Others (e.g., property corner certifications, geotechnical
certifications, permits, violations, etc.) Full list of requirements from PFM 2-0603 :
http://www.fairfaxcounty.gov/dpwes/publications/pfm/chapter2.pdf
![Page 12: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/12.jpg)
Shared Goal: Bond Release
Most common hold ups:› VDOT street acceptance› Proffers/development conditions
› Streetlights – either not installed or payment not received
![Page 13: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/13.jpg)
Defaults (PFM 2-0604)http://www.fairfaxcounty.gov/dpwes/publications/pfm/chapter2.pdf
Remember the emails sent at 60 and again 30 days?› (and again at default?)
If the development agreement expires, project moves into default
![Page 14: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/14.jpg)
Consequences of Default PFM 2-0600 Future agreements may not be
accepted Future bond amounts may be 150% of
engineering estimate Future cash or letter of credit may be
required in lieu of performance bond Hold up permit issuance and
inspections
![Page 15: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/15.jpg)
Per VA Code § 15.2-851.1, developers with prior defaults risk needing to post cash or letter of credit :
If the owner or developer has not met all previous land development obligations in accordance with all development agreements with the locality as determined by the governing body or its designated administrative agency for the previous seven years, then a personal, corporate, or property bond may be disallowed by the governing body as security for such facilities, and in such event, security for such facilities shall be restricted to a certified check, cash escrow, or a letter of credit that meets the requirements of clause (iv) herein.
See also PFM 2-0601.5.
![Page 16: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/16.jpg)
Per VA Code § 15.2-851.1, developers with prior defaults may be required to post 150% construction cost for future developments:
However, if for the previous seven years the owner or developer has not met all previous land development obligations in accordance with all development agreements with the locality as determined by the governing body or its designated administrative agency, the governing body may require that the allowance for estimated administrative costs, inflation, and potential damage to existing roads or utilities be greater than 25% of the estimated construction costs, but not to exceed 50% of the estimated construction costs. “Developer,” as used in this section, means any owner, builder, subdivider or other person or entity engaged in the land development process and shall include their principals, officers, members, managers, partners, alter egos, and members of the immediate family related to any of the foregoing.
![Page 17: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/17.jpg)
Developer Performance – Bond Amount
2-0601.2B (95-06-PFM) The bond amount is the full amount of the cost estimate plus contingencies, engineering costs and inflation. In the event the developer has not met all the previous land development obligations in accordance with all development agreements with Fairfax County for the previous seven years, then the bond amount should include the cost estimate plus a factor of 50 percent of the estimate to cover administrative costs, inflation, and potential damage to existing roads or utilities.
![Page 18: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/18.jpg)
Importance of Bond Release Avoid difficulties with your future
agreements – obtain bond release Street acceptance most frequent
hurdle NVBIA/NAIOP/Fairfax County/VDOT
committee› Joint inspection process› Better results
![Page 19: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/19.jpg)
Joint Inspections County inspector and technical specialist VDOT inspector Owner/developer and optionally their
contractor performing work onsite Held after owner/developer submits post-
construction package› Submit to county inspector with public street
inspection guideline checklist› County forwards to VDOT› VDOT contacts county staff with inspection
date/time
![Page 20: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/20.jpg)
Past Example Photos Conditions are site specific These are just examples – ultimately
the approving authority (e.g., VDOT) determines the final punch list› Joint inspection has helped speed this up
Your bond release can be held up because of details missed at construction
![Page 21: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/21.jpg)
Not ok - severely exposed aggregate on top of curb. Also, no cracks are acceptable – hairline or otherwise, in header curb or gutter pan.
![Page 22: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/22.jpg)
OK – Minor chips to curb and gutter is acceptable if damage is localized.
![Page 23: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/23.jpg)
Storm drain structure opening too wide: safety hazard. Not OK.
![Page 24: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/24.jpg)
Variable width
sidewalk, not ok
![Page 25: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/25.jpg)
Minor damage to gutter pan, ok if proper seal obtained when asphalt topping is applied. No severe chipping into gutter pan.
![Page 26: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/26.jpg)
Streets Degrade Over Time Proceed with street dedication before
wear and tear Failure to achieve street dedication
may require future milling and paving
![Page 27: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/27.jpg)
Questions?
![Page 28: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/28.jpg)
For more information http://www.fairfaxcounty.gov/dpwes/co
nstruction/bonds/ Most common errors:
http://www.fairfaxcounty.gov/dpwes/construction/bonds/common-errors.htm
Development agreement: http://www.fairfaxcounty.gov/dpwes/forms/developmentagreement.pdf
![Page 29: Bonds and Agreements Primer](https://reader035.fdocuments.us/reader035/viewer/2022070516/58751c961a28ab05598b79c9/html5/thumbnails/29.jpg)
For more information Bonds and Agreements Center
› Hallala Faraj, Chief› 703-324-1519› [email protected]
Site and Technical Services› Kenneth Williams, Chief› 703-324-1757› [email protected]
Customer and Technical Support Center› Ellie Codding, Chief› 703-324-1695› [email protected]