Bonding & Earthing (Final)

download Bonding & Earthing (Final)

of 67

Transcript of Bonding & Earthing (Final)

  • 8/3/2019 Bonding & Earthing (Final)

    1/67

  • 8/3/2019 Bonding & Earthing (Final)

    2/67

    BONDINGBond means an electrical

    connection between two or

    more conductors or non currentcarrying metallic parts oftraction masts or structures or

    supports and rails.

  • 8/3/2019 Bonding & Earthing (Final)

    3/67

    Transverse Bond It means a bond

    between two rails of a track or tworails of adjacent tracks.

    Longitudinal BondIt is an electricalconnection across a rail jointbetween consecutive lengths of rails.

    TYPES OF BOND

  • 8/3/2019 Bonding & Earthing (Final)

    4/67

    Impedance Bond It is a bond

    installed by signal and telecomdepartment, which provides a low

    impedance path for the tractionreturn current and relatively highimpedance path for track circuit

    current.

  • 8/3/2019 Bonding & Earthing (Final)

    5/67

    Fig.1. Impedance Bond

  • 8/3/2019 Bonding & Earthing (Final)

    6/67

    Fig.2. Impedance Bond

  • 8/3/2019 Bonding & Earthing (Final)

    7/67

    Fig.3. Impedance Bond

  • 8/3/2019 Bonding & Earthing (Final)

    8/67

    Structure Bond Bondconnecting the non-current

    carrying metallic parts oftraction mast or structure or

    support to the traction rail.

  • 8/3/2019 Bonding & Earthing (Final)

    9/67

    Fig: Structure Bond

  • 8/3/2019 Bonding & Earthing (Final)

    10/67

    Signal bond It is an electricalconnection across a rail joint,provided by the Signalling &

    Telecommunication Department,to facilitate flow of track circuit

    current.

  • 8/3/2019 Bonding & Earthing (Final)

    11/67

    Terminal Bond It allows delimiting

    the track circuit at a boundary with aninsulated Rail joints.

    Cross Bond It means a bond

    between two rails of a track or two

    rails of adjacent tracks. It is also called

    a transverse bond.

  • 8/3/2019 Bonding & Earthing (Final)

    12/67

    INTEGRAL TRANSVERSAL LINK ( ITL )

    It is interconnection of Dn line OPC,

    BEC and Up line OPC, BEC and tracks

    direct or through impedance bond.

    This shall be provided at an

    interval of 1 Km or less than one km.

  • 8/3/2019 Bonding & Earthing (Final)

    13/67

    TYPICAL ARRANGEMENT

    INTEGRAL TRANSVERSE LINK (ITL)

    ABB LIMITEDALTERNATE ARRANGEMENT

    INTEGRAL TRANSVERSE LINK ( TYPICAL LOCATION AT SUBHASH NAGAR FP)

    AT SUBHASH NAGAR FP

  • 8/3/2019 Bonding & Earthing (Final)

    14/67

    OVERHEAD PROTECTION CABLE (OPC)

    It is an ACSR conductor run on traction masts or

    structures or supports and clamped to their

    metallic parts/supports and connected to earth

    through ITL.

    ACSR conductor consists of 7 steel wires and 12

    aluminium wires each 2.5 mm dia .

    Its cross sectional area is 93.3 sq mm andoverall diameter is 12.5mm.

    Its tension should be 400kgf.

  • 8/3/2019 Bonding & Earthing (Final)

    15/67

    BURIED EARTH CABLE (BEC)It is a flexible Copper Conductors having 7 strands

    each of 2.5 mm ,35 sq mm x-sectional area and overall dia of 7.5 mm.

    It is run along the viaduct with which all themetallic reinforcement steel bars of via duct, piers

    parapet and equipments at viaduct are connected

    to maintain proper earthing.

    It is connected to earth to earth grid of Auxiliarysubstation through ITL

  • 8/3/2019 Bonding & Earthing (Final)

    16/67

    PLINTH OR CONTINUITY JUMPER

    An insulated stranded flexible copper

    conductors of approx.35 sq mm is used forinter connecting two track plinth to maintaincontinuity.

    The each end of deck is connected with theBEC for proper earthing.

  • 8/3/2019 Bonding & Earthing (Final)

    17/67

    EARTHING

    OF

    ELECTRICL

    SYSTEM

  • 8/3/2019 Bonding & Earthing (Final)

    18/67

    WHAT IS EARTHING?Earthing is an essential requirement to drain the potential

    deposition on any machine frame, structure, support,electrical installation etc due to poor insulation for

    achieving a safe working upon.

    E E

    FAULT CURRENT THROUGH EARTH

    LINK

    FUSE

    R

    YB

    N

    230VFAULT TO

    EARTH

    IN WINDING

  • 8/3/2019 Bonding & Earthing (Final)

    19/67

    WHY EARTHING?

    Earthing is designed primarily to preserve the securityof the system by ensuring that the potential on each

    conductor is restricted to such a value as is consistent

    with the level of insulation applied.

    Earthing shall generally be carried out in accordance

    with the requirement of Indian Electricity rules1956(I.E.Rule 2003) & IS 30431987.

  • 8/3/2019 Bonding & Earthing (Final)

    20/67

    OBJECTIVE OF EARTHING

    It should stabilise circuit potential with respect toground potential and limit the potential rise.

    It should protect men & materials from injury or

    damage due to over voltage or touching.

    It should provide a low impedance path to fault

    currents to ensure prompt & consistent operation of

    protective devices.

  • 8/3/2019 Bonding & Earthing (Final)

    21/67

    It should keep the maximum voltage gradient

    along the surface inside & around the substation

    within safe limits during ground fault.

    It should protect underground cables fromoverall ground potential rise & voltage gradient

    during ground fault in the system.

  • 8/3/2019 Bonding & Earthing (Final)

    22/67

    IMPORTANT I.E. RULE

    RELATED TO EARTHING:

    RULE No: 33.Earth terminal on consumers premises.

    RULE No: 61.

    (A) MAX: PERMISSIBLE RESISTANCE OFEARTHING SYSTEM.

    Large power station: - 0.5 ohms.

    Major sub-station: - 1.0 ohms.

    Small sub-station: - 2.0 ohms.In all other cases : - 8.0 ohms.

    The earth continuity: - 1.0 ohms.

    inside an installation

  • 8/3/2019 Bonding & Earthing (Final)

    23/67

    (B) CONNECTION WITH EARTH

    Earthing of neutral conductor of a 3-phase, 4-wire

    system.

    Earthing of all metal casing / covering of electric supply

    lines or apparatus.

    Testing of such earth resistance not less than once in

    every two years during a dry day of a dry season shall

    be conducted and recorded.

    Test results should be recorded and shall be made

    available to the EIG or Assisting officer to EIG, when

    required.

  • 8/3/2019 Bonding & Earthing (Final)

    24/67

    RULE No: 67.

    CONNECTION TO EARTH

    All equipments associated with HV /EHV installation,

    shall be earthed by not less than two distinct and

    separate connection with the earth having its own

    electrode, except an earth mat

    Testing of such earth resistance not less than once inevery year during a dry day of a dry season shall be

    conducted & recorded.

  • 8/3/2019 Bonding & Earthing (Final)

    25/67

    RULE No: 90. EARTHING

    In distribution system, all metal supports and allreinforced/pre-stressed cement concrete supports of

    overhead line and and metallic fittings attached shall be

    permanently and effectively earthed.

    Each stay wire shall be similarly earthed, unlessinsulators have been provided in it at a height not less

    than three mtrs from the ground.

    Every 5th pole as a minimum shall be grounded, if the

    foundations are not cements concrete blocks.

    RULE N 91

  • 8/3/2019 Bonding & Earthing (Final)

    26/67

    RULE No: 91.

    SAFETY AND PROTECTIVE

    DEVICE

    Every overhead line erected over any part of street or

    public place shall be protected with a device, approved

    by the EIG, for rendering the line electrically harmless

    in case it brakes.

    The owner of every high and extra high overhead line,

    shall be protected to the satisfaction of the EIG, to

    prevent unauthorised persons from ascending any of

    the supports of such overhead lines.

  • 8/3/2019 Bonding & Earthing (Final)

    27/67

    RULE No: 92.

    PROTECTION AGAINST LIGHTENING

    The owner of every overhead line which is so exposed

    , as may be liable to injury from lightening, shall

    adopted efficient means for diverting to earth, any

    electrical surge during lightening.

    The earthing lead for any lightening arrester shall not

    pass through any iron or steel pipe but shall be taken

    as directed as possible from the lightening arrester to aseparate earthing electrode / mat.

  • 8/3/2019 Bonding & Earthing (Final)

    28/67

    DISTINCTION BETWEEN

    GROUNDING AND EARTHING

    Grounding: Grounding implies connection of currentcarrying parts to ground.It is mostly either generator ortransformer neutral. Hence it is popularly called neutralgrounding.

    Grounding is for equipment safety.

    In case of resistance grounding system, it limits the core

    damage in stator of rotating machines. In case of solidlygrounded system, substantial ground fault current flowsenabling sensitive fault detection and fast clearance.

  • 8/3/2019 Bonding & Earthing (Final)

    29/67

    Earthing: Earthing implies connection of non currentcarrying parts to ground like metallic enclosures.

    Earthing is for human safety.

    Under balanced operating condition of power systems,earthing system does not play any role. But under anyground fault condition, it enables the ground faultcurrent to return back to the source without endengeringhuman safety.

  • 8/3/2019 Bonding & Earthing (Final)

    30/67

    Generator Transformer

    NG NG

    Earthing

    Neutral Grounding and Earthling

  • 8/3/2019 Bonding & Earthing (Final)

    31/67

    Earth As Conductor:

    Resistivity() of earth is typically 100-M.

    Resistivity() of copper is 1.7x 10 -8-M.

    Resistivity() of G. I. is 1.7x 10-7

    -M.Take as reference, 25x4mm copper strip.

    To obtain the same resistance, the size of G.I. Will be65x10mm.

    The corresponding figure for earth is 800x800 meters (158

    acres.)Hence, it shows metallic conductor is a preferred alternative

    conductor to earth to bring the fault current back to source.

    EARTH AS CONDUCTOR

  • 8/3/2019 Bonding & Earthing (Final)

    32/67

    Generator Transformer

    NG NG

    Earthing

  • 8/3/2019 Bonding & Earthing (Final)

    33/67

    ELECTROD RESISTANCE TO EARTH

    Conventional practice by Electrical engineer to measure

    the earth resistance is by using ohms law.

    This is similar to CT, where the flow of primary current

    results in voltage appearing across CT secondary. Which

    drives the current through the connected relay(burden).

    For electrode resistance to earth, current is injected to earth

    by electrode and electric field travels through the earth.The

    voltage appears at certain distance from electrode and the

    resulting impedance is electrode resistance to earth.

  • 8/3/2019 Bonding & Earthing (Final)

    34/67

    IF

    CT RV

    x

    v1

    Resistance area of driven earth rod

  • 8/3/2019 Bonding & Earthing (Final)

    35/67

    HEMISPHERICAL ELECTORD

    Consider a hemispherical electrode used for injection of

    current.Current flows through a series of hemisphericalshells of earth of continuously increasing cross section.

    The resistance offered by earth to spread of electrical field

    is given by:

    RX = dX / 2 X2.

    The resistance as a function of distance from electrode.

    The most interesting aspect is that almost 95% of final

    resistance is contributed by soil within 5meters of the

    electrode.

  • 8/3/2019 Bonding & Earthing (Final)

    36/67

    dx

    1

    x

    Spherical shells

    Resistance to earth of hemispherical electrode

  • 8/3/2019 Bonding & Earthing (Final)

    37/67

    Now consider two location A & B 100 Km apart from each

    other with respect to earth grids.Assume current is

    discharged at A. Only the soil within first 5 to 10 metersfrom A offers substantial resistance.

    The resistance offered by earth subsequently to reach B is

    very minimal.

    This the reason of our practice to treat earth pits with lime ,

    charcoal, & watering the pits. This reduces the resistance ofthe soil locally around the earth electrode. As the resistance

    away from the earth electrode is minimal.

  • 8/3/2019 Bonding & Earthing (Final)

    38/67

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    00 5 10987621 3 4

    4(-100MM)RadiusHemi-sphere

    Distance in Met.

    Resistancein%

    RESISTANCE TO EARTH OF HEMISPHERICAL ELECTRODERESISTANCE TO EARTH OF HEMISPHERICAL ELECTRODE

    INFLUENCING FACTORS FOR ELECTRODE

  • 8/3/2019 Bonding & Earthing (Final)

    39/67

    INFLUENCING FACTORS FOR ELECTRODE

    RESISTANCE

    The major factor is the length.

    Diameter or width(Cross section) has very minor influence.

    The resistance of pipe electrode is given by:-

    R = ( / 2 L) [ LN{ 8L / ( x 2.7183)}].Where, L = Length in Met.(pipe)LN=Nominal length(buried conductor)

    = Diameter in MetLet, consider the case of a length = 6 Met.

    For = 2.5Cm, R = 16.4 .

    For = 10 Cm, R = 15.3.

  • 8/3/2019 Bonding & Earthing (Final)

    40/67

    A horizontal earth strip of 75x10mm Cu and 45x10mm GI

    both of same length will offer almost same electrode

    resistance.

    Other interesting observation is that the electrode resistance

    is not much dependent on type of electrode materials like

    Cu,Al or GI.Resistance is the function of physicaldimension, mainly length.

    So, it is observed that 300% increase in diameter, resistance

    decreases by app: 7% only.

  • 8/3/2019 Bonding & Earthing (Final)

    41/67

    PLATE ELECTRODE

    In early days only plate electrode were used.

    It was presumed that to get low electrode resistance toearth,surface area should be large as per conventional ohms

    law resistance.

    In some cases efforts were made to cover the entire site

    with plate electrode.

    One solid plate & another annular ring both with same

    radius of 50cm are taken for using as earth electrode.

    Calculation shows that resistance to earth in both the cases

    is 29.2 .

  • 8/3/2019 Bonding & Earthing (Final)

    42/67

    Resistance for strip or horizontal wire electrode is

    measured by RYDERs formula:-

    R = ( / 2 L) [ LN(8L/T)+LN(L/h)- 2

    +(2h/L)-(h2/L2)].

    Where,

    L = Length in Met.(electrode)

    LN=Nominal length(buried conductor)

    h = Depth in Met.

    T = Width in Met.(for strip).

    = 2 x diameter in Met.(for wire)

  • 8/3/2019 Bonding & Earthing (Final)

    43/67

  • 8/3/2019 Bonding & Earthing (Final)

    44/67

    1 MET

    5 CM

    50 CM50 CM

    RESISTANCE TO EARTH OF PLATE ELECTRODE

  • 8/3/2019 Bonding & Earthing (Final)

    45/67

    Similarly, one plate electrode & one strip electrode of

    same volume are taken. But resistance to earth of plate

    electrode is almost three times that of strip electrode.

    The linear dimension of plate electrode is perimeter,

    i.e,4M., where as for strip electrode is 13M.

    Hence, hypothesis is that electrode resistance is

    dominated by length of the electrode buried.

    Thus, it is concluded that plate electrode is inefficient.

  • 8/3/2019 Bonding & Earthing (Final)

    46/67

    1 M

    75 mmX 8 mm X 13.3M

    0.008M3

    REL= 9. 5

    1 M

    P =100 -M

    1 M X 1M X 8 mm

    0.008M3

    REL = 26..2

  • 8/3/2019 Bonding & Earthing (Final)

    47/67

    PARALLEL ELECTRODES

    To obtain low effective earth grid resistance, electrodes are

    connected in parallel. So that the total resistance will be halfof individual resistance.

    This is again due to our extrapolation of conventional ohms

    law concept. But it is true only when the separationdistance between electrodes are adequate.

    For discharging the field effectively, each electrode needs

    exclusive soil below it. If the rods are too close, resistance

    area of one electrode will interfere with that of other and

    expected gain is not realised. As a thumb rule if the rod

    length is L, separation distance shall be 2L.

  • 8/3/2019 Bonding & Earthing (Final)

    48/67

    I

    Over lapping resistance areas of two earth rods

  • 8/3/2019 Bonding & Earthing (Final)

    49/67

    L

    Separation distance

    2L

    I

    SEQUENCE IMPEDANCE TRANSMISSION LINE

  • 8/3/2019 Bonding & Earthing (Final)

    50/67

    SEQUENCE IMPEDANCE TRANSMISSION LINE

    The values can be obtained from any line parameter

    evaluation program considering one circuit or bothcircuit. S/C D/C

    ZPOS(ohm/Km) 0.15 + j 0.41 0.08 + j 0.22

    ZZERO(ohm/Km)0.37 + j 1.29 0.29 + j 1.04Positive sequence impedance of D/C line is almost 0.5

    times of S/C as expected. But Zero sequence impedance

    of D/C line is only about 0.8 times of S/C line.This is

    because positive sequence does not involve earth returnbut zero sequence involves earth return.Only if the separation distance is large enough, they will

    behave like two single circuit line. This is seldom

    achieved in practice.

    RESISTANCE OF EARTH GRID

  • 8/3/2019 Bonding & Earthing (Final)

    51/67

    RESISTANCE OF EARTH GRID

    In EHV switchyard, earthing grid is formed by a mesh

    of horizontal strip electrode & vertical rod electrode.

    The resistance to earth of the entire grid is calculated

    by SVERAK formula :

    RG = C1 +C2 1+(1/C3) .C1 = 1/L; C2 = 1/ 20A ; C3 = 1+ h 20/A.A = Area of earthing grid.

    L = total length of buried conductor includingrod electrode in Meter.

    = resisvity in ohm-meter.

  • 8/3/2019 Bonding & Earthing (Final)

    52/67

    h

    Switchyard earthing grid

    METHODS TO REDUCE ELECTRODE

  • 8/3/2019 Bonding & Earthing (Final)

    53/67

    METHODS TO REDUCE ELECTRODE

    RESISTANCE TO EARTH

    1.To reduce soil resistivity() to a low value.Typical values for different type of soil:

    Soil type Wet Moist Dry Bed rock

    ( in -M) 10 100 1000 10,000Treatment of soil--- such as watering, adding cock,

    wood charcoal, bentonite clay, common salt.

    After treatment there is a gradual decrease in soil

    resistivity, However there will be gradual increase in soil

    resistivity with passage of time as salt is washed away by

    continual water seepage.

  • 8/3/2019 Bonding & Earthing (Final)

    54/67

    200

    160

    120

    80

    40

    0

    025 40353010

    5 15 20

    Resistance,o

    hm-Met

    Months

    Before Treatment

    EFFECT OF ARTIFICIAL TREATMENTEFFECT OF ARTIFICIAL TREATMENT

    After Treatment

    After

    Retreatment

  • 8/3/2019 Bonding & Earthing (Final)

    55/67

    Second method is to increase the length of

    buried conductor to the maximum extent

    possible, the increase in cost has to be borne at

    the beginning budget.

    If parallel electrodes are considered for

    individual earth pits to get low resistance, it

    must be emphasized that unless sufficient

    spacing exists between electrodes,desired

    reduction in earth resistance is not realized in

    practice.

    ELECTRODE SIZING

  • 8/3/2019 Bonding & Earthing (Final)

    56/67

    ELECTRODE SIZING

    The choices for materials & size are only with respect to the

    amount of fault current to be discharged to earth.

    The current density(A/mm2)as per IS-3043.

    Materials Cu Al GI

    0.5 sec rating 290 178 113

    1 sec rating 205 126 80

    Earthing grid for EHV switchyards are designed for 0.5 sec duty

    & for others 1sec duty is selected.

    HUMAN ELEMENT & ELECTRIC SHOCK

  • 8/3/2019 Bonding & Earthing (Final)

    57/67

    HUMAN ELEMENT & ELECTRIC SHOCK

    Electric shock is possible only when the human bodybridges two points of unequal potential.

    This is the reason why a bird can sit comfortably on a220kv

    line conductor without getting electrocuted as the voltagebetween its leg (IR drop) is insignificant.

    Max: tolerable current for human body is 160mA for one

    second.If this limit exceeds, it will result in death due to

    ventricular fibrillation(heart attack)

    Allowable body current IB(Amperes) for two body weights,

  • 8/3/2019 Bonding & Earthing (Final)

    58/67

    as per IEEE Std:-80. is given:

    IB = 0.116/TS for body weights of 50kg.= 0.157 /TS for body weight of 70kg.

    TS =duration of current exposure (fault clearance time).

    TS IB ( 50kg) IB (70kg).0.2sec 259mA 351mA.

    0.5sec 164mA 222mA.

    1.0sec 116mA 157mA.

    Average value for human body resistance under dry

    condition is 8 to 9k-ohms. But for design purpose, assumed

    as 1k-ohm.

  • 8/3/2019 Bonding & Earthing (Final)

    59/67

    GROUND POTENTIAL RISE

    Ground potential rise(GPR) is the voltage to which theearth mat is going to rise when it discharges the

    current.

    If IG is the current discharge to earth & RG is the

    earth grid resistance,

    GPR = IG X RG,

    IG = K x IF ( IF is the fault current).

    IG is always not equal to fault current.

    FAULT IS WITHIN THE SWITCHYARD & TRANSFORMER

  • 8/3/2019 Bonding & Earthing (Final)

    60/67

    CONNECTION IS STAR-DELTA.

    Here, entire fault current is discharged to earth to return to

    source 2. In this case K = 1.

    Source 2Source 1 Switchyard

    IF

    IF

    IG = IF

    Fault within sub-station (star-delta)Fault within sub-station (star-delta)

    FAULT IS WITHIN THE SWITCHYARD & TRANSFORMER IS

  • 8/3/2019 Bonding & Earthing (Final)

    61/67

    CONNECTED IN DELTA- STAR.

    Part of the fault current (IF1) returns to local transformer via metallic

    conductor ( earth mat) and does not contribute to GPR. The other part

    (IF2) is discharged to earth to return to source2 and contributes to GPR.

    In this case, K

  • 8/3/2019 Bonding & Earthing (Final)

    62/67

    CONNECTION IS DELTA-STAR.

    Part of fault current (IF1) returns to transformer at source 1 via earth & contributes

    to GPR. The other part IF2 returns to source2 via earth & contributes to GPR at the

    other switch yard. Where K

  • 8/3/2019 Bonding & Earthing (Final)

    63/67

    STEP & TOUCH POTENTIAL

    Step & touch potential refer to the potential experienced by a

    person standing on a surface when earth mat buried, say

    750mm, below surface has risen to GPR.

    Step potential is the difference in surface potential experiencedby a person bridging a distance of 1 meter with his feet

    without contacting any other grounded object.

    Touch potential is the difference between GPR & the surface

    potential at the point where person is standing, while his hand

    is in contact with grounded structure.

  • 8/3/2019 Bonding & Earthing (Final)

    64/67

    Touch and step potentials

    IG

    RGPF = 2R

    RGPF= R/2

    RR RR Gravel

    VTOUCH

    VTSTEP

    Soil

  • 8/3/2019 Bonding & Earthing (Final)

    65/67

    If resistance offered by each foot is R,

    Then for step potential the resistance is 2Rwhile for touch potential is R/2

    Touch potential is the difference between

    GPR & surface potential while step

    potential is the difference between twosurface potential

  • 8/3/2019 Bonding & Earthing (Final)

    66/67

    EFFECT OF THIN LAYER OF

    CRUSHED ROCK

    In outdoor switchyard,a thin layer of crushed

    rock is spread on the surface.

    The resistivity of gravel ( ) is 2000 -M whilethat of soil is 100 -M. Since of gravel is high ,only a high voltage can force the current throughthe body to cause injuries. The gravel act like

    insulator & throws the electric field generated

    by GPR back to soil.

  • 8/3/2019 Bonding & Earthing (Final)

    67/67