Bond Construction Update Citizens Oversight Committee

18
Bond Construction Update Citizens Oversight Committee Long Beach Community College District August 8, 2011 EDUCATE ENGAGE EMPOWER 1

description

Bond Construction Update Citizens Oversight Committee. Long Beach Community College District August 8, 2011. EDUCATE  ENGAGE  EMPOWER . Agenda. Completed Construction Projects LAC South Walkway Extension - PowerPoint PPT Presentation

Transcript of Bond Construction Update Citizens Oversight Committee

Page 1: Bond Construction Update  Citizens  Oversight Committee

Bond Construction Update

Citizens Oversight Committee

Long Beach Community College District August 8, 2011

EDUCATE ENGAGE EMPOWER 1

Page 2: Bond Construction Update  Citizens  Oversight Committee

Agenda Completed Construction Projects

LAC South Walkway Extension LAC Infrastructure Improvements Project and District Wide –

Energy Efficiency Project

Current Construction Projects LAC Building A – Student Services Retrofit LAC Building I (Bookstore) LAC W Trailers Demo LAC Master Landscape PCC MDAB (Multi-Disciplinary Academic Building) PCC Tech 1 (Sheet Metal)

Upcoming Construction Projects LAC Stadium Parking Lot Lights and Stadium Lights PCC Building CC Retrofit LAC Math Technology Building PCC Building GG LAC Building C Retrofit

Q & A

2

Page 3: Bond Construction Update  Citizens  Oversight Committee

Completed Construction ProjectsLAC South Walkway Extension

Measure E 2008

3

Project complete Palm trees to be replaced August 2011 Continues Master Plan pedestrian corridor

Page 4: Bond Construction Update  Citizens  Oversight Committee

4

LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008

Completed Construction Projects

Total annual estimated savings of 1.5 mil. Kwh Project started Fall 2009; currently hydro seeding all

affected areas(All phases) Majority of existing building HVAC systems to be

upgraded and connected to the Central Plant Buildings B,C,D,E,G, & H are connected

Exterior lighting and controls upgrades All parking lots north of Lew Davis are on new system

New Reclaimed Water tie-ins to irrigation connected New gas lines installed for Buildings B, C, D, E, G, H,

J, M, N, and P New domestic lines installed for Buildings B, C, D, E,

F, G, H, I Trailers, J, K,L, M, N, P Construction completed Summer 2011

Page 5: Bond Construction Update  Citizens  Oversight Committee

Current Construction ProjectsLAC Building A – Student Services Retrofit

Measure E 2008

5

New home for A&R, Counseling, Health Services, Cashier, Transfer Center

Project currently in structural upgrade End of construction anticipated Summer 2012

Page 6: Bond Construction Update  Citizens  Oversight Committee

Current Construction Projects

6

Adds additional 4,000 square feet to existing building Architecture to match LAC Mediterranean Theme Work on framing and utilities underway End of Construction anticipated Fall 2011

LAC Building I - Measure E 2008

Page 7: Bond Construction Update  Citizens  Oversight Committee

Current Construction Projects

7

Grading of lot and paving to be completed this month

Project will address storm run off issues with bio swales

Site to be converted to a parking lot Estimated project completion Summer 2011

LAC W Trailers Demo - Measure E 2008

Page 8: Bond Construction Update  Citizens  Oversight Committee

Current Construction Projects

8

Currently in Design Phase(Finalizing design) Plans to be submitted to DSA in August Quad areas North and South of Bldg. A will bid Fall 2011 Remaining areas designed at 25% Scope includes new hardscape/landscape and pedestrian

pathways

LAC Master Landscape - Measure E 2008

Page 9: Bond Construction Update  Citizens  Oversight Committee

Current Construction ProjectsPCC MDAB

(Multi-Disciplinary Academic Building)Measure E 2008

9

MDAB building remodel project Phase 1 of 2 currently under construction Project currently in demolition and structural reinforcement Phase 1 Project to be completed Summer 2012

Page 10: Bond Construction Update  Citizens  Oversight Committee

Current Construction Projects

10

Construction started Summer 2011 Equipment and utilities currently being installed Projected to be completed before start of Fall semester 2011

PCC Tech 1 (Sheet Metal) - Measure E 2008

Page 11: Bond Construction Update  Citizens  Oversight Committee

11

Stadium Parking Lot Lights and Stadium Lighting Measure E 2008

Upcoming Construction Projects

Stadium parking lot lights and Stadium lighting retrofit Awaiting final DSA approval

Estimated start of construction Fall 2011

Page 12: Bond Construction Update  Citizens  Oversight Committee

Upcoming Construction ProjectsPCC Building CC Retrofit - Measure E 2008

12

Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices

Swing space located on PCC Campus (Bldg. GG) Approved by DSA on 1/27/11. Currently in bid process To be completed concurrently with MDAB project phase 1 Anticipated end of construction Fall 2012

Page 13: Bond Construction Update  Citizens  Oversight Committee

Upcoming Construction Projects

Will house Math and Culinary Arts instructional program as well as Reprographics

Design Build delivery method Currently Requesting Qualifications (RFQ)

Due 8/3 Shortlist and interview 5 respondents (TBD)

Select 3 and request for proposals Anticipated start of construction 2013

LAC Math Technology Building – Measure E 2008

13

Page 14: Bond Construction Update  Citizens  Oversight Committee

Upcoming Construction ProjectsPCC Building GG - Measure E 2008

14

Design Build delivery method Request for Qualifications (RFQ)

Start in September and due late October Building to house Health Services, EOPS, DSPS, Financial Aid, Cashier, A&R, and

Counseling Estimated start of construction December 2013

Page 15: Bond Construction Update  Citizens  Oversight Committee

Upcoming Construction ProjectsLAC Building C Retrofit - Measure E 2008

15

Hired Architect to do design work Currently in schematic phase Work includes modernization of structure, classrooms spaces, and

office areas

Page 16: Bond Construction Update  Citizens  Oversight Committee

l i b

e r

a l

a r t

s

Liberal Arts CampusSite Plan

Page 17: Bond Construction Update  Citizens  Oversight Committee

p a

c i f

i c

c o

a s

t

Pacific Coast CampusSite Plan

Page 18: Bond Construction Update  Citizens  Oversight Committee

QUESTIONS&

ANSWERS

EDUCATE ENGAGE EMPOWER 18