Biobeds Five Arable Farm Case Studies
description
Transcript of Biobeds Five Arable Farm Case Studies
![Page 1: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/1.jpg)
BiobedsFive Arable Farm
Case Studies
Prepared byBill Basford
![Page 2: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/2.jpg)
WelcomeEach study comprises five slides
1. About the farm2. Previous practice and risks to water3. Solution4. Costs and Grants5. Farmer FeedbackMore information are contained in the speakers notes version of these case studies. These can be found here
![Page 3: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/3.jpg)
The five arable farms
1Berkshire – Biobed - 1000Ha
2Suffolk – Biofilter – 1700Ha
3 Norfolk – Biobed – 1200Ha
4Essex - Covered Area – 445Ha
5 Norfolk 2 - Biobed - 282Ha
Click this home button to get back to this page
Click each farm to go direct their start (About the farm) page
Or click page down or return on keyboard to scroll through each case study
![Page 4: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/4.jpg)
About The Farm
• Lambourn, Berkshire• 1,000ha arable, combinable crops• Berthoud Self Propelled 30m, 4,200
litres• Sprayer washed down in field and
yard• Annual Washings
– 2,500 – 3,500l internal washing– 1,500l external washing– 21,000l rainwater
11
Berkshire – Biobed - 1000Ha
![Page 5: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/5.jpg)
Water Risks
• Borehole 75m from site. • Porous stoned area, no apparent
drainage route• Possible accumulations over chalk
subsoil• No specific washings disposal plan• Currently no detections in surface
water• Concern at risks to groundwater
(chalk)
1
![Page 6: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/6.jpg)
Solution
• Bunded fill area created,• Gravity feed to pre biobed
holding tank • Pumped to biobed and then to
irrigation area• Dedicated fill area• Treatment capacity• Approx 30,000l washings
and rainwaterBunded fill area, central drain
1
![Page 7: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/7.jpg)
Costs and Grants• Handling area: £9,000• Biobed: £2,200. • Farm labour:
– Biobed hole– Mixing biomix
• Optional extras:– Filter– Pressure gauge
Gravity flow from fill area
Grant Received £1,800 on biobed
cost only
1
![Page 8: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/8.jpg)
Farmer Feedback• No functional
problems• Check all material
specifications• Peace of mind• Liquid fertiliser
scorch Biobed with central pump
1
![Page 9: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/9.jpg)
About The Farm
• Clare, Suffolk• Arable, combinable
crops, 1700 ha.• John Deere 4,000 L,
24m self propelled• Concrete sloping area
with run off• No known pollution
issues
Original fill area
22
Suffolk – Biofilter – 1700Ha
Sprayer filling area, rainwater harvesting and biofilter supported by Essex & Suffolk Water as demonstration site
![Page 10: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/10.jpg)
Water Risks
• Unidentifiable drainage route • Site close to watercourse leading to
River Stour• Sprayer washed down in field and yard• No specific washings disposal plan• Washouts c. 6-7 per year, 2,800 –
3,500l• No problems with surface or ground
water
2
![Page 11: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/11.jpg)
Solution
• Total water volume for filling area and biobed excessive
• New facility with dedicated chemical storage
New sprayer store/fill area with rainwater harvesting
2
• Fill area in new covered sprayer store eliminating rainfall
• Biofilter now sufficient for washing volumes
• Biofilter drainage pumped to final irrigation area in small wood
![Page 12: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/12.jpg)
Costs and Grants
• New sprayer store: £17,000• Fill area/floor to chemical store:
£10,000 • Biofilter £1,200• Optional extras - auto panel door:
£2700• CSF Grant for biofilter + roofed
area: £5,292
2
![Page 13: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/13.jpg)
Farmer Feedback• Used since 2012, no problems,
meets requirements well• Limits washings/ dirty water
produced• Can wash sprayer down
Fill area bunded below access level, building includes and
biofilter & chemical store
Biofilter within sprayer store/fill area.
Influent/effluent sampled by Essex &
Suffolk Water
2
![Page 14: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/14.jpg)
About The Farm
• East Lexham, Norfolk• Arable and root crops 1200 Ha• 36m trailed sprayer, 6000 litre capacity• Most washing done in field• Annual Washings
– 8-10 per year = 6,000 l max– Extra wash down volumes 350 l/washdown =
3,500 l– Rainwater = 24,000 l– Total > 30,000 l
33 Norfolk – Biobed – 1200Ha
![Page 15: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/15.jpg)
Water Risks
• Original site:– concrete yard sloping to yard drain– traffic crossing area– possible yard run-off across road to
watercourse and an SSSI only 104m away!
• Disposal - No arrangements• Ground and Surface Water risks
and local highway could convey to local culvert
3
![Page 16: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/16.jpg)
Solution• Bunded fill area, dedicated
drainage to tank to biobed and then irrigation area
• 3 pump system• 6000 l emergency sized tank for
fill area pre-biobed; operates at 1,500 l by float switch control.
• Handles 35,000 l per year• Biobed and irrigation area
created in unused farm yard area.
Bunded fill area with cross drain
Biobed with central extract pump
3
![Page 17: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/17.jpg)
Costs and Grants
• Handling Area – minimal spend, new bund area created,
farm labour used. – Ground work equipment, concrete,
electrics and drains £3,804 plus farm labour cost.
• Washings Treatment 7 x 6m biobed– Kit: liner £764, 3 pumps and pipework
£675• Extras: 3 pumps. • Grant from Natural England
3
NB Costs from 2008
![Page 18: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/18.jpg)
Farmer Feedback
• Biobed: sound anti-pollution policy
• 3 pump system regretted, would have preferred gravity flow Early view of irrigation area
3
• No problems, irrigation area has good vegetative growth.
• Investment supported sound management avoiding pollution
![Page 19: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/19.jpg)
About The Farm
• Chelmsford, Essex• Combinable crops 445 ha• Knight self propelled 24m 3000L• Sprayer previously filled in
other yard areas• Annual Washings
– 4-6 pa = 2,000 l maximum– 250 l x 4-6 external washdowns =
1,000-1500 l– Rainwater = 21m3 annually– Total > 24,500 l
44
Essex - Covered Area – 445Ha
2010 Original fill area, nil control of discharges
![Page 20: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/20.jpg)
Water Risks• Unknown drainage route from fill area• Fill site in main yard, sloping• Heavy traffic flow from let buildings• Sprayer washed out and down in field • No specific washings disposal plan• No surface problems with surface
water yet• Looking for ecurity in potential
pollution control
Temporary fill area, bunded to control washings/spills 2011
2012 - 3 x rinsed containers now drain to IBC
4
![Page 21: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/21.jpg)
Solution
• Bunded fill area developed first
• New building w fill area, chemical and sprayer store.
• Water volumes minimised • Liquid directed from fill area
to 7000 l holding tank• Less than 1000 l per season• No biobed/filter• Easy to adapt in future
2012 New facility housing
chemical store and fill area
4
![Page 22: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/22.jpg)
Costs and Grants
• Building, w chemical store, general storage area, fill area, apron & all tanks and drainage, 2 x 7000 l water supply tanks also included, approx £72,000,
• Grant – towards concrete fill area for sprayer and roof directly above this £3,434
4
![Page 23: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/23.jpg)
Farmer Feedback
• Secure building • New site isolated
from yard traffic• Self contained
operation• Meets current rules• Adaptable to future
needs
Chemical store under development in new facility
4
![Page 24: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/24.jpg)
About The Farm
• Cawston, Norfolk• 112 + 170 ha arable, combinable crops farm
part of 1200 ha business• 2 x Sands 24m Self Prop. 1 x 3000 l, 1 x 4000
litre • Sprayers filled in other yard; in-field wash
out• Annual Washings
– 8 Washouts pa = 4,500 l max– 8 x 250 l per exterior = 2,000 l– Rainwater = 24m3– Total = 30,500 l
55 Norfolk 2 - Biobed - 282Ha
![Page 25: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/25.jpg)
Water Risks
• Unidentifiable drainage route • Fill site close to watercourse leading
to River Wensum• Sprayers washed out in field with
some pressure washing in yard areas.
• No washings disposal plan• No problems yet but watercourse
within 25m
5
![Page 26: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/26.jpg)
Solution
• Fill area now 10m from liquid fert. store
• A direct biobed due to– limited space – no power: so gravity flow for
direct biobed and solar power to recharge 2 x 12v batteries for pump
• Enough flow and pressure to meet biobed needs
• Pump delivers biobed drainage to final distribution area (40m2)
Solar panel for recharge 12v system
Drive on direct biobed
5
![Page 27: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/27.jpg)
Costs and Grants
• Direct biobed fill area, £5,800, limited farm labour to dig out biobed pit and produce and install drive over grid
• Grant Received £2,700
Solar panel Drive on grid
5
![Page 28: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/28.jpg)
Farmer Feedback
• System in use from 2010• No problems: system works
well, batteries charge and pump actuation good.
• Peace of mind• May develop new roofed fill
area and chemical store at other farms as a result of good performance with this unit.
• Used within contract farm operations, farm owner also appreciates facility.
Secure battery storage
Drip irrigation on nearby bank
5
![Page 29: Biobeds Five Arable Farm Case Studies](https://reader036.fdocuments.us/reader036/viewer/2022062423/568143a5550346895db028d8/html5/thumbnails/29.jpg)
The End
1Berkshire – Biobed - 1000Ha
2Suffolk – Biofilter – 1700Ha
3Norfolk – Biobed – 122100Ha
4Essex - Covered Area – 445Ha
5 Norfolk 2 - Biobed - 282HaMore information is contained in the speakers notes version of these case studies. These can be found here