Bill of Quantities
-
Upload
co-kho-martin -
Category
Documents
-
view
8 -
download
1
description
Transcript of Bill of Quantities
-
Republic of the Philippines DEPARTMENT OF TRANSPORTATION AND COMMUNICATIONS
Procurement of
INFRASTRUCTURE PROJECTS
CONSTRUCTION OF EXTERNAL WATER SUPPLY SYSTEM
(New Bohol Airport Construction and Sustainable Environment Protection Project)
Section VIII Bill of Quantities
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM DESCRIPTION TOTAL PRICE
SUMMARY
PART I GENERAL REQUIREMENTS
A. Mobilization and Demobilization
B.Provide and maintain one ( 1) rented service vehicle for the use of the Resident Engineer
C. Provide and Install three (3) Project Signboards and one (1) COA Signboard
D. Maintenance of Resident Engineer's Office including Engineer's Requirements
Total " Part I "
PART II PIPELINES AND RELATED CIVIL WORKS
A. Pipelines
B. Valves
C. Assemblies
D. Pavement Demolition & Surface Restoration
E. Over-Excavation for Pipelines
F. Miscellaneous
Total " Part II "
PART III CIVIL WORKS
A. Pipe Crossings
B. Structures
Total " Part III"
PART IV ELECTRO-MECHANICAL WORKS
A Pumping Equipment
B. Chlorination Facilities
C. Electrical Works
Total " Part IV"
TOTAL AMOUNT IN FIGURES PHP_______________
TOTAL AMOUNT IN WORDS __________________________________________________
Signature and Official Stamp of Bidder: ____________________________________ Date: ________________
SECTION VIII- BILL OF QUANTITIES
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
PART I
LUMP SUM and UNIT BID ITEMS
for
GENERAL REQUIREMENTS
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM UNIT QTY. UNIT PRICE TOTAL PRICE
PART I
A. Temporary site facilities, project organization and resource movement LS 1
B.MOS. 8
C. LS 1
D. LS 1
TOTAL AMOUNT IN FIGURES PHP _______________
Signature and Official Stamp of Bidder: ____________________________________ Date: _____________________
GENERAL REQUIREMENTS
Provide and maintain one ( 1) rented service vehicle for the use of the Resident Engineer.
DESCRIPTION
SECTION VIII - BILL OF QUANTITIES
Maintenance of Resident Engineer's Office including Engineer's Requirements
Provide and Install three (3) Project Signboards and one (1) COA Signboard
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
PART II
UNIT PRICE BID ITEMS
for
PIPELINES AND RELATED CIVIL WORKS
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM UNIT QTY. UNIT PRICE TOTAL PRICE
A.
Note 1 : Quantity - Length in meters, excluding length of
valves, assemblies and fittings under Items B and C.Note 2 : Concrete thrust blocks not required for welded steel
pipes.
Note 3 : Warning and detection tapes required for all pipes.
Note 4 : The unit cost of pipelines includes the cost of providing barricades, warning lights and steel plates.
A.1 TRANSMISSION PIPELINES
A.1.1 150 mm dia., HDPE-PE 100 SDR 13.6(PN 12.5) LM 8,796
ST-A TOTAL AMOUNT IN FIGURES PHP _______________
Signature and Official Stamp of Bidder: ____________________________________ Date: _____________________
SECTION VIII- BILL OF QUANTITIES
PIPELINES - Furnish and install pipes complete includingjoints, fittings and warning and detection tapes, performexcavation in any type of soil (excluding rock and excavationexceeding 1.5 m deep measured from existing ground level)dewatering, backfilling using suitable materials from trenchexcavation, disposal of surplus materials where directed, thrustblock, hydrotesting and disinfection as per Specifications andDrawings.
DESCRIPTION
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM UNIT QTY. UNIT PRICE TOTAL PRICE
B.
B.1 Gate Valves on Proposed Lines
B.1.1 150 mm SETS 2
ST-B TOTAL AMOUNT IN FIGURES PHP _______________
Signature and Official Stamp of Bidder: ____________________________________ Date: __________________
VALVES - Furnish and install gate or butterfly valves complete with valve boxes; perform all necessary excavation and construct concrete base as per Specifications and Drawings.
DESCRIPTION
SECTION VIII - BILL OF QUANTITIES
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM UNIT QTY. UNIT PRICE TOTAL PRICE
C.
C.1
C.1.1 25 mm diameter SETS 16
C.2 Blow - off - Valve Assemblies
C.2.1 75 mm diameter SETS 1
C.3 Fire Hydrant Assemblies
C.3.1 100 mm diameter Residential type SETS 1
ST-C TOTAL AMOUNT IN FIGURES PHP _______________
Signature and Official Stamp of Bidder: ____________________________________Date: ________________
ASSEMBLIES - Furnish and install the items hereunderdescribed with all necessary joints and appurtenances and performexcavation and concrete construction including thrust blocks as per Specifications and Drawings.
Air Vacuum / Air Release Valves - Furnish and instal air vacuum/ air relase valve laterals, vandal proof steel casing, thrust blocksand fittings as specified and as shown on the Drawings.
DESCRIPTION
SECTION VIII - BILL OF QUANTITIES
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM UNIT QTY. UNIT PRICE TOTAL PRICE
D.
D.1
Note 1: Payment will be based on the maximum allowable trench width as tabulated under standard drawing CT-18.
Note 2: No payment shall be made for asphalt pavement if its thickness is less than 50mm.
Note 3: Cost of cutting/ sawing the pavement shall be included in the unit bid for pavement demolition.
D.1.1 Asphalt Pavement ( 50mm minimum thickness) SQ.M. 5
D.1.2 Concrete Pavement ( roads, sidewalks & driveways) :
D.1.2.1 Equal or less than 75 mm ( 3") thick pavement SQ.M. 100
D.1.2.2 Between 75 mm (3") to 150 mm ( 6") thick pavement SQ.M. 20
D.1.2.3 More than 150 mm ( 6") thick pavement SQ.M. 30
D.1.2.4 Concrete curb and Gutter LM 10
D.2
`
Note 1 : Cost for the supply and preparation of the base course when required shall be included in the bid unit price.
Note 2 : Payment will be based on the volume of concrete or asphalt pavement restored considering the maximum allowable trench width as tabulated under standard drawings CT-18.
D.2.1 Asphalt Pavement including base course CM 10
D.2.2 Concrete Pavement including base course CM 30
D.2.3 Concrete curb and Gutter CM 10
ST-D TOTAL AMOUNT IN FIGURES PHP _________________
Signature and Official Stamp of Bidder: ____________________________________ Date: _____________________
Surface Restoration - Furnish materials, labor and equipment necessary to construct pavement and restore surface as specified and as shown on the Drawings.
PAVEMENT DEMOLITION AND SURFACE RESTORATION
Pavement Demolition - Furnish, labor, tools and equipment necessary to demolish pavement including the hauling of these discard materials to appropriate dump site. Locating appropriate dump site shall be the contractor's responsibility.
SECTION VIII - BILL OF QUANTITIES
DESCRIPTION
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM UNIT QTY. UNIT PRICE TOTAL PRICE
E.
E.1 Over 1.5 to 2.0 m CU.M. 10
E.2 Over 2.0 to 2.5 m CU.M. 10
E.3 Over 2.5 m CU.M. 10
ST-E TOTAL AMOUNT IN FIGURES PHP _______________
Signature and Official Stamp of Bidder: ____________________________________ Date: _____________________
OVER - EXCAVATION FOR PIPELINES - Over excavation for pipelines when ordered by the Engineer applies when the measured cover from top of pipe to existing ground surface exceeds 1.5 meters
SECTION VIII - BILL OF QUANTITIES
DESCRIPTION
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM UNIT QTY. UNIT PRICE TOTAL PRICE
F.
F.1
CU.M. 2250
F.2 Suitable bedding/backfill from borrow CU.M. 10
F.3
CU.M. 10
F.4CU.M. 10
F.5CU.M. 10
F.6 CU.M. 765
ST-F TOTAL AMOUNT IN FIGURES PHP _______________
Signature and Official Stamp of Bidder: ____________________________________ Date: _____________________
Reinforced concrete encasement to be furnished and installed when ordered by the Engineer.
Concrete Blocks / Concrete Anchor block to be furnished and installed when ordered by the Engineer
SECTION VIII - BILL OF QUANTITIES
DESCRIPTION
Rock Excavation
MISCELLANEOUS
Sand Bedding / backfill from borrow area to be furnished and installed when ordered by the Engineer.
Crushed rock bedding to be furnished and installed when ordered by the Engineer.
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
PART III
LUMP SUM BID ITEMS
for
CIVIL WORKS
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM UNIT QTY. UNIT PRICE TOTAL PRICE
A.
A.1 Mariveles River Crossing LS 1A.2 Culvert Crossing No.1 LS 1A.3 Culvert Crossing No.2 LS 1A.4 Culvert Crossing No.3 LS 1A.5 Culvert Crossing No.4 LS 1A.6 Culvert Crossing No.5 LS 1A.7 Culvert Crossing No.6 LS 1A.8 Culvert Crossing No.7 LS 1A.9 Culvert Crossing No.8 LS 1A.10 Culvert Crossing No.9 LS 1A.11 Culvert Crossing No.10 LS 1
ST-A TOTAL AMOUNT IN FIGURES PHP _______________
Signature and Official Stamp of Bidder: ____________________________________ Date: _____________________
PIPE CROSSINGS - Furnish materials, labor, tools, supplies and equipment necessary to construct the river crossing and culvert crossings with all necessary pipes, thrust blocks, supports, fittings, couplings, anchorage and all other works including hydrotesting and disinfecting as specified and as shown on the Drawings.
SECTION VIII - BILL OF QUANTITIES
DESCRIPTION
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM UNIT QTY. UNIT PRICE TOTAL PRICE
B.
B.1 2- 75 cu.m. Reinforced Concrete Ground Receiving Tankincluding Pump House, Generator House, Chlorine House andGuard House LS 1
B.2 2 - 75 cu.m. Reinforced Concrete Ground Relay Tank LS 1
`
ST-B TOTAL AMOUNT IN FIGURES PHP _______________
Signature and Official Stamp of Bidder: ____________________________________ Date: _____________________
DESCRIPTION
STRUCTURES - Furnish materials, labor, plant, tools, supplies and equipment to construct and complete the structure including site development works, fencing & gate , yard pipeworks, valves and fittings, waterproofing, excavation, backfill and all necessary works including soil investigations at reservoir sites as specified and as shown on the drawings.
SECTION VIII - BILL OF QUANTITIES
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
PART IV
LUMP SUM BID ITEMS
for
ELECTRO-MECHANICAL EQUIPMENT
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM UNIT QTY. UNIT PRICE TOTAL PRICE
PART III ELECTRO-MECHANICAL WORKS
A.
A.1 Receiving Tank Pumping Equipment LS 1
`
ST-A TOTAL AMOUNT IN FIGURES PHP _______________
Signature and Official Stamp of Bidder: ____________________________________ Date: _____________________
DESCRIPTION
Pumping Equipment - Furnishing installation, testing and commissioning of mechanical equipment such as centrifugal pumps and electric motor set, complete with suction pipes, discharge pipes, flowmeter, gauges, valves, check valves, fittings and all appurtenances as specified and as shown on the Drawings
SECTION VIII - BILL OF QUANTITIES
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM UNIT QTY. UNIT PRICE TOTAL PRICE
B.
B.1 Receiving Tank Chlorination facilities 1 LS
`
ST-B TOTAL AMOUNT IN FIGURES PHP _______________
Signature and Official Stamp of Bidder: ____________________________________ Date: _____________________
SECTION VIII - BILL OF QUANTITIES
DESCRIPTION
PROPOSED CHLORINE FACILITIES - Furnishing installation, testing and commissioning of hypo-chlorination facilities complete with mixer-stirrer, mixing tank, piping and all other appurtenances as specified and as shown on the Drawings.
VIII -1
-
NEW BOHOL AIRPORT CONSTRUCTION AND SUSTAINABLE ENVIRONMENT PROTECTION PROJECT(Construction of External Water Supply System)
ITEM UNIT QTY. UNIT PRICE TOTAL PRICE
C.
C.1 Receiving Tank Electrical Works LS 1
C.2
C.2.1 75 KVA , Three Phase, 230V, 60Hz., Standby Generator Unit, Outdoor type, with Enclosure complete with standard safety features such as but not limited to ff; MCCB protection, Battery Charger, Muffler and extension, skid type daytank, Fuel transfer pump, piping system, and pump controller LS 1
C.3 Underground Distribution LS 1
C.4 Relay Tank Electrical Works LS 1
`
ST-C TOTAL AMOUNT IN FIGURES PHP _______________
Signature and Official Stamp of Bidder: ____________________________________ Date: _____________________
DESCRIPTION
ELECTRICAL -Furnishing, installation, testing and commissioning of interior and exterior lighting, power and grounding system including dry type transformers, panels, protective devices, controls, wires, conduits, transformer switch, concrete pedestal, power transformer and other appurtenances as specified and as shown on the Drawings.
SECTION VIII - BILL OF QUANTITIES
Generator Sets - Furnishing, installation, testing and commissioning of diesel generator sets complete with diesel engine and alternator, instrument panels, fuel oil day storage tank and piping, automatic transfer switch, genset accessories, generator feeders and conduits and all appurtenances as specified.
VIII -1