7/28/2019 Bibiyana 03 Addendum 03 With Attachment
1/28
Addendum No. 03Memo No. 3022 -BPDB (Sectt)/Dev- 187/2007 date : 15 - 11 - 11
Clarification/ amendment of the Tender document for Construction of Bibiyana300 -450 MWGas BasedCombined Cycle Power Plant
Clarification/ amendment of theTender document for Construction of Bibiyana300 - 450 MWGas Based
Combined Cycle Power Plant Project [Tender invitation no. 2100 -BPDB (Sectt)/Dev- 187/2007 date : 14-07-11; Addendum no. 1 ref: 2302-BPDB (Sectt)/Dev- 187/2007 date 08-08-11; Addendum no. 02 ref: 2800-
BPDB (Sectt)/Dev- 187/2007 date 10-10-11] is hereby issued as mentioned below:
Sl.
no.
Subject of
clarification/
amendment
TD
Page
no.
Clause no. Mentioned in Tender
document/ Addendum
Clarification/ Amendment of
Tender document
1. Eligibility ofTenderers/Experience
of Project
Implementation
2, 12 Tendernotice sl. no.
10;
Clause 5.1of ITT, Vol.
1;
Addendum
no. 02, sl.
no. 9
The Tenderer shall have the
experience of supply,erection, installation, testing
and commissioning on
Turnkey basis of minimum2(two) Power Plant having
each minimum 250 MWcapacity during last 15
(fifteen) years. One of these
projects have to be outside
the tenderers country andone of these projects have to
be combined cycle plant. In
support of his experiences,
the Tenderer shall submitwith his Tender for all work
performed by him, detailedevidence that he himself and
/ or Lead partner of JVCAhave carried out the design,
manufacture, supply,
construction, erection,
testing, commissioning and
put into commercialoperation of power planthaving minimum capacity of
250 MW. It is to be notedthat Subcontractors'
The Tenderer shall have the
experience of supply, erection,installation, testing and
commissioning on Turnkey basis of
minimum 2(two) Power Plant havingeach minimum 250 MW capacity (For
Combined cycle plant, single blockcapacity having configuration 1:1:1 or
2:2:1. For Non combined cycle plant,
total capacity of maximum 02 no. of
units) during last 15 (fifteen) years.One of these projects have to be
outside the tenderers country and one
of these projects have to be combined
cycle plant. In support of hisexperiences, the Tenderer shall
submit with his Tender for all workperformed by him, detailed evidence
that he himself and / or Lead partnerof JVCA have carried out the design,
manufacture, supply, construction,
erection, testing, commissioning and
put into commercial operation of
power plant having minimumcapacity of 250 MW. It is to be notedthat if the tenderer himself/ lead
partner of JVCA were not anindividual contractor or JVCA lead
evsjv`k we`yr Dbqb evWBANGLADESH POWER DEVELOPMENT BOARD
Office t
Central Secretariate,BPDB, Dhaka.
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
2/28
Sl.
no.
Subject of
clarification/
amendment
TD
Page
no.
Clause no. Mentioned in Tender
document/ Addendum
Clarification/ Amendment of
Tender document
The Tenderer shall include at leasttwo (02) certificates from the end
users on two (2) years satisfactoryperformance of the plants having
minimum 250 MW capacity PowerPlants [One of these projects have to
be outside the tenderers country andone of these projects have to be
combined cycle plant] which weredesigned, supplied, constructed, tested
& commissioned by the Tenderer to
establish the Tenderer's minimumrequired experience to Tender. The
certificates shall mention the name of
power plant, number, capacity and
commissioning date of the power
plant (make, model) supplied by theTenderer; issue date, name and
address (Telephone/Fax/e-mail) of theend user duly signed in the official
pad. Without such certificates orwhere the certificates are un-
satisfactory to BPDB, the Tender shall
be considered technically non-responsive.
These certificates must be notarizedand have authentication from the
Chamber of Commerce of theTenderer's country or the
Embassy/High commission of the endusers country situated in Dhaka. In
absence of that, authentication isrequired from the Embassy/High
Commission of tenderers country inDhaka.
The Contractor shall arrange site visit
of 03 (three) personnel of the
Employer to the Premises of thePower Plants as mentioned in
Experience Certificates. All living,
accommodation, food, transport
expenses of the personnel during the
period of visit including air-fares,incidental expenses, medical
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
3/28
Sl.
no.
Subject of
clarification/
amendment
TD
Page
no.
Clause no. Mentioned in Tender
document/ Addendum
Clarification/ Amendment of
Tender document
3. FinancialQualification
13 Clause 5.2of ITT,
Vol. 1
--- The following is added in Clause 5.2of ITT, Vol. 1:
The tenderer must have theexperience of completion of a Power
plant Project through ECA/ Bankfinancing of minimum 150 million
USD during last 15 years. Certificate/authenticated document shall have to
be submitted in this regard. Withoutsuch Certificate/ authenticated
document or where the Certificate/
authenticated document are un-satisfactory to BPDB, the Tender
shall be considered technically non-
responsive. This certificate must be
notarized and have authentication
from the Chamber of Commerce ofthe Tenderer's country or the
Embassy/High commission of thecertificate issuing authoritys country
situated in Dhaka. In absence of that,authentication is required from the
Embassy/High Commission of
tenderers country in Dhaka.
4. FinancialProposal
19 Volume 1of 2 ITT
Clause No
14.0
----- The following is added:Grace Period will be minimum 03
years, Repayment Period (excluding
Grace period) will be minimum 10
years, Repayment shall be made half-
yearly.5. LTSA 19 Volume 1
of 2 ITTClause No
14 (vi)
The Tenderer shall, in
addition to essential spareparts and consumables for
warrantee period also submit
a price list of spare parts and
services with OEM part no.for LTSA period (next 4
years after warrantee period)
which reflects the OEM'sguidelines and Tenderer'sexperience in the operation
and maintenance of the typeof equipment proposed. ForLTSA period also the
Contractor shall supply all
The tenderer have to provide a
price quotation from GT OriginalEquipment Manufacturer with
confirmation that they agree to
provide LTSA for GT for 5 years
after the warranty period within theterms and condition of the
quotation, which will be attached
along with the tender. BPDB willsign a separate contract with OEMfor GT on the basis of quotation
related LTSA.
Without such confirmed quotation
the tender will be rejected. It is to
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
4/28
Sl.
no.
Subject of
clarification/
amendment
TD
Page
no.
Clause no. Mentioned in Tender
document/ Addendum
Clarification/ Amendment of
Tender document
6. Localtraining and
Overseastraining
during LTSAperiod
- - - The following is included:
LTSA provider personnel shall beresponsible for providing instruction
and guidance to BPDB personnel inthe operation and maintenance of the
equipment. During LTSA period, itshall also be the responsibility of the
LTSA provider to train up (by on jobtraining) BPDB personnel adequately
and properly in a planned manner so
that they can take over theresponsibility of operation and
inspection/ maintenance of the plant
and equipment independently. As a
part of on job training, BPDB
personnel shall have to be engaged inthe schedule/ unscheduled
maintenance of the equipment so thatthey could get a clear idea about
inspection/ maintenance of theequipment.
As mentioned below, LTSAprovider will provide overseas
training to BPDB personnel and they(BPDB personnel) will witness
manufacturing process and tests ofthe materials and spares (to be
supplied under LTSA) atmanufacturers' works:
For HGPI materials/ spares: 03person, 30 person-days (each person
10 days excluding travel time);For MI materials/ spares : 06 person,
60 person-days (each person 10 daysexcluding travel time).
09(nine) round trip air fares fromDhaka, Bangladesh to the
Manufacturer's factory, meals,
lodging costs transport expenses of
the BPDB personnel during the period
of training including incidentalexpenses or medical expenses or
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
5/28
Sl.
no.
Subject of
clarification/
amendment
TD
Page
no.
Clause no. Mentioned in Tender
document/ Addendum
Clarification/ Amendment of
Tender document
7. ServiceEngineers
afterwarranty
period;Maintenance
during LTSAperiod
116 ofVo. 1;
20 ofVol. 2
Part A
Clause 27.1of PCC,
Vol. 1;Clause 2.21
of Vol. 2
Part A
The Contractor shall provideOne (1) Competent
Operation Engineer who willbe in overall in charge of the
Plant, one (1) Engineer forElectrical Maintenance &
I&C, one (1) EngineerMechanical Maintenance
(BOP), one (1) Engineer GasTurbine Maintenance and
One (1) Engineers for Steam
Turbine & HRSGMaintenance during 4 years
LTSA period -----------
LTSA provider shall provide One (1)Engineer for GT and One (1)
Engineer for C&I during 5 yearsLTSA period -----------
8. Evaluation 21 Clause 25.0of ITT,
Vol. 1
------- Amended as mentioned in attachment01 of this addendum.
9. Terms of
Payment
92-95 Clause
61.03 and61.04 ofGeneral
conditions,
Vol. 1;
Addendumno. 02, sl.
no. 6 and 7
-------- The following is added:
If credit amount is 85% or higher ofthe EPC contract amount (for bothForeign currency and Local
currency), advance payment of
foreign currency will be 15% instead
of 10%. Progress payment (paymentagainst receiving cum damage report/
monthly invoice) percentage offoreign currency will be reduced
accordingly.
Credit repayment shall be made halfyearly.
10. BangladeshIncome taxand VAT for
Incomeearned in
Bangladesh
88 Clause51.01 (a) ofGeneral
conditions,Vol. 1;
---------- For Tendererscredit financing, IncomeTax, VAT and all other taxes
as mentioned above will beapplicable at the time of
deferred payment on theprincipal and interest
amount. -------------
---------- For Tenderers creditfinancing, Income Tax, VAT and allother taxes as mentioned above will
be applicable at the time of deferredpayment on the principal amount. ---
11. ExhaustSystem
49 Clause
4.3.2.10 of
Vol. 2, Part
A
Gas turbine unit shall be
equipped with an exhaust
duct and a suitable by pass
stack (not less than 40 m) ---
Gas turbine unit shall be equipped
with an exhaust duct and a suitable by
pass stack (not less than 50 m) --------
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
6/28
Sl.
no.
Subject of
clarification/
amendment
TD
Page
no.
Clause no. Mentioned in Tender
document/ Addendum
Clarification/ Amendment of
Tender document
work will not be required and pricefor this item will be deleted from the
contract amount. But this price will beconsidered during evaluation.
Revised Bill of Materials/Quantities& price schedules are enclosed asattachment 02 of this addendum.
All other terms and condition shall remain unchanged.Signed.
dt. 15.11.1011
(Md. Azizul Islam)Secretary,
Bangladesh Power Development Board
WAPDA Building (1st
Floor)
Motijheel C/Area, Dhaka-1000,
Bangladesh
Fax : 880-2-9564765
Memo No. 3022-BPDB (Sectt)/Dev- 187/2007 date : 15 - 11- 11Copy for information & necessary action to:
1. Secretary, Power Division, Ministry of Power, Energy and Mineral Resources, Dhaka.2. DG, IMED, Planning commission, CPTU, Dhaka. He is requested to take necessary action for posting
addendum No. 03 in the CPTU website.
3. Member, Generation/ P&D/Finance, BPDB, Dhaka.4. Chief Engineer, Generation/ P&D/PSC, BPDB, Dhaka.5. Controller (Finance & Accounts), BPDB, Dhaka.
6. P.S to Hon'ble Advisor to Prime Minister for Power, Energy and Mineral Resources, Dhaka.7. PS to Hon'ble State Minister, Ministry of Power, Energy and Mineral Resources, Dhaka.8. Project Director, Bibiyana 300-450 MW Combined Cycle Power Plant Project, BPDB.9. C.S.O to Chairman, BPDB, Dhaka.10.Director, Design & Inspection-1/ Design & Inspection-2/System Planning/Program/ Finance/ Contract
& C.A, BPDB, Dhaka.
11.Director, Purchase, BPDB, Dhaka. He is requested to send addendum No. 03 to those, who purchasedtender document and to enclose addendum No. 03 with the tender document before selling.
12.Senior System Analyst, BPDB Dhaka. He is requested to post the addendum No. 03 in BPDB website.
13.M/S ___________________________14.Office copy.
Signed.
dt. 15/11/11
Sr. Section Officer (Dev)
BPDB, Dhaka.
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
7/28
Attachment 01 of addendum no. 03 (page no. 7 to 11)
EVALUATION
The Technical Proposals submitted by the Tenderers shall be opened first in presence of the Tenderers. At
the same time the envelope marked "Financial Proposal" submitted by the respective Tenderers will be
noted for record and kept unopened in proper custody of the Secretary, Bangladesh Power Development
Board, until the Technical Proposals are completely evaluated. Considering all the aspects ( in connection
with specified work) offered by each Tenderer as well as the data and information submitted and on proper
judgement of the capability of individual Tenderers, technically qualified proposals shall be selected
amongst them and listed. The technical qualifications and overall capability of the Tenderer for carrying out
the work as specified as well as the specifications of the equipment/materials offered and fulfilment of thekey dates/data shall be the essence for selection of technically qualified Tenderers.
In the process of evaluation, tender may be considered as responsive only if it is submitted in compliancewith the mandatory requirements set out in the tender document, without material deviation or reservation.
A material deviation or reservation is one -a) Which affects in any substantial way the scope, quality or performance of the works.b) Which limits in any substantial way, inconsistent with the tender document, the procuring entitys
rights or the tenders obligations under the contract; orc) Whose rectification would affect unfairly the competitive position of other tenderers presenting
responsive tenders.
Total time from Contract Effective Date to Completion of ICO of the unit:
Shall not exceed 660 Days for Simple Cycle OperationShall not exceed 900 Days for Combined Cycle Operation (Including 660 days for SC operation)
Guarantee data shall have to be furnished with technical proposal as stated in guarantee schedule-A, vol. 2of 2 of tender document. The Tender shall be rejected if the Tenderers do not comply with thisrequirement.
Data given by the Tenderer which significantly affect the result of evaluation shall be included in theContract as requirements tobe guaranteed and will be subject to verification at the cost of the Tendererand to the satisfaction of the BOARD.
No proposal which offers less than 300 MW capacity (Net output at site condition) of Power Plant asspecified in Technical Requirements will be accepted. Excess Net output more than 450 MW at Siteconditions shall not be considered for evaluation of per KW cost stated hereunder.
The "Financial Proposals" of those eligible Tenderers whose offers qualify in the "Technical Proposal" willb d i f th T d if d t t b tifi d l t If "T h i l P l"
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
8/28
Financial Analysis:
For the purpose of evaluation all costs shall be based on equivalent Bangladeshi Taka as of the date of theTender closing.
The evaluation of the proposal would be done by Financial analysis method taking into account thefollowing:
A. Tender Price (excluding LTSA cost)B. Initial costC. Debt servicing costD. Fuel costE. O & M cost.
Initial cost of the proposals shall be determined by bringing the scope of works of all the proposals to acommon basis (Tender price plus average price of omitted equipment/ materials quoted by otherresponsive Tenderers).
Debt servicing cost shall be calculated by considering Non credit amount, Credit amount, Annual interestrate, Re-payment Period, Grace period and others with a view to comparing different nature of CreditProposal to a equivalent status by applying Net Present Value @ 12 % discount factor.
Example of Financial analysis for Debt servicing cost
In this example, Credit portion is 80% of contract value (for both FC and LC), Non Credit portion is 20% ofcontract value (for both FC and LC), Annual interest rate i%, Grace period 03 years, Repayment period 10years are considered.
Initial cost = m Bangladeshi Taka (BTk.)Installment payment duration = 06 months (half yearly)Discount rate = 12%Po = Total Net output at generator Step-up transformer HT terminals at Site Condition in kW
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
9/28
TotalNet present value of Repayment amount (NT) will be calculated as shown in Table below:
Slno.
Principal amount(In Eq. BTk.)
Interest(In Eq. BTk.)
Repaymentamount
(In Eq. BTk.)
Net present value ofRepayment amount
(In Eq. BTk.)
0 F0 = Initial payments
for loan effectiveness,such as commitmentfee, risk premium etc.
- R0 = F0 N0 = R0
Grace period payment
1 P1 =0 I1 = (0.8m x i%)/ 2 R1 = I1 N1 = R1/ (1.12)0.5
2 P2 =0 I2 = (0.8m x i%)/ 2 R2 = I2 N2 = R2/ (1.12)1
3 P3 =0 I3 = (0.8m x i%)/ 2 R3 = I3 N3 = R3/ (1.12)1.5
4 P4 =0 I4 = (0.8m x i%)/ 2 R4 = I4 N4 = R4/ (1.12)2
5 P5 =0 I5 = (0.8m x i%)/ 2 R5 = I5 N5 = R5/ (1.12)2.5
6 P6 =0 I6 = (0.8m x i%)/ 2 R6 = I6 N6 = R6/ (1.12)3
Repayment periodpayment
7 P7 = 0.8 m/ 20 I7 = (0.8m x i%)/ 2 R7 = P7 +I7 N7 = R7/ (1.12)3.5
8 P8 =0.8 m/ 20 I8 = [{(19x0.8m)/20} x i%]/ 2 R8 = P8 +I8 N8 = R8/ (1.12)4
9 P9 =0.8 m/ 20 I9 = [{(18x0.8m)/20} x i%]/ 2 R9 = P9 +I9 N9 = R9/ (1.12)4.5
10 P10 =0.8 m/ 20 I10 = [{(17x0.8m)/20} x i%]/ 2 R10 = P10 +I10 N10 = R10/ (1.12)5
11 P11 =0.8 m/ 20 I11 = [{(16x0.8m)/20} x i%]/ 2 R11 = P11 +I11 N11 = R11/ (1.12)5.5
12 P12 =0.8 m/ 20 I12 = [{(15x0.8m)/20} x i%]/ 2 R12 = P12 +I12 N12 = R12/ (1.12)6
13 P13 =0.8 m/ 20 I13 = [{(14x0.8m)/20} x i%]/ 2 R13 = P13 +I13 N13 = R13/ (1.12)6.5
14 P14 =0.8 m/ 20 I14 = [{(13x0.8m)/20} x i%]/ 2 R14 = P14 +I14 N14 = R14/ (1.12)
7
15 P15 =0.8 m/ 20 I15 = [{(12x0.8m)/20} x i%]/ 2 R15 = P15 +I15 N15 = R15/ (1.12)7.5
16 P16 =0.8 m/ 20 I16 = [{(11x0.8m)/20} x i%]/ 2 R16 = P16 +I16 N16 = R16/ (1.12)8
17 P17 =0.8 m/ 20 I17 = [{(10x0.8m)/20} x i%]/ 2 R17 = P17 +I17 N17 = R17/ (1.12)8.5
18 P18 =0.8 m/ 20 I18 = [{(09x0.8m)/20} x i%]/ 2 R18 = P18 +I18 N18 = R18/ (1.12)9
19 P19 =0.8 m/ 20 I19 = [{(08x0.8m)/20} x i%]/ 2 R19 = P19 +I19 N19 = R19/ (1.12)9.5
20 P20 =0.8 m/ 20 I20 = [{(07x0.8m)/20} x i%]/ 2 R20 = P20 +I20 N20 = R20/ (1.12)10
21 P21 =0.8 m/ 20 I21 = [{(06x0.8m)/20} x i%]/ 2 R21 = P21 +I21 N21 = R21/ (1.12)10.5
22 P22 =0.8 m/ 20 I22 = [{(05x0.8m)/20} x i%]/ 2 R22 = P22 +I22 N22 = R22/ (1.12)11
23 P23 =0.8 m/ 20 I23 = [{(04x0.8m)/20} x i%]/ 2 R23 = P23 +I23 N23 = R23/ (1.12)
11.5
24 P24 =0.8 m/ 20 I24 = [{(03x0.8m)/20} x i%]/ 2 R24 = P24 +I24 N24 = R24/ (1.12)12
25 P25 =0.8 m/ 20 I25 = [{(02x0.8m)/20} x i%]/ 2 R25 = P25 +I25 N25 = R25/ (1.12)12.5
26 P26 =0.8 m/ 20 I26 = {(0.8m/20) x i%}/ 2 R26 = P26 +I26 N26 = R26/ (1.12)13
TotalNet presentvalue ofRepaymentamount (NT) :
26
Nn =n=0
TotalNet present value of Repayment amount (NT) will be added with non credit amount to find Total Debtservicing cost (DT). Hence, DT = NT + 0.2m
Per unit Debt servicing cost (T1) in BTk. per kW will be found by dividing DT by net plant capacity Po in kWat site condition. Hence, T1 = DT / Po .
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
10/28
Basis of Financial analysis for Fuel cost and O&M Cost
For the purpose of Financial analysis, the following data would be considered:
a. Plant life 20 years but for evaluation purpose 10 years O&M and fuel cost will be
consideredb. Plant will operate on natural gasc. Considered plant factor = 80%d. Cost of natural gas, Tk per Nm3 = Tk 5.90 per Nm3
(Fuel Calorific Value (LHV) of Gas fc = 35,350 kJ/Nm3)
e. Heat rate to be used for weighted average of50%, 75% and 100 % load under SiteConditionSo H = H100% x 0.5 + H75% x 0.3 + H50% x 0.2 KJ per Kwh
f. Operation and Maintenance cost - Tk. 0.20 per kWhg. Discount rate on capital investment - 12%
Example of Financial Analysis for Fuel cost and O&M Cost:
Po = Total Net output at generator Step-up transformer HT terminals (Delivery point) at SiteCondition in kW
EP0 = Annual delivered energy at Delivery point in Kwh= P0 x 24 x 365 x 0.8 Kwh
H = Average weighted heat rate of generating unit at Delivery point(100%, 75%and 50% load at Site Condition) in KJ / kWH
= H100% x 0.5 + H75% x 0.3 + H50% x 0.2 KJ per Kwh
Hc = Annual heat consumption at Delivery point= H x EP0 in KJ
Fuel Calorific Value (LHV) of Gas fc = 35,350 kJ/Nm3
Annual fuel consumption =Hc/ fc , Nm3 = Fa
FAC = Annual fuel cost = Tk 5.90 Fa
Ca = Annual operating and maintenance cost = Tk 0.20 x EP0
d = Discount rate=12% perannum
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
11/28
The Total Discounted Fuel and O&M cost, Te will be calculated as shown in Table below:
Year Fuel CostIn Taka
O&M Cost per yearIn Taka
Discounted Fuel and O&M costper YearIn Taka
1. Fac Ca (Fac+Ca)/(1+d)
2. Fac Ca (Fac+Ca)/(1+d)2
3. Fac Ca (Fac+Ca)/(1+d)3
4. Fac Ca (Fac+Ca)/(1+d)4
5. Fac Ca (Fac+Ca)/(1+d)5
6. Fac Ca (Fac+Ca)/(1+d)6
7. Fac Ca (Fac+Ca)/(1+d)7
8. Fac Ca (Fac+Ca)/(1+d)8
9. Fac Ca (Fac+Ca)/(1+d)9
10. Fac Ca (Fac+Ca)/(1+d)10
Te =
Then Per unit Discounted Fuel and O&M cost (T2) in BTk. per kW will be found out by dividing Te by thenet plant capacity, Po in kW at Site conditions. Hence T2 = Te/ Po.
Evaluated Price
Finally Evaluated cost (T) in BTk. per kW will be found out by adding T1 and T2.Hence T = T1 + T2.
The tenderer whose Tvalue is the lowest will be adjudged the lowest tenderer.
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
12/28
Attachment 02 of addendum no. 03 (Page 12 to 28 )
Revised Bill of Materials/Quantities&
Price Schedule
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
13/28
Addendum 03, Bibiyana 300-450 MW 13
The Tenderer shall fill-up the following table of prices and shall include the same in the financial proposal
Schedule-1
Supply of Equipment:Sl.No
Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for
Transportationup to Site
Custom Clearanceand Inland
Transportation
Rate Total Rate Total Rate Total Rate Total Rate Total
1A-1 Packaged Gas Turbine Generating unitcompleted in all respect including allauxiliaries, instrumentation, grounding system
and inter-connection piping, cabling, gas fueloperation, air intake filtration facilities, inletand exhaust silencing facilities, ducts andother ancillaries equipment.
Gas Turbine2 nos. for2:2:1 Config.
or1 no. for 1:1:1Config.
Gas TurbineGenerator2 nos. for2:2:1 Config.or
1 no. for 1:1:1Config.
1A-2 Complete equipment for off base coolingsystem.
1(one) Set
1A-3 Complete equipment for off base natural gassupply system including gas treatment skid.
1(one) Set
1A-4 Gas Booster Compressor with all ancillary,auxiliary [3X60%]
3(three) sets
1A-5 GT (Bypass) Stack. 2 nos. for2:2:1 Config.or1 no. for 1:1:1Config.
1A-6 15.75 KV Generator Switchgear(circuit breaker, isolators, earthing switches,CT, PT, surge capacitors, surge absorber
assembly)
2 (two) sets
1A-7 Station Transformer, 6.6/0.415 KV. 4(four) Sets
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
14/28
Addendum 03, Bibiyana 300-450 MW 14
Sl.No
Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for
Transportationup to Site
Custom Clearanceand Inland
Transportation
Rate Total Rate Total Rate Total Rate Total Rate Total
1A-8 Unit Auxiliary Transformer, 15.75/6.6 KV. 2(one) Sets
1A-09 230/11/6.6 kV Transformer 1 (one) set
1A-10 230 kV U/G cable, conductors 1 (one) Lot
1A-11 230 kV switchgear, protection & meteringequipment etc.
1 (one) Lot
1A-12 Steel structures, insulators etc. for 230 kV 1 (one) Lot
1A-13 11 kV switchgear, protection & metering
equipment etc.
1 (one) Lot
1A-14 11 kV cable, conductors, insulators 1 (one) Lot
1A-15 11/ 0.4 kV Transformers 1 (one) Lot
1A-16 0.4 kV cable, conductors, insulators 1 (one) Lot
1A-17 6.6 KV station switchgear. 1 (One) Lot
1A-18 415 V switch gear and power centres 1 (One) Lot
1A-19 Emergency Diesel Generator (EDG) (cap 1000kVA) with all ancillary and diesel storage tank.
1 (one) set
1A-20 Other miscellaneous equipment/materials 1 (One) Lot
Sub-total : 1A
1B-1 Heat Recovery Steam Generator(s) 2 nos. for2:2:1 Config.or1 no. for 1:1:1Config.
1B-2 Structural Steels 1 (one) lot
1B-3 Piping work 1 (one) lot
1B-4 Valves 1 (one) lot
1B-5 Instrumentation & Control facilities 1 (one) lot
1B-6 Lagging & Cladding 1 (one) lot
1B-7 On & Off-load Cleaning equipment 1 (one) set
1B-8 Gas Duct 1 (one) lot
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
15/28
Addendum 03, Bibiyana 300-450 MW 15
Sl.No
Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for
Transportationup to Site
Custom Clearanceand Inland
Transportation
Rate Total Rate Total Rate Total Rate Total Rate Total
1B-9 Hydraulic Diverted damper with hydraulic oilskid
2 nos. for2:2:1 Config.or1 no. for 1:1:1Config.
1B-10 Motor operated Guillotine Damper 2 nos. for2:2:1 Config.or
1 no. for 1:1:1Config.
1B-11 HRSG Stack 2 nos. for2:2:1 Config.or1 no. for 1:1:1Config.
1B-12 Chemical dozing system including pumps 01 (one) lot
1B-13 Other miscellaneous equipment/materials 1(one) lot
Sub-Total 1B
1C-1 Steam Turbine & auxiliaries 1 (one) set
1C-2 Steam Turbine Generator including excitationsystem, AVR & other auxiliaries
1 (one) set
1C-3 Surface condenser 1 (one) set
1C-4 Deareator 1 (one) set1C-5 Air extraction system, ejector 1 (one) set
1C-6 Air extraction system, Vacuum Pump 02 (two) Nos.
1C-7 Closed loop cooling water system 1 (one) lot
1C-8 Feed Water Pump 3 (three) nos.
1C-9 Condensate water Pump 3 (three) nos.
1C-10 Circulating water pump (cooling Tower Pump) 3 (three) nos.
1C-11 Cooling Tower fans 1 (one) lot
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
16/28
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
17/28
Addendum 03, Bibiyana 300-450 MW 17
Sl.No
Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for
Transportationup to Site
Custom Clearanceand Inland
Transportation
Rate Total Rate Total Rate Total Rate Total Rate Total
1E-2 6.6 KV XLPE power cable 1 (one) Lot
1E-3 600 V power cable 1 (one) Lot
1E-4 Control and Instrument cable 1 (one) Lot
1E-5 Raceway Materials 1 (one) Lot
1E-6 Grounding System 1 (one) Lot
1E-7 Lighting and small power 1 (one) Lot
1E-8 Battery (125 V DC Alkaline Ni-Cd battery)
Battery Chargers
2(two) sets
1E-9 DC distribution board, switchgears, cables etc. 1 (one) Lot
1E-10 2x 100% capacity Invertors with relatedswitchgears, cables etc.
1 (one) Lot
1E-11 Communication system
PABX Telephone systemPaging system
Power supplyTelemetering facilities, Communication &SCADA EquipmentCCTV System
1(one) Lot1(one) Lot
1(one) Lot1(one) Lot1(one) Lot1(one) Lot
1E-12 Other miscellaneous equipment/materials 1(one) Lot
Sub-total : 1E
1F-1 Chemical water treatment plant including allreservoirs, storage tanks, pumps, valves,
pipings, electrical and I&C system with allauxiliaries complete in all respect.
1(one) Lot
1F-2 Chemical laboratory with standard apparatusfor Combined cycle Power Plant
1(one) Lot
1F-3 Effluent Treatment Plant 1(one) Lot
1F-4 Other miscellaneous equipment/materials 1(one) Lot
Sub-total : 1F
1G-1 GT Hall EOT Crane 1 (One) no.
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
18/28
Addendum 03, Bibiyana 300-450 MW 18
Sl.No
Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for
Transportationup to Site
Custom Clearanceand Inland
Transportation
Rate Total Rate Total Rate Total Rate Total Rate Total
1G-2 ST Hall EOT Crane(if ST is located in different hall or GT EOTcrane can not be used for ST)
1 (One) no.
1G-3 CWP House EOT Crane 1 (One) no.
1G-4 GBC House EOT Crane 1 (One) no.
1G-5 Mobile Crane 1 (One) no.
1G-6 5 ton truck with 3 ton jib crane 1 (One) no.
1G-7 5 ton fork lift 1 (One) no.1G-8 5 ton truck/ lorry 1 (One) no.
1G-9 1 ton half truck 1 (One) no.
1G-10 Hoist for EDG room, River intake pump house,Fire fighting pump house, Chemical plant
1(one) Lot
1G-11 Special tools and Special lifting and handlingappliances
1(one) Lot
1G-12 Other miscellaneous equipment/materials 1(one) LotSub-total : 1G
1H-1 Fire Fighting Facilities 1(one) Lot
1H-2 Special Maintenance tools including Boroscope 1(one) Lot
1H-3 Electrical workshop tools 1(one) Lot
1H-4 Machine Shop equipment & Tools 1(one) Lot
1H-5 Laboratory Equipment (Testing Bench) 1(one) Lot
1H-6 Transport:03 nos. of four wheel drive Jeep (3000 CC),04 nos. of sedan car (1600 CC), 04 nos. ofdouble cabin Pick up (2700 CC), 02 nos. ofmicrobus (2400 CC), 10 nos. of motorcycle(100 CC), 01 no. of ambulance.
1(one) Lot
1H-7 Other miscellaneous equipment/materials 1(one) Lot
Sub-total : 1H
1I-1 Local & Remote unit control desk Boards/ HMI 1(one) Lot
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
19/28
Addendum 03, Bibiyana 300-450 MW 19
Sl.No
Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for
Transportationup to Site
Custom Clearanceand Inland
Transportation
Rate Total Rate Total Rate Total Rate Total Rate Total
1I--2 15.75 KV common switchgear control deskboard including Gen. WH & VarH Recordingmeters
1(one) Lot
1I--3 Auxiliary power supply control desk board 1(one) Lot
1I-4 420 KV control, metering and protectionpanels including delivery point WH & VarHRecording meters
1(one) Lot
1I--5 Synchronising panels (swing type)
Plant Control System with on-line PlantPerformance Monitoring & OptimizationSystem
1(one) Lot
1I-6 Standard weather station 1(one) Lot
1I-7 Continuous emission monitor module 1(one) Lot
1I-8 Other miscellaneous equipment/materials 1(one) Lot
Sub-total : 1I
1J-1 Approx. 09 km Gas pipe line 1(one) Lot1J-2 Fuel gas regulating & metering station 1(one) Lot
1J-3 Other Fuel Gas Handling facilities 1(one) Lot
Sub-total : 1J
1K-1 Spares for Warranty period 1(one) Lot
1k-2 Consumables for Warranty period 1(one) Lot
Sub-total : 1k
1L-1 Simulator for Power Plant operation Training 1 (one) SetSub-total : 1L
Sub-total : 1
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
20/28
Addendum 03, Bibiyana 300-450 MW 20
Schedule-2Erection & Commissioning
Sl.No.
Description Qty Erection & Commissioning Insurance forErection &
Commissioning
Foreigncurrency
Bangladesh Taka Bangladesh Taka
Rate Total Rate Total Rate Total
2A Gas Turbine Generating unit Complete with auxiliary equipment 1 lot
2B Heat Recovery Steam Generator complete with auxiliaryequipment
1 lot
2C Steam Turbine Generating unit complete with auxiliary equipment 1 lot
2D Transformers, switchgears and other electrical equipment and
materials
1 lot
2E Approx. 09 km Fuel gas pipe line 1 lot
2F Fuel Gas regulating & metering station 1 lot
2G Other Fuel handling facilities and Gas Booster compressor 1 lot
2H Chemical Plant, Chemical lab, Effluent treatment plant 1 lot
2I Cooling Tower 1 lot
2J Fire fighting facilities 1 lot
2K Communication system 1 lot
2L Mechanical Auxiliary equipment 1 lot
2M Maintenance facilities, Workshop facilities, EDG and other
mechanical facilities
1 lot
2N Central control equipment 1 lot
Sub-total : 2
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
21/28
Addendum 03, Bibiyana 300-450 MW 21
Schedule-3Civil & Building Works:
Sl.No.
Description Qty Civil & Building Works Insurance for Civil &Building Works
Foreigncurrency
Bangladesh Taka Bangladesh Taka
Rate Total Rate Total Rate Total
3A-1 Soil test, demarcation & serveying and Excavation 1 lot
3A-2 Filling and Land development 1 lot
3A-3 Others, if necessary (Tenderer shall specify those items) 1 lot
Sub-total : 3A
Site works
3B-1 Internal Road, fencing, path and parking area 1 lot
3B-2 Drainage system 1 lot
3B-3 Sewage works 1 lot
3B-4 Water works, deepwell and pumps (2X100%) 1 lot
3B-5 Storage tank for fire-fighting 1 lot
3B-6 Piping and others 1 lot
3B-7 Landscaping, turfing, gravel surfacing 1 lot
3B-8 Others (if any);Tenderer shall specify those items 1 lot
Sub-total : 3B
PilingTenderer shall specify kind of piles to be utilised
3C-1 For Gas Turbine generating unit foundations 1 lot
3C-2 HRSG unit foundations 1 lot
3C-3 STG unit foundations 1 lot
3C-4 For Transformers, switchgears, equipment etc. foundations 1 lot
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
22/28
Addendum 03, Bibiyana 300-450 MW 22
Sl.No.
Description Qty Civil & Building Works Insurance for Civil &Building Works
Foreigncurrency
Bangladesh Taka Bangladesh Taka
Rate Total Rate Total Rate Total3C-5 GBC, EDG and other equipment foundation 1 lot
3C-6 For Building foundations 1 lot
3C-7 For gantry, steel structure foundations 1 lot
3C-8 Cooling Tower 1 lot
3C-9 Permanent jetty/ platform for loading, unloading ofequipment
1 lot
3C-10 River Water Intake 1 lot
3C-11 All storage Tanks 1 lot
3C-12 For Others (if any) ;Tenderer shall specify 1 lot
Sub-total : 3C
Foundation
3D-1 Gas turbine generating unit, HRSG, STG, GBC, EDG, Firefighting pumps and all associated equipment/auxiliaries
1 lot
3D-2 Transformers, switchgears, equipment foundations 1 lot
3D-3 Gantry, steel structures foundations 1 lot
3D-4 Buildings foundations 1 lot
3D-5 Cooling Tower 1 lot
3D-6 All storage Tanks 1 lot
3D-7 Permanent jetty/ platform for loading, unloading ofequipment
1 lot
3D-8 River Water Intake 1 lot
3D-9 Other foundation (if any) (Tenderer shall specify) 1 lot
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
23/28
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
24/28
Addendum 03, Bibiyana 300-450 MW 24
Schedule-4
Services :Sl.
No.
Description Qty Services
Foreign currency Bangladesh TakaRate Total Rate Total
4A DESIGN AND ENGINEERING 1 lot
4B WORKSHOP TESTS INCLUDING TEST WITNESSING 1 lot
TRAINING
4C1 Training at manufacturers factory 1 lot
4C2 Traveling charges, ____ persons 1 lot
4C3 Living allowance, ____Man-Month 1 lot
4C4 Training at the site 1 lot
4D DOCUMENTS (DRWINGS, OPERATION MANUALS,
STANDARDS etc.)
1 lot
4E Service for Execution of Schedule maintanance (Firstinspection, HGPI etc.) during 2 years warranty period
1 lot
4F Operation and maintenance services after satisfactory
performances test. (warrantee engineers for 2 yearswarranty period).
1 lot
Sub-total : 4
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
25/28
Addendum 03, Bibiyana 300-450 MW 25
Schedule-5A
Spare parts for Long Term Service Agreement (LTSA) for 5 years after warrantee period: [Will not be considered in
Evaluation]
Sl.No
Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for
Transportationup to Site
Custom Clearanceand Inland
Transportation
Rate Total Rate Total Rate Total Rate Total Rate Total
5A-1 Spare parts & consumables for the 1st year ofLTSA
1(one) Lot
5A-2 Spare parts & consumables for the 2
nd
year ofLTSA 1(one) Lot
5A-3 Spare parts & consumables for the 3rd year ofLTSA
1(one) Lot
5A-4 Spare parts & consumables for the 4th year ofLTSA
1(one) Lot
5A-5 Spare parts & consumables for the 5th year ofLTSA
1(one) Lot
Sub Total of 5AN.B: In preparation of the list the tenderer have to consider plant factor as 80%.
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
26/28
Addendum 03, Bibiyana 300-450 MW 26
Schedule-5B
Service for Long Term Service Agreement (LTSA) for 5 years after warrantee period: [Will not be considered in
Evaluation]
Sl.No.
Description Qty Foreign currency Bangladesh Taka
Rate Total Rate Total
5B.1 Service for the 1st year of LTSA (with break-up cost for requiredservice personnel including no. of visits, per-diem cost and expectedman-days)
1(one) Lot
5B.2 Service for the 2nd year of LTSA (with break-up cost for required
service personnel including no. of visits, per-diem cost and expectedman-days)
1(one) Lot
5B.3 Service for the 3rd year of LTSA (with break-up cost for requiredservice personnel including no. of visits, per-diem cost and expectedman-days)
1(one) Lot
5B.4 Service for the 4th year of LTSA (with break-up cost for requiredservice personnel including no. of visits, per-diem cost and expectedman-days)
1(one) Lot
5B.5 Service for the 5th year of LTSA (with break-up cost for requiredservice personnel including no. of visits, per-diem cost and expectedman-days)
1(one) Lot
Sub-total : 5B
N.B: In preparation of the list the tenderer have to consider plant factor as 80%.
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
27/28
Addendum 03, Bibiyana 300-450 MW 27
Schedule 5 : Total Prices for 5 years LTSA
Sch.No.
Description Foreign currency Bangladesh Taka
FOB Insurance
& Freight
Service/
Erection,Commissioning
, Civil &Building works
Insurance Customs
Clearance &Inland
transportation
Erection,
Commissioning, civil and
building works
Transportation
upto site
Erection
commission-ing, civil &building works
Sch. 5A Supply of Spares
Sch. 5B Services
Total of Schedule 5
Note: For gas turbine maintenance at least 1 (One) CI, 1 (One) HGPI and 1 (One) MI within the LTSA period have tobe considered.
-
7/28/2019 Bibiyana 03 Addendum 03 With Attachment
28/28
Addendum 03, Bibiyana 300-450 MW 28
Summary of Prices:Sch.
No.
Description Foreign currency Bangladesh Taka
FOB Insurance& Freight
Service/Erection,
Commissioning, Civil &Building works
Insurance CustomsClearance &
Inlandtransportation
Erection,Commissioning,
civil and buildingworks
Transportation
upto site
Erection
commission-ing, civil &building works
Sch. 1 Supply ofEquipment
Sch. 2 Erection &Commissioning
Sch. 3 Civil and Buildingworks
Sch. 4 Services
VAT & TAX for thework except CIF
Value of permanent
materials (@10.5%)
Grand Total
Sch. 5 LTSA
VAT & TAX for thework except CIF
Value of permanentmaterials (@10.5%)
Total