BHS / BTC ReEnvisioningUpdate...BHS / BTC ReEnvisioningUpdate. Current Status uSD estimate is $21M...
Transcript of BHS / BTC ReEnvisioningUpdate...BHS / BTC ReEnvisioningUpdate. Current Status uSD estimate is $21M...
BHS / BTC ReEnvisioning Update
Current Status
u SD estimate is $21M higher than available funds
u This will require one or more of the following:
u Re-visiting the Design Directives and Scope
u Keeping Property Services on Shelburne Rd.
u Reuse of more of the existing space
u(More renovation and less new construction)
u Additional funding through donations, grants etc.
uNOTE: Going back to taxpayers is NOT an option
What has been happening since the SD estimate came in:
u 8 cost-saving concepts presented
u One concept selected:
u Best chance to meet budget
u (But we are not there yet)
uWill still require re-visiting scope
I N S T I T U T E R O A D
N O R T H A V E N U E
Upright 12" CMP
Rim=174.86'
?
?
CO
CO
CO CO CO CO
CO
Flagpole
PROPOSED COLOR KEY
BLDG-NEW
BLDG-EXIST
DRIVES
PARKING
WALKWAYS
ATHLETIC COMPLEX(FIELDS, WALKS, BLDGS)
ATHLETIC COMPLEX
STUDENT PARKING
GMT BUS LOOP TO REMAIN
THEATER ACCESS
ADA RAMPEMERGENCY RESPONDER ACCESS
BTC AUTOBODY PROGRAM ACCESS
SERVICE ENTRANCES
FOOD SERVICE DELIVERY
BTC AUTOMOTIVE PROGRAM ACCESS
STAFF PARKING
EMERGENCY EGRESS
BICYCLE PARKING
BSD SPECIAL NEEDS DROP OFF
ACCESSIBLE PARKING
OUTDOOR CLASSROOM
SALT SHED
WOOD CHIP DELIVERIES
PROPERTY SERVICES FLEET VEHICLE PARKING
PROPERTY SERVICES FLEET VEHICLE PARKING
BTC PRE-SCHOOL ENTRANCE AND PLAYGROUND ACCESS
BTC PRE-SCHOOL DROP-OFF
EMERGENCY RESPONDER ACCESS
PARENT DROP OFF PARALLEL SPACES
GRAVEL WETLAND
GRAVEL WETLAND
EXTENT OF EXISTING SIDEWALKS TO REMAIN (OR BE REPLACED) T.B.D.
north
© 2019, Black River Design, Architects. All rights reserved.
ARCHITECTSBLACK RIVER DESIGNBURLINGTON HIGH SCHOOL RE-ENVISIONINGscale: 1" = 60'-0"
PROPOSED OVERALL SITE PLAN
10/09/19
Preliminary Calculations for Plan “B”
u Square Footage of Existing Building 237,500
u Less Demolition of C & E (41,303)
u Square Footage to be Renovated 196,197
u Square Footage of New Construction 74,107
u Proposed Net Square Footage 270,303
Preliminary Schedule Update
Phase Start Date End Date
Schematic Design Oct. 2019 Jan. 2020Schematic Design Estimate Jan. 2020 Feb. 2020Design Development Feb. 2020 June 2020Construction Documents June 2020 Feb. 2021Bidding Period Feb. 2021 April 2021Guaranteed Max. Price Presented April 2021Board Approvals April 2021 May 2021Construction June 2021 Oct. 2024
NOTE: This schedule is a work in progress. Tasks and dates are subject to change