Basement
-
Upload
hafizah-ayob -
Category
Documents
-
view
4.669 -
download
4
Transcript of Basement
IZATUL LAILI JABAR
WHAT IS BASEMENT…
A basement is a story or several stories of a building that are either completely or partially below the ground floor.
Not all buildings have basements. For buildings with basements, the furnace, water
heater, car park and air-conditioning system of a house or building are typically located in the basement; so also are amenities such as the electrical distribution system, and cable television distribution point.
IZATUL LAILI JABAR
Basement Grades (BS 8102)Grade Possible Use Conditions Required Moisture Exclusion
Grade 1:
Basic Utility
Car parking,
Mechanical plant rooms
>65% relative humidity
15-32oC temperature
Minor wet seepage and visible damp patches may be acceptable.
Grade 2:
Better Utility
Retail Storage,
Electrical plant rooms
35-50% relative humidity
Temperature depends on use:<15oC for storage,
up to 42oC for plant rooms
Wet seepage unacceptable. No visible moisture patches
Grade 3:
Habitable
Offices, Residential use, Kitchens,
Restaurants etc
40-60% relative humidity
Temperature range 18-29oC, depending on use
Seepage and wet patches unacceptable. Possible active control of internal environment required to control temperature and humidity.
Grade 4:
Special
Archive storage of books, documents, art etc
35-50% relative humidity
Temperature range typically 13-22oC
Environment tightly controlled by active measures. Seepage and visible dampness unacceptable.
IZATUL LAILI JABAR
Selection of types of basement
Level of ground water on site Possible contamination of ground water Natural drainage Soil type Access to site
IZATUL LAILI JABAR
Requirement of wall below ground
Structural stability Durability Moisture exclusion Buildability
IZATUL LAILI JABAR
Basement Type
Type A - Tanked Use impervious material internally or externally to
exclude moisture The selected waterproofing element must be
capable to withstand hydrostatic pressure from ground water & other loadings
Create a tanking effect
IZATUL LAILI JABAR
Type A - Tanked
IZATUL LAILI JABAR
Type B – Waterproof Utilise waterproof materials within the structure of
walls – structural integrated protection. Introduce crystallising agent inside concrete +
usage of proper construction joints
IZATUL LAILI JABAR
Type B – Waterproof
IZATUL LAILI JABAR
Type C – Drained Allow the ground water to pass through the wall
by providing mechanism to drain it away.
IZATUL LAILI JABAR
Type C – Drained
IZATUL LAILI JABAR
IZATUL LAILI JABAR
TYPES OF BASEMENT CONSTRUCTION
OPEN-CUT CONSTRUCTIONCUT AND COVER
CONSTRUCTIONBOTTOM UPTOP DOWN CONSTRUCTION
IZATUL LAILI JABAR
OPEN-CUT EXCAVATION
IZATUL LAILI JABAR
For all excavations, operators must know: the line; the final depth of the excavation; the approximate width of the excavation at
the top; and the location of any services or other
hazards.
IZATUL LAILI JABAR
If there is sufficient right of way, open cut trenches can be used in almost any soil condition.
Generally a sloped open cut excavation is the most cost and schedule effective method of trenching.
When the trench is very deep and/or expensive backfill materials are required, then a vertical cut at the toe of the slope supported by shoring may be effective.
Ground water and weak lower layers may force partial shoring or flattening of the excavation slopes.
IZATUL LAILI JABAR
OPEN-CUT CONSTRUCTION
IZATUL LAILI JABAR
Open cut advantages
Allows continuous excavation, laying and backfilling operations. Minor breakdowns usually do not cause delays to all activities. The open trench needs only the design of the cut bank slope.
OSHA guidelines can be used, although cost saving usually will result if the bank slope is checked and designed by a registered engineer for a steeper slope. Sloping the excavation is the simplest method to design and use.
Because there are no additional support operations and equipment, it is the economical choice.
The open trench provides easy access to the work because equipment and construction materials are minimized.
The open cut method is suitable for most ground conditions, except for oozing mud and running sands.
IZATUL LAILI JABAR
Open cut disadvantages The slope of the bank requires more excavation
and backfill volume than the other options. The only bank support is the strength of the soil. If
drying, flooding, or change of soil properties weakens the soil, then sloughing and collapse can happen with little or no warning.
The sloped banks require a wider work area. The bank slopes may force the use of larger
equipment because the distance to reach into the trench is increased and a greater volume of soil must be excavated and backfilled.
19
Construction Method for Shallow Basement
Open excavation with sloping sides (if constraints of space on the site permits)
Angle of slope nature of soil + moisture content
20
Construction Method for Deep Basement Open excavation is not suitable:
Extent of excavation required around the building would be impractical
Risk of affecting ground support for adjacent building High cost for large scale of excavation Existence of high ground water level
Use: excavation with temporary support Excavation supported by permanent retaining walls
embedded in ground
IZATUL LAILI JABAR
CUT AND COVER CONSTRUCTION
IZATUL LAILI JABAR
The cut and cover construction technique has been used for many years as a means for building underground transportation facilities.
This method involves the installation of temporary walls to support the sides of the excavation, a bracing system, control of ground water, and underpinning of adjacent structures where necessary.
IZATUL LAILI JABAR
The main disadvantages of a cut and cover tunnel are its disruptive effects in congested urban environment.
Cost of cut and cover construction increases sharply with increased depth. Tunnel driving costs are usually higher per meter of tunnel than the average shallow cut and cover tunnel.
IZATUL LAILI JABAR
Cut and cover tunnel Ramp
IZATUL LAILI JABAR
Soldier piles and lagging
IZATUL LAILI JABAR
Steel sheet piles
IZATUL LAILI JABAR
BOTTOM UP CONSTRUCTION
28
1. Form perimeter walls to enclose the area to be excavated
2. Excavation install props excavation
3. Construct foundation+column slab (suspended slab)
4. Proceed upper works: extend column, continue upper slabs towards ground level
IZATUL LAILI JABAR
TOP DOWN CONSTRUCTION
30
Preferred method: ↑speed, ↓cost, ↑ground stability
Make use of permanent elements to provide rigidity and bracing.
Not required temporary props
IZATUL LAILI JABAR
Overall construction method: typically top down, bottom upwards or semi top-down.
Wall method. (temporary, permanent or both) king post walls steel sheet piling soil mix columns r.c. contiguous piles r.c. secant piles (hard/hard, hard/soft) diaphragm walls
IZATUL LAILI JABAR
Wall selection
King post walls. Timber laggings allowed to slide downwards between king posts. Poor tolerances, loss of ground.
Sheet piling. poor tolerances, Split clutches due to obstructions.
Contiguous piles, secant piles. wasting of pile shafts. Overbreak.
Diaphragm walls. Slurry inclusions, poor joints, poor cover to steel,bleed, poor tolerances, inclusions at toe of walls.
IZATUL LAILI JABARContiguous Piled Wall - 750mm diameter at 900mm Centres
IZATUL LAILI JABAR
Plunge Columns - Sequence
IZATUL LAILI JABAR
IZATUL LAILI JABARrig boring wall piles Secant Walls and Columns
IZATUL LAILI JABAR
Diaphragm Wall Excavation
IZATUL LAILI JABAR
Reinforcing Cage Installation
IZATUL LAILI JABARGuide wall Construction for piling
IZATUL LAILI JABARSchematic of Construction Sequence
for hard secant piled wall
The hard / hard secant piled wall, consisted of 304 piles, 1180mm diameter at 1950mm spacing up to 31m long. The secant piling formed the lower part of the wall, with a new in-situ concrete retaining wall up to 1m thick built over the top. A steel beam was cast into every third pile designed to extend 7m above the pile cut off level into the existing basement. Short flat jack props were placed horizontally in the narrow gap between the beams and the existing wall, to aid the eventual demolition of the old wall. During the development of the site, six existing piles from the previous structure to occupy the site were incorporated into the wall. Water tightness was ensured between these and the new piles by injection grouting.
IZATUL LAILI JABARCompleted Hard / Hard Secant Piled Wall
42
1. Formation of permanent retaining walls to the perimeter of basement area.
2. Form internal foundation and column support by using plunge method.
3. Create the uppermost floor slab (with temporary base)
4. Excavate downwards tru openings on slab or service shafts
5. Remove temp. base, excavate until the depth of next floor level.
6. Cast the next floor level, repeat the process.
7. Can use non-suspended slab for the basement slab.
Top-Down Construction
IZATUL LAILI JABAR
Typical sequence of top down construction
IZATUL LAILI JABAR
2) Install bearing piles with plunge columns
IZATUL LAILI JABAR
3) Cast ground floor slab
IZATUL LAILI JABAR
4) Excavate and cast upperbasement floor slab.
5: Extend columns and castfirst floor slab
IZATUL LAILI JABAR
6: Excavate and cast middlebasement slab
7: Extend columns and castsecond floor slab (notshown)
IZATUL LAILI JABAR
8: Excavate and cast lowerbasement slab.
9: Extend columns and castupper floor slabs (notshown).
IZATUL LAILI JABAR
Top-down excavation for basementlevels 1 and 2
The existing massive piled raft at newbasement 2 level was broken up with explosive
charges at night and cleared during the day
Excavation at basement 3 level finallyincluded breaking up existing large-diameter piles that were part of
the observational method contingency arrangements