Moisture resistant sealTo keep the moisture fromconcrete entering the basement
Structural Screed topping 75mmwith high performance stip resistantfloor finish
Drainage layer
Reinforcement concrete foundationdetail with a concrete floor toppingof 150mm
DPC
Xtratherm rigid insulationupstand
Foamglas Perisul structuralinsulation
Concrete Cast In Situ Column CorbelSteel dowel bars cast into the column corbel tosupport the floor aboveTo engineers specifications
Blockwork wall construction with aninner cavity layer of 60mmBlockwork (100mm x 215mm)
Drainage layer
Pervious pavingSloping ratio level 1 in20
High performance slip resistant floor finish
Gyproc plasterboard12.5mm with a 30 minutefire protection option
Vapour barrier should becontinous and sealed atcorners
Isover mineral insulation(Metsec system with steelchannels)
Xtratherm rigid insulation installed toavoid thermal bridging once the stonecladding attachment joints will beinstalledSupported by C channels
150
Structural Screed Topping 75mm
Concrete Hollowcore Floor Slab 150mm
Isover mineral wool insulationwith zee steel channel support
Cement fiberboard (moistureresistant) 13mm
Sand Layer (Hardcore) 50mm
Geotextile layer
Drainage pump
Area for basement drainage with sump pump
Rigid insulation floorbase detail
DPM
Screed topping
Drainage layer
Reinforcement concretefoundation detail
DPC
Xtratherm rigid insulationupstand
Foamglas Perisul structuralinsulation
Concrete Cast In Situ Column CorbelSteel dowel bars cast into the column corbel tosupport the floor aboveTo engineers specifications
High performance slip resistant floor finish
Car Park Ramp (1:10)Concrete Construction
Aluminium expansion joint cover
Basement Drainage with pump
400
2800
Height Warning Sign
High performance, slip resistant floor finishCurved at edges
Structural screed toppoing 75mm
Concrete Hollowcore floor slab 150mm
Isover mineral wool insulation with zeesteel channels acting as support
Cement fiberboard 13mm fixed to theabove structure
Light Fixing within the cavity
Metsec wall system with Isover mineral insulation
Xtratherm rigid insulation with c channels andstonelite rainscreen cladding system on theexterior
Steel capping construction supported by a concretecolumn, with external lighting fixed within the resets
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology CarlowBSc. in Architectural Technology
Year 3 2015-2016
1 : 10
25/0
4/2
016 1
7:4
4:5
6
Basement Construction Detail
3
Primary Care Center
April 2016
Rasmante Sedleckaite
Dan O'Sullivan/ Noel Dunne/Mark Duffy
A118
1 : 10
Basement Construction Detail1
1 : 10
Basement Entrance Detail2
Basement Isometric View3