BALDWIN CREEK ROCKY RIVER STABILIZATION NEAR … › ... › 1556 › BD_NearAbbeyRoad.pdfABBEY ROAD...

1
Abbey Rd Copyright nearmap 2015 Project Assets Regional Stormwater System ¯ 0 50 100 Feet BALDWIN CREEK STABILIZATION NEAR ABBEY ROAD North Royalton, Ohio SUMMARY This project includes over 400 linear feet of channel realignment and floodplain reconnection west of Abbey Road to create a stable meander pattern and alleviate severe bank erosion. A private driveway crossing will be evaluated for replacement because it is in poor condition and contributes to stream instability. Project Details BD00287 BD00291 BD00292 BD00293 GED/Bid/Build $440,000 3rd QTR 2020 Watershed Team Leader: Donna Friedman [email protected] ROCKY RIVER WATERSHED BALDWIN CREEK SUBWATERSHED

Transcript of BALDWIN CREEK ROCKY RIVER STABILIZATION NEAR … › ... › 1556 › BD_NearAbbeyRoad.pdfABBEY ROAD...

  • Abbey R

    d

    Copyright nearmap 2015

    Project AssetsRegional Stormwater System

    ¯ 0 50 100 Feet

    BALDWIN CREEK STABILIZATION NEAR ABBEY ROADNorth Royalton, Ohio

    SUMMARYThis project includes over 400 linear feet of channel realignment and floodplain reconnection west of Abbey Road to create a stable meander pattern and alleviate severe bank erosion. A private driveway crossing will be evaluated for replacement because it is in poor condition and contributes to stream instability.

    Project DetailsAsset Numbers:BD00287BD00291BD00292BD00293Contract Type:GED/Bid/BuildConstruction Cost:$440,000

    Anticipated Construction NTP:3rd QTR 2020Watershed Team Leader:Donna [email protected]

    ROCKY RIVERWATERSHED•BALDWIN CREEKSUBWATERSHED