Bab 3 Interim Payment
-
Upload
amyamirulali -
Category
Documents
-
view
312 -
download
4
description
Transcript of Bab 3 Interim Payment
BAB 3
INTERIM PAYMENT
3.1 : INTRODUCTION
1. Methods of payments to contractor normally determined by the size of jobs.
Small jobs : Contractor will be paid on completion of the job i.e.
only 1 payment involved.
Big jobs : Contractor is to be paid in instalmens i.e. many
payments are made until the whole contract sum is settled.
2. Interim payments – all payments made to the contractor other than the final
payment. These payments are made during and after the contract period until the
issuance of final payment.
3. During Construction – the contractor is entitled to interim payments at regular
interval in accordance with a proper evaluaton of the work done and materials
supplied i.e. the contractor receives regular payments as the work progresses.
21
4. After completion – the interim certificates are not subjected to monthly interval.
5. There should not be any large amount outstanding to the contractor after completion
and payments within this period mey be required:
a) To release retention sum (where applicable),
b) For final evaluation of variations,
c) Settlement of an account for loss and expenses,
d) N.S.C.’s and N.S.’s accounts.
3.2 : P.W.D. FORM 203A (Rev. 2007)
1. The relevant contractual provisional regarding interim payments are as
shown in Table 1.
P.W.D. FORM 203A (Rev. 2007)
Clause 20.0 : Unfixed materials and goods
Clause 28.0 : Payment to contractor
Clause 30.0 : Fluctuation of price
Clause 33.0 : Deduction from money due to contractor
Clause 34.0 : P.C./ Provisional sums
Clause 40.0 : Damages for non-completion
Clause 60.0 : Payment for Nominated sub-contractors or Nominated
supplier
Table 1 ; Contractual provisional
2. The above Clauses explain the procedure to be adhered to in the payment
process which include:
a) The timing of payments to the contractor.
b) The amount to be paid to the contractor.
c) The right of set-off by the employer.
d) The enforcement of payment.
22
e) The procedure and conditions precedent.
3.3 : PROCEDURE OF CERTIFICATION
Figure 1: Interim payment process.
3.4 : CONTRACTOR’S APPLICATION
1. The submission of payment application by the contractor is not
mandatory under the contract. The S.O. has to make valuation for
interim payment even though contractor does not submit his claim.
2. However, contractor normally submits his claim for work done and
materials on site to help speed up the valuation process. The claim is
n the form or BQ or Summary in the tender.
3. S.O./ Consultant to check and approve the application. Consultant
also to certifyin writing that the work is in accordance to contract.
4. For administrative purposes, it’s good to agree on the specific date of
each month for the submission of the application.
23
Progress claim submitted by contractor.
Valuation prepare by S.O.
Certification by S.O.
Payment made by employer
5. The application shows the estimated value of work done by the
contractor and should be presented in an approved format.
6. The contractor should include everything that he thinks he entitled to
be paid in his application since the claim is going to be the basis of
the evaluation.
3.5 VALUATION
3.5.1 Generally
‘When the contractor has executed work including delivery … of any unfixed
materials or goods intented for use thereon … the S.O. at that time make the first
valuation of the same.’ (Clause 28.)
1. The S.O. has to make interim valuation in order to arrive at the
amount due in interim certificates.
2. The evaluation is for the work properly executed and materials
delivered on site.
‘Thereafter, once (or more often at the discretion of the S.O.) during
the course of each succeeding month the S.O. shall make a fair
valuation …’ (Clause 28.2)
3. The evaluation is to be carried out at least once a month.
4. In practice, the S.O. and the contractor have to agree on specific dates
or days of the month to carry out the valuation work.
5. The evaluation should be as accurate as is reasonably possible and is
subject to the month to carry out the valuation work.
6. A new evaluation of the work done provides an opportunity to adjust
or modify previous evaluations of earlies certificates.
7. No interim certificate is final and conclusive and is subject to
adjustment in subsequent interim certificates and final certificate.
8. The value of work executed consists of preliminaries and permanent
work done by the contractor.
24
3.5.2 Preliminaries
1. This section consists of those items that do not form part of the
permanent works but are essential to be provided for the successful
completion of the job.
2. The employer and the contractor should agree on the method of
paying for the preliminaries items at the beginning of the contract.
3. Valuation is only made on the items that are priced and carried out by
the contractor.
4. The price of each item may be broken down and categorized as initial
cost progressive cost or completion cost to the employer.
5. Initial cost – a lump sum to be paid to the contractor in the first
interim payment.
6. Progressive cost – a continuing cost to be spread throughtout the
execution of the work and either related to the time or to the
expenditure on the work.
7. Completion cost – a lump sum to be paid to the contractor upon
completion the work.
25
Example for calculation of payment for Preliminaries
Table 2 shows an example of breakdown of the preliminaries items.
The total amount of RM 361,700.00 in coloum ‘Initial’ to be paid in the first
interim payment.
The total amount of RM 33,100.00 in coloum ‘Comlpetion’ to be paid in the last
regular interim.
BQ REF. DESCRIPTION TOTAL INITIAL PROGRESSIVE COMPLETION
D/11/A Temporary roads
Temporary office
Signboards
Light & power
Water for the works
Contractor’s equipment
Site telephone
Temporary hoardings
Work programme
Cash flow estimate
Progress report
Progress photographs
Shop drawings
Site meetings
Interim certificate claims
Testing & apparatus
Maintenance on public roads
Safeguarding the works
Keeping site clear
Clearing site on completion
Setting out
Contractor’s superintendence
Workmen’s compensation
10,000.00
18,000.00
2,000.00
10,000.00
15,000.00
300,000.00
8,500.00
28,000.00
20,000.00
5,000.00
2,000.00
6,000.00
2,000.00
3,000.00
2,000.00
5,000.00
3,000.00
30,000.00
50,000.00
15,000.00
20,000.00
240,000.00
75,000.00
7,500.00
14,000.00
1,700.00
1,000.00
3,000.00
50,000.00
500.00
20,000.00
1,000.00
1,000.00
-
-
-
-
-
2,000.00
-
-
-
-
15,000.00
-
75,000.00
1,500.00
3,500.00
200.00
8,500.00
11,500.00
240,000.00
7,500.00
5,000.00
19,000.00
4,000.00
2,000.00
6,000.00
2,000.00
3,000.00
2,000.00
3,000.00
3,000.00
28,000.00
50,000.00
-
5,000.00
240,000.00
-
1,000.00
500,00
100.00
500.00
500.00
10,000.00
500.00
3,000.00
-
-
-
-
-
-
-
-
2,000.00
-
15,000.00
-
-
-
-
TOTAL 1,049,500.00 361,700.00 654,700.00 33,100.00
Table 2: Breakdown of Preliminaries
26
The total amount of RM 654,700.00 in coloum ‘Progressive’ to be paid
progressive during the execution of the works and can be done in 2 ways:-
a) Pro-rata on contract period :
Assumptions: Contract period = 24 months
Progressive payment = RM 654,700.00 = RM 27,279.17 / Month
24
Amount of Preliminaries items to be paid:
Payment No. 1 = RM 361,700.00 + (654,700.00 x 1) = RM 388,979.17
24
Payment No. 2 = RM 361,700.00 + (654,700.00 x 2) = RM 416,258.33
24
b) Pro-rata on the value of work executed
Assumptions:
Contract sum = RM 25,000,000.00
Provisional sums = RM 1,500.000.00
Preliminaries = RM 1,049,500.00
Net contract sum = RM 25,000,000.00 – (RM 1,500.000.00 + RM 1,049,500.00)
= RM 22,450,500.00
% of progressive cost to net contract sum = RM 654,700.00 x 100
RM 22,450,500.00
= 2.91619 %
Amount of Preliminaries items to be paid:
If net value of work executed by contractor to date = RM 900,000.00
Progressive payment = RM 900,000.00 x 2.91619 % = RM 26,245.717
3.5.3 Value of the permanent works executed
Only the value of work properly executed by the contractor in accordance with
the contract must be included in the certificate – Townsend v Stone Toms &
Partners (1985).
27
‘the amount stated as due in an interim certificate shall, subject to any
agreement between the parties as to payment by stages, be the estimated total
value of the work properly executed …’ (Clause 28.4)
a) Valuation based on Contractor’s work executed
The valuation calculates the estimated value of work executed by reference
to:
i. The detailed quantities and rates for every items in the bills of
quantities as in Table 3.
B.Q REF DESCRIPTIONS TENDERED
AMOUNT (RM)
PERCENTAGE OF
WORKDONE (%)
AMOUNT OF
WORKDONE (RM)
D/1/A
D/1/B
D/1/C
D/1/0
D/2/A
D/2/B
D/2/C
D/2/0
D/3/A
D/3/B
D/3/C
W.B.L.F.F
Excavation
To red. lev.
For pile cap n.e. 1.00m dp.
Ditto 1.00 – 2.00m dp.
Grd. Bm. n.e. 0.50m dp.
Hardcore
Conc. Gr. 15
Lean conc. to pile cap
Ditto to grd. bm.
Conc. Gr. 30
Pile cap
Col. Stump
Grd. bm.
bed
900.00
10,900.00
5,520.00
1,890.00
2,850.00
3,248.00
8,690.00
125,080.00
7,695.00
32,631.00
53,852.00
100.00
100.00
100.00
90.00
30.00
100.00
100.00
100.00
100.00
25.00
0.00
990.00
10,900.00
5,250.00
1,701.00
855.00
3,248.00
8,690.00
125,080.00
7,695.00
8,157.75
0.00
Total Carried Forward 172,566.75
Table 3: Valuation besed on measured items.
28
ii. The cost of elements or work sections as in Table 4.
ITEM DESCRIPTIONS TENDERED
AMOUNT (RM)
PERCENTAGE OF
WORKDONE (%)
AMOUNT OF
WORKDONE (RM)
A
B
C
D
E
F
G
H
J
K
L
M
N
P
W.B.L.F.F
FRAME
UPPER FLOOR
STAIRCASE
ROOF
EXTERNAL WALLS
INTERNAL WALLS
WINDOWS
DOORS
INT. WALL FINISHES
INT. FLOOR FINISHES
INT. CEILING FINISHES
EXTERNAL FINISHES
MECHANICAL &
ELECTRICAL WORKS
25,400.00
31,900.00
18,250.00
5,890.00
20,850.00
9,500.00
3,240.00
8,500.00
5,400.00
12,690.00
22,200.00
13,850.00
15,800.00
58,000.00
100.00
95.00
90.00
90.00
30.00
35.00
30.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
25,400.00
30,305.00
16,4250.00
5,301.00
6,255.00
3,325.00
972.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL261,470.00 - 87,983.00
Table 4 : Valuation based on elemental cost
iii. The contract sum
This only suitable for small jobs and to be done by experienced
staff only.
The amount of done is calculated by multiplying the estimated
percentage completion with the contract sum.
Example:
Amount of work done = 25% x RM100,000.00 = RM 25,000.00
Where 25% is the percentage of work completed and RM
100,000.00 is the contract sum.
29
b) Valuation based on stage of completion
i. This is an alternative method of valuing the work executed by the
contractor.
ii. Interim payment to be made on the basis of percentage
completion of the various components of the project.
iii. An example of breakdown of works for stage payment for a
residential building is as shown in Table 5.
BREAKDOWN OF CONTRACT SUM
ITEM
S
STAGES OF WORKS
PERCENTAGE OF
CONTRACT SUM
1 Foundation and ground floor 15 %
2 Reinforced concrete frame, staircases and upper floor 20 %
3 Walls including doors and windows 15 %
4 Roofing, electrical wiring and plumbing 15 %
5 Finishes 15 %
6 Roads, drains and sewerage works 20 %
TOTAL 100%
Table 5 : Schedule of breakdown of contract sum.
iv. The detail of breakdown of works and the percentage of
payment to each stage of work will be decided by the employer
and attached to the tender document or as agreed by both the
employer and the contractor before the signing of the contract.
v. The amount to be paid to the contractor for the work
executed is equal to the value of the percentage of the contract
sum assigned to the work.
vi. In some arrangement, materials on site are not considered
for payments.
30
c) Percentage Adjustment
‘The Govermentreserves the right to adjust the prices and rates in the Bills of
Quantities … to ensure their reasonableness before acceptance of tender…’
(Clause 26.2)
‘Any adjustment of the prices and rates in the B.Q. required … above and any
arithmetical error or omission in the B.Q. shall before signing of the contract be
so rectified and adjusted that when correctly calculated, the total amount in the
summary of the B.Q. shall represent the same amount as the tender amount in
the Form of Tender ...’ (Clause 26.3)
i. Before the signing of contract document – the S.O has to check the
contract document and make adjustment or corrections to:
a) Unreasonable and inconsistent rates
b) Arithmetical error in the pricing by the contractor.
ii. Normal sources of errors:
a) ‘Extension’ e.i. multiplication of rates and quatities.
b) Adding up the total of each item on each page of B.Q.
c) Transferring the total on each page to Collection.
d) Transferring the total from Collection to Summary.
e) Transferring the total from Summary to Form of Tender.
iii. Correction has to be made to avoid mistakes in the computation of
interim payments.
‘… The tender amount shown in the Form of Tender shall remain unaltered
but the nett aggregate amount of the difference ..., shall be calculated as a
percentage of the total adjusted amount shown in the summary of the B.Q.
and all prices and/ or rates throughout shall be subject to such percentage
discounts or premiums as the case may be. Provided always that Provisional
and P.C sums shall be excluded from such calculation and shall not be
subject to such percentage discount or premium.’ (Clause 26.3)
31
iv. The original contract sum in the Tender Form must not be changed.
v. The S.O. has to calculate the percentage of the difference between the
tender sum and the corrected tender amount.
Example of the calculation of percentage adjustment
A. TOTAL AMOUNT as tendered RM 1,000,000.00
B. TOTAL AMOUNT as corrected RM 950,000.00
C. ERROR RM 50,000.00
B. TOTAL AMOUNT as corrected RM 950,000.00
Less Total Provisional Sums RM 100,000.00
D. TOTAL for Builder’s Works as corrected RM 850,000.00
E. PERCENTAGE ADDITION / OMMISION = C X 100 D 1
= 0.058823529% X 100 1
=5.8823529%
ADDITIONAL/OMISSION
If Tender amount > Corrected amount = + percentage adjustment
If Tender amount < Corrected amount = - percentage adjustment
vi. The amount to be paid to the contractor in the interim certificate is
subjected to the percentage adjustment.
32
Example of application of percentage adjustment in interim payment:
Example 1:
Assumptions:Value of work executed by the contractor(Preliminaries + building work + external work) = RM 500,000.00Percentage adjustment = + 5.8823529%
Value of work executed = RM 500,000.00 Add percentage adjustment= RM500,000.00 x 0.058823529 = RM 29,411.76Amount to be paid = RM 529,411.76
Example 2:Assumptions:The work is 100% completed.
Value of work executed = RM 850,000.00Add percentage adjustment= RM 850,000.00 x 0.058823529 = RM 50,000.00Amount to be paid = RM 900,000.00
d) Variations
i. This is for the value of work which is not part of the original scope of
work but has been carried out by the contractor as the result of the
S.O.’s instruction.
‘The amount of variations shall be certified by the S.O. and added to or deducted
from the contract sum …’ (Clause 25.3)
ii. The value of variation work must also be included in the variation of
permanent work executed by the contractor.
iii. The value so considered for payment includes the variation work
where variation certificate is not yet prepared.
e) Nominated Sub-contractors Works
i. The methods of valuation of works done by Nominated sun-
contractors are similar to that for main contractor.
33
3.5.4 Materials On Site
a) Generally
i. The contractor is entitled to payment for all unfixed materials
delivered to site but not yet incorporated in the work.
‘Unfixed materials and goods delivered to … Site … shall not be removed except
for use upon the works, unless the S.O. has consented in writing to such removal
…’ (Clause 20.0)
ii. Materials brought to site for the work must not be removed out of the
site without the S.O. consent.
iii. Materials which have been paid belong to the employer but the
contractor is still responsible for their safety.
iv. Materials not intended for the work must not be brought to site and
the S.O. instruct the contractor to remove those materials from site.
b) Prerequisite for payment
‘…value of the unfixed materials and goods deliverd to or adjacent to the site
intended for incorporation into the permanent works … such certificate shall
only include the value of the said unfixed materials and goods … they are
reasonably and properly and not prematurely delivered to or adjacent to the site
and adequately protected against weather, damage and deterioration.’
(clause 28.4)
i. Unfixed materials may be considered for payment if they are:
- Delivered to site or adjacent to site.
- Intended for incorporation in the permanent works i.e. in
accordance with the contract.
- Reasonably, properly and not prematurely brought to site.
- Adequately protected against weather and other casualties.
ii. The contractor also needs to obtain adequate title to the goods which
he pass on to the employer i.e. payment should be made to rightful
owner.
34
iii. The costc of the materials must have been paid by the contractor to
the supplier.
c) Computation of valuation
i. The materials are priced at invoice prices i.e. the actual price paid by
the contractor to supplied and the price should be reasonable and
based on market price.
‘The amount stated as due in an interim certificate shall, …up to 90% to the
value of the unfixed materials and goods delivered to adjacent to the site
intented for incorporation into the permanent works up to and including the
date the valuation was made …’ (Clause 28.4)
ii. The amount to be paid to the contractor is 90% of the value of
materials.
iii. The type and quantity of materials must be in accordance to contract
– as stated in Specification, shown on drawings, described in B.Q.
etc.
iv. Only total value of materials available on site on the date of
valuation considered for payment.
‘… unfixed materials and goods which are supplied and delivered by Nominated
suppliers for which payment should be made for the full value …’ (Clause 28.5)
v. Materials supplied by Nominated suppliers are to be paid in full.
35
3.5.5 Fluctuation of Price
‘… the amount payable by the Government to the Contractor upon the issue by
the S.O. of an interim certificate … shall be increased or descreased accordinglt
…’ (Clause 30)
i. The changes in cost of materials due to the market conditions must
be taken into account in the interim payments.
ii. Objective – to reduce risk of contractor as result of price increase by
compensating contractor for the increase during contract period.
iii. Price adjustment is made through the application of indices which
are issued by the Department of statistics in a formula.
iv. The calculation of the amount of fluctuation in price is to be made
monthly.
v. Base index figure is the index figure for the month the tender closes.
This index is to be inserted in Appendix B of the contract provision
before signing of the contract.
vi. Current index is the index figure for the month preceding the date of
the month of valuation.
Amount of Addition/Omission = Fluctuation factor x Effective value of
workdone
Fluctuation factor = Recovery factor x (Current index figure – Base index figure)Base index figure
Effective value of work done = Builder’s work – Preliminaries items
Recovery factor = 0.61 i.e. estimated material cost is 60% of the total cost of work.
Builder’s work = Total value of work done – (P.C. Sums + Provisional Sums)
*Addition/omission : quatity for the month x (previous price – current price)
(steel)
36
3.5.6 Performance Bond
‘The contractor shall, on the of the possession of site, provide a Performance
bond … issued by an approved licensed bank or financial institution
incorporated in Malaysia in favour of the Government for a sum equivalent to
five percent (5%) of the total contract sum … to secure the due performance of
the obligations under this contract by the contractor …’ (Clause 13.1(a))
i. A performance bond is an agreement between the Government, the
contractor and a third party i.e. a bank or an insurance company.
ii. The third party here agrees to pay a sum of money to the
Government in the event of non-performance of the contract by the
contractor.
iii. The performance bond must be for an amount 5% of the contract
sum.
‘… the Government shall make a payment to the contractor as
follows:
(a) Where the Performance Bond is in the form of a Banker’s,
Insurance or Finance Company Gurantee, payment shall be
made on the amount certified as due to the contractor in the said
interim certificate; …’ (Clause 28.6(a))
iv. The contractor will be paid the whole amount certified as payable to
him in the certificate as no money will be retained by the employer.
3.5.7 Performance Guarantee Sum
‘The contractor may opt for Perfomance bond in the form of Performance
Guarantee Sum … whereby deductions of ten percent (10%) shall be made from
the first interim payments and subsequent interim payment until the total
amount deducted aggregate to a sum equivalent to five percent (5%) or the
Contract Sum…’ (Clause 13.2)
37
i. This is an alternative form of guarantee for non-performance of
construction contract.
ii. The gross value of work done and materials delivered as ascertained
in the certificate is subject to deduction for Performance guarantee
sum.
iii. The deduction of 10% is made in every interim payment certificate.
Only 90% of the amount certified as due to the contractor will be
paid to him.
iv. The deductions must stop when the accumulated amount retained
reaches its limit of 5% of the contract sum.
3.6.8 Liquidated Damage for Delay
‘Upon the issuance of the Certificate of Non-Completon, the Government
shall be entitled to recover from the Contractor Liquidated and Ascertained
Damages calculated at the rate stated in the Appendix from the period of the
issuance of the Certificate of Non-Completion to the date of issuance of the
Certificate of Non-Completion to the date of issuance of Certificate of
Practical Completion or the date of termination of this contract. The S.O.
may deduct such damages from any money due or to become due the
Contractor …’ (Clause 40.2)
v. Liquidated and ascertained damages is a pre-estimate of a certain
sum of money to be paid as compensation if a breach actually takes
place.
vi. The amount is fixed and stated in Appendix to the Conditions of
contract.
vii. The contractor has to pay liquidated damages to the employer
38
3.7 CERTIFICATIONS
3.7.1 Generally
a) Taken Construction Co. Ltd. V Charlton Estates Ltd (1973) laid out that a
certificate in the expression in a definite form of opinion by the S.O. regarding
some matter according to the contract.
b) Wording such as ‘The amount stated as due in an interim certificate ...’ (Clause
28.4), and ‘... and interim certificate stating the amount due to the contractor ...’
(Clause 28.3) imply that certificates are required to be in writing.
c) The S.O. is responsible to certify to the Employer the amount of payment
payable to the Contractor within 14 days from the date of the valuation.
d) Content of an interim payment:
i. Value of work done (Clause 28.4)
ii. Value of materials on site (Clause 28.4)
iii. Fluctuation of prices (Clause 30)
iv. Variation works (Clause 25.3)
v. P.C and Provisional sums (Clause 60)
vi. Contractual claims (Clause 44)
e) The deduction are made for:
i. Previous payments made (Clause 28.4)
ii. Performance guarantee sum (Clause 13.2)
iii. Recoupment of advance payments (Treasury Instruction 11/1981)
iv. Liquidated and ascertained damages (Clause 40.2)
v. Other permitted deductions – payments to other contractors making good
defects (Cl. 48.2), default in payments of wages (Cl. 23.5), ect...
‘... the S.O. shall issue an interim certificate ... PROVIDED THAT the signing of this
contract shall not be a condition precedent for the issue of the first interim certificate
(and no other) so long as teh contractor has returned the Letter of Acceptence duly
39
signed and has deposited with the S.O. ... the relevent insurance policies ...’ (Clause
28.4)
f) First interim certificate can be issue even before signing of contract provided the
contractor deposited with S.O.:
i. Signed L.A.
ii. Public liability insurance and insurance of work.
g) For Government contracts, 3 interim certificates can be issued within 4 months
after the issuance of Letter of Acceptance even before signing of contract –
Treasury circular 10/1995.
‘NO certificate of the S.O. ... shall be considered as conclusive evidence as to the
sufficiency of any work, materials or goods to which it relates, nor shall it relieve the
contractor from his liability to amend and make good all defects, imperfections,...
(Clause 32.0)
h) Interim certificate is not an evident that the work have been properly carried out
and complete and it does not release the contractor of his responsibilities for
defects.
3.7.2 Certificate As A Condition Precedent To Payment
‘Within a number of days as stated in the Appendix ... (or if none stated then within 30
days) ... of the issue of any such interim certificate ... the Government will make a
payment to the contaractor on the amount certificate as due to the contractor in the
said certificate’ (Clause 28.6)
a) The payment certificate must be prepare before a payment can be made to the
contractor.
b) London Borough of Camden V Thomas Mclnerney & Sons Ltd. (1986) – the
architect signed certificates but they never sent out because a subsequent
40
inspection revealed defective work. It was held that since the certificates was not
issued, it was of no effect.
3.7.3 Late Certification
‘within 14 days from the date of any such valuation being made ... the S.O. shall issue an
Interim Cerificate stating the amount due to the Contractor ...’ (Clause 28.3)
a) No provision to deal with situation where the S.O. fails to certify within the
specified time.
b) However, contractor can commence arbitration proceeding on the ground that the
certificate has been improperly witheld. He does not have to wait until the work
practically completed.
3.7.4 Minimum Amount
‘... and the total value thereof has reached the sum reffered to in the Appendix ... the
S.O. at that time make the first valuation on the same.’ (Clause 28.1)
Thereafter, once (or more often at teh discretion of the S.O.) during the course of each
succeeding month ... each subsequent valuation shall not be less than the sum reffered to
in the Appendix ...’ (Clause 28.2)
a) The amount certified should be graeter than the minimun amount for interim
payment certificates in accordance with the KPKR’s instruction and as stated in
the Appendix of the conditions of contract as follows:
i. First payment – value of work executed and materials delivered is not less
that RM 1,000.00.
ii. Subsequent payments – ditto.
b) However, the S.O. may issue the certificate when dealing with a small balance at
the end of the contract.
41
3.7.5 Correction of Certificates
a) The contractor is entitled to be paid only for work properly done.
b) The S.O. may make any correction or modification in any previous certificate.
c) Certificates issued cannot be withdraw but the contractor can request the S.O. to
issue a further certificate to correct any patent or letent error discovered.
d) The S.O. has the authority to omit or reducethe value of any work not carried out
to his satisfaction in any certificate (Clause 48.3).
3.7.6 Under-certification
a) If the contractor is not satisfied with the amount certified by the S.O.:
i. Contractor can request S.O. to adjust the under-certification in a subsquent
certificate.
ii. If S.O. refuses, contractor may take the dispute to immediate arbitration
on the ground that certificate is not prepared properly.
iii. The contract gives no right to contractor to sue for higher sum.
b) Lubenham Fidelities & Investment Co. Ltd. V South Pembrokeshire Distric
Council (1986) – The employer only needs to pay the contractor the sum stated
in the interim certificate as being due to the contractor from the employer even if
the certificate contains a latent or patent error.
3.8 PAYMENT TO CONTRACTOR
3.8.1 Generally
42
‘Within a number of days as stated in the Appendix ... (or if none stated then within 30
days of the issue of any such Interim Certificate), the Gevernment will make a payment
to the contractor ...’ (Clause 28.6)
a) The certificates are binding on the employer and he must make the payment
within a specified period.
b) However, there is no provision to deal with situation where the Government fails
to py within the specified time.
3.8.2 Dispute by employer
a) Over-payment will result in unnecessary early expenditure by the employer and
also will cause problem in recovering his money in the event of insolvency of
contractor.
b) The employer may dispute the S.O.’s opinion but the contract gives no right to
the employer to withhold payment due to the contractor. The employer must pay
up within the honouring period.
43