ASCP Assignment

3
Business Requirements Planners want to see following information: I. Demand Planners: Demand and Supply for Swift on weekly basis for next 1 year. II. Material planners: Daily material requirement for next 6 months. III. Capacity planners: Monthly Resource requirement for next 1 year to meet forecasted demand IV. Sales Order for a particular day should consume weekly forecast for that week. Available Information End Product: Swift Weekly Forecast for Swift from 5 th Jan 15 onwards for year 2015 : 3000 units/week Sales Order for Swift for 20 th July: 100 units For Swift, Production will take new order 3 days after it is booked. Swift BOM Operation 10 Engine qty:1 10 Body qty:1 20 Tyres qty:4 Swift Routing 10 Assembly 96 hrs of resource1 20 Finishing 48 hrs of resource2 Calendar Organization follows manufacturing calendar where 5 days are working 2 days are off in a week. Two shifts run in a day and each shift is of 8 hours. Resource Availability

description

ascp assignment

Transcript of ASCP Assignment

Business RequirementsPlanners want to see following information:I. Demand Planners: Demand and Supply for Swift on weekly basis for next 1 year.II. Material planners: Daily material requirement for next 6 months.III. Capacity planners: Monthly Resource requirement for next 1 year to meet forecasted demandIV. Sales Order for a particular day should consume weekly forecast for that week.Available InformationEnd Product: SwiftWeekly Forecast for Swift from 5th Jan 15 onwards for year 2015 : 3000 units/weekSales Order for Swift for 20th July: 100 unitsFor Swift, Production will take new order 3 days after it is booked.Swift BOMOperation10 Engine qty:110 Body qty:120 Tyres qty:4Swift Routing10 Assembly 96 hrs of resource120 Finishing 48 hrs of resource2CalendarOrganization follows manufacturing calendar where 5 days are working 2 days are off in a week.Two shifts run in a day and each shift is of 8 hours.

Resource Availability

resource1 (machine resource) is item based and 2 units of resource is available per shift. resource2 (person resource) is lot based and 1 unit of resource is available per shift.

SourcingAll components are bought from various suppliers

For engine: it takes 2 days for item to be available in my inventory from the time the supplier ships it. for me it takes 1 day to place order with supplier and 1 day for supplier to release it to its shop floor. supplier takes 2 days to manufacture it

For Body: it takes 1 days for item to be available in my inventory from the time the supplier ships it. for me it takes 1 day to place order with supplier and immediately it is released to shop floor. supplier takes 2 days to manufacture it.

For tyres: it takes 1 days for item to be available in my inventory from the time the supplier ships it. for me it takes 1 day to place order with supplier and immediately supplier ships the order as he maintains a stock.Consulting OutputI. How many and what type of plans should be run?II. What setups are required is source and planning instance? Provide snapshots