Arrangements Non-standard Arrangements Concepts · · 2017-03-22» Utility connections and...
Transcript of Arrangements Non-standard Arrangements Concepts · · 2017-03-22» Utility connections and...
2/20© Clean Energy Systems Integration Lab, 2017
A Systems Perspective on SOFC
Sizing and Storage
Standard SOFC ArrangementsNon-standard Arrangements
Zero Carbon & TRL 5-6 Concepts
3/20© Clean Energy Systems Integration Lab, 2017
15
14
27
38
52
64
77
8693 97 98 99 99 100
0
10
20
30
40
50
60
70
80
90
100
110
0
300
600
900
1200
1500
1800
2100
2400
2700
3000
3300
Cum
ulat
ive
Perc
ent
# of
Inst
ance
s
Demand (%)
» Utility connections and equipment charges for 100% demand
» Average use is ≈13%» Demand is <20%, for
99% of the time» Generally predictable
demand
0
10
20
30
40
50
60
70
80
0 2 4 6 8 10 12 14 16 18 20 22 24
% o
f Max
imum
Dat
a Ce
nter
Dem
and
Hour
Daily Demand Profiles
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6Day 7 Day 8 Day 9 Day 10 Day 11 Day 12
0
5
10
15
20
25
30
35
40
45
50
0 3 6 9 12 15 18 21 24 27 30
% o
f Max
imum
Dat
a Ce
nter
Dem
and
Day of Month
99th Percentile
Average
78.8%
4/20© Clean Energy Systems Integration Lab, 2017
Lead-Acid1 : $1,206k˃ Assume: $26/kW, $77/kWh, 3C discharge (50% capacity
loss), 300 cycles 7x replacement˃ 4x needed kWh capacity
Lithium Iron Phosphate Batteries1: $193k˃ Assume: $16.7/kW, $250/kWh, 15C discharge (5% capacity
loss) 1500 cycles 1x replacement˃ 1.5x needed kWh capacity
2017 Costs» Assuming 100% = 10MW» SOFC size is 2MW = 99th percentile
˃ Worst peak period: 0.8MW, 250kWh˃ Worst power surge: 5.8MW, 190kWh
» SOFC initial system cost $5,000/kW» 50k hr stack, replace twice at
$1,800/kW for 20yr plant» Net capex is = $17.2M
Capacitor: $4M˃ Assume: $12/kW, $16,000/kWh, 1,300C discharge, 1e6
cycles no replacement˃ 50x needed power capacity
Battery + Data Center Control: $125k˃ Match kWh needs, throttle data center power surges
1 Shouzhong Yi, Discussion on Lithium Iron Phosphate Batteries Used for IDCs Compared with VRLA Batteries. International Stationary Battery Conference 2016. http://www.battcon.com/PapersFinal2016/Yi%20Paper%202016.pdf2 Maxwell Rechnologies White Paper http://www.maxwell.com/images/documents/whitepaper_powerelectronicsinterface.pdf
Conclusion: peaks & surges can be handled for ≈ 1-2% of SOFC system cost
Fuel Cell
Ultra-capacitor
0
10
20
30
40
50
60
70
80
0 10 20 30 40 50 60
% o
f Max
imum
Dat
a Ce
nter
Dem
and
Minutes99th Percentile Day 1 Day 2 Day 3Day 4 Day 5 Day 4b Day 8
5/20© Clean Energy Systems Integration Lab, 2017
Simulated SOFC response: 0.04% per second
Demonstrated SOFC response: 4% per second1
1 Li Zhao, Jack Brouwer, Sean James, Eric Paterson, Jie Liu, Di Wang, “Fuel Cell Powered Data Centers: In-Rack DC Generation” 2015 http://fuelcellseminar.com/wp-content/uploads/Zhao-Fuel-Cell-Powered-Data-Centers.pdf
0 10 20 30 40 50 600.5
1
1.5
2
2.5
Time (Minutes)Po
wer
(kW
)
Rack DemandSOFC output
6/20© Clean Energy Systems Integration Lab, 2017
» Fuel and water supply˃ Fuel content: pipeline natural gas, landfill or waste gas?˃ Can be net water positive.
» Fuel pre-conditioning˃ Sulfur and particulate removal
+ Won’t focus on this sub-system. Fuel stream determines best technology.
» Power conditioning˃ DC-DC conversion vs. DC-AC and AC-DC conversion˃ Solutions at all scales have similar efficiencies >97%.
+ Next talk will go into greater detail here…
» Stack˃ Important trade-offs: Size, Operating Voltage, Fuel Utilization, Lifespan,
Transient Response Rate
» Thermal management˃ Efficiency, Complexity, and Cost trade-offs in: Heat Exchanger size/type,
Reformer, Air Blower, Combustor, Waste Heat Recovery
7/20© Clean Energy Systems Integration Lab, 2017
DCDC
Combustor
Pre-reformer
Humidification Sulfur Removal
Blower
Fuel Supply
CathodeAnode
ExhaustBypass
Cell/Stack Objectives» Minimize electrical/ionic
resistance» Minimize degradation» Minimize thermal stresses» Lower manufacturing costs
System Objectives» Maximize H2 utilization» Maximize heat recovery» Minimize parasitic losses» Avoid costly high
temperature equipment» Minimize heat loses
Start-up Combustor
8/20© Clean Energy Systems Integration Lab, 2017
1. DC efficiency is directly linked to Voltage
2. Stack cost is inverse of current density
• Stack cost is ≈15% of small system, ≈45% of large system
3. Higher temperature and higher current are linked to faster degradation
4. Higher power density leads to higher thermal stress (convection limited HT)
• High air flow rates for cooling increase pressure drops, and thus blower parasitic
0
0.5
1
1.5
2
2.5
3
0
0.2
0.4
0.6
0.8
1
1.2
0 1 2 3 4 5
Pow
er D
ensit
y (W
/cm
2 )
Cell
Volta
ge (V
)
Average Current Density (A/cm2)
800-V 700-V 600-V800-P 700-P 600-P
5. Degradation from 0.9V to 0.8V (a 11% loss), can cause >50% increase in heat generation
• Air handling system must be sized for end-of-life, not initial conditions
9/20© Clean Energy Systems Integration Lab, 2017
Partial Oxidation
600°C50% CH4, 45% H2O, 5% Other
700°C0% CH4, 5% CO, 20% CO2, 50% H2, 20% H2O, 10% Other
600°C79% N2, 20% O2, 1% Other
10% Energy Loss
750°C20% CH4, 5% CO, 15% CO2, 10% H2, 40% H2O, 10% Other
600°C10% CH4, 10% CO, 15% CO2, 30% H2, 25% H2O, 10% Other
No Energy Loss
10% Energy Gain
750°C20% CH4, 5% CO, 15% CO2, 10% H2, 40% H2O, 10% Other
750°C0% CH4, 10% CO, 10% CO2, 60% H2, 15% H2O, 5% Other
1000°CCombustion Products
800°CCombustion products
Adiabatic Heat Recovery
10/20© Clean Energy Systems Integration Lab, 2017
Pros: most direct control of FC conditions Cons: Tremendous heat to evaporate water, low hydrogen utilization, large heat exchangers
DCDC
Combustor
Pre-reformer
Humidification Sulfur Removal
Blower
Fuel Supply
CathodeAnode
ExhaustBypass
11/20© Clean Energy Systems Integration Lab, 2017
Pros: best efficiency, single heat exchanger, no fuel humidification, reduced cathode air flowCons: SOFC must tolerate high levels of internal reforming and higher temperature gradients, reduced controllability with ejector
DCDC
Combustor
Pre-reformerSulfur Removal
Fuel Supply
CathodeAnode
ExhaustBypass
ejector
12/20© Clean Energy Systems Integration Lab, 2017
Pros: High efficiency, minimal CH4 reforming in stack, additional control of anode inlet temperatureCons: possibly slower transient response
DCDC
Combustor
Sulfur Removal
Fuel Supply
CathodeAnode
ExhaustBypass
ejector
13/20© Clean Energy Systems Integration Lab, 2017
» Case A: Self-sufficient 2.5kW SOFC modules» Case B: Centralized air blower & desulphurization
˃ Possible safety issue if plumbing odorless methane throughout building
» Case C: Centralized fuel processing, combustion & heat exchange» Case D: Centralized plant
DCDC
Combustor
Sulfur Removal
Fuel Supply
Cathode
Anode
Bypass
ejector
DCDC
Combustor
Sulfur Removal
Fuel Supply
Cathode
Anode
ExhaustBypass
ejector
Centralized
In Rack
Centralized In Rack
Pros: Efficiency & redundancy in air blower and desulphurizationCons: More high temperature equipment in rack and 50% more heat into room
Pros: Efficiency & redundancy in air blower and desulphurizationCons: Significant heat loss between SOFC and plant
14/20© Clean Energy Systems Integration Lab, 2017
Assumptions1. 10kW rack powered by 2.5kW SOFC and 200Wh Li-ion battery2. 2MW system has 8% DC loses between SOFC & rack, uses 250kWh battery3. Centralized blower has secondary redundant blower4. Data center management can readily shift work between racks in event of module failure5. SOFC durability is 60,000 hours (2x replacement in 20 years) for 2MW and 2.5kW
systems, and 45,000 hours (3x replacement) for 1MW6. Availability: SOFC stack – 99.7%, SOFC BoP – 96% (7.5kW) –99.9% (1.5MW) Blower –
98.5%, Grid – 99.9%7. Initial SOFC cost is $9,382 for 2.5kW ($3,753/kW), $1.06M for 1.5MW ($705/kW)8. Stack replacement cost is $887 ($354/kW) for 2.5kW, $294,140 for 1.5MW ($196/kW)9. Grid cost is $0.04/kWh, $2.5/kW demand charge, $1/kW capacity reservation charge10. Fuel cost is $0.50 $/therm11. Battery cost is $250/kWh, 15C discharge, need 175kWh for 1.5MW system12. Inflation 1.9%, Financing interest 6%, SOFC O&M $50/kW per year
Case Net SOFC Capacity
Availability (%)
Cost ($M/yr)
Utilization (%)
Grid 0 99.9% 1.454 N/AA 2.5MW 99.9999% 1.438 52%B 2.5MW 99.98% 1.375 52%C 2.5MW 99.97% 1.148 52%D 2MW 99.58% 0.635 65%Hybrid 1MW 99.9994% 1.159 98.7%
SOFC cost data taken from a DOE report prepared by Battelle. Assessment was scaled from 5kW to 7.5kW. Annual production rates of 10,000 7.5kW units and 100 1.5MW units were assumed. https://energy.gov/sites/prod/files/2014/06/f16/fcto_battelle_cost_analysis_apu_feb2014.pdfResults are in line with 2013 PNNL Report http://www.pnnl.gov/main/publications/external/technical_reports/PNNL-22732.pdf
Fuel Processing6%
Stack10%
Air Supply8%
Heat Transfer18%Electronics
and Controls27%
Instrumentation8%
Assembly7%
De-sulfurization
5% Install11%
PRODUCTION OF 2.5KW AT 10,000 UNITS/YEAR
$100
,000
per
yea
r
10 5
0
5
10
15Reserve capacity chargeDemand charges
Use charges
Fuel cost
O & M
Finance
Grid Only A B C D Hybrid
15/20© Clean Energy Systems Integration Lab, 2017
» LG: estimated 64% DC efficiency with >5year life˃ Degradation of 5mOhm-cm2/khrs ≈ 0.3%
per 1000 hrs
» FCE: demonstrated 68% DC efficiency for 1500 hr˃ Degradation of 0.3-0.5% per 1000 hrs˃ Estimated >50,000 hr life ≈ 6 years
» Ceres Power: demonstrated 56% efficiency˃ Degradation of <0.5% per 1000 hrs
» Bloom: 52.3% efficiency ˃ Taken from 850lb CO2/MWh assuming CH4
input˃ Degradation unknown
https://www.netl.doe.gov/File%20Library/Events/2016/sofc/Lee-Babcock.pdfhttps://www.netl.doe.gov/File%20Library/Events/2016/sofc/Ghezel-Ayagh.pdfhttp://fuelcellseminar.com/wp-content/uploads/Mukerjee-Ceres-Powers-Steel-Cell-Technology.pdf
16/20© Clean Energy Systems Integration Lab, 2017
» Absorption chilling» Chillers as dispatchable load» Building thermal storage» Cold-water thermal storage
17/20© Clean Energy Systems Integration Lab, 2017
» Solar PV / Wind˃ Adds to range over which FC must operate˃ Possibly extends FC life (lower current density)
» Bio-fueled˃ More expensive gas clean-up, but generally unchanged performance
» Carbon capture˃ Can improve net fuel utilization, and often can co-produce H2
˃ SOFC-MCFC hybrid, with about 8:1 power ratio captures >90% CO2
» Reversible SOFC˃ Captures excess renewable energy to create fuel, FC as a battery˃ Improvement over PEM electrolyzer + FC˃ H2 storage issues˃ Methanation as pathway to use existing natural gas infrastructure as
storage
18/20© Clean Energy Systems Integration Lab, 2017
C T
Air Exhaust
ExhaustAir
Heat
100kW
700kW
400kW
FC-GT Hybrid Challenges:1. Air flow rate & temperatures
must match2. Off-design, GT flow doesn’t
change, FC does3. Large plenum volume,
stall/surge risk
19/20© Clean Energy Systems Integration Lab, 2017
» For high efficiency you must operate at high voltage and avoid burning fuel if at all possible
» Possibility for surge power SOFC is interesting, but BoP system must be designed for peak
» Primary benefit of placing SOFC in rack is eliminating power distribution & transforming
+ Negated if a centralized UPS is deployed+ Added heat load to server room
˃ Pros: greater redundancy, same solution anywhere and any scale˃ Cons: requires fuel distribution in addition to electric distribution system,
does not transfer to non-data center applications
» More zero-carbon options with centralized system