Transcript of April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
April 21, 2010
Barbara C. Jordan Elementary School Update
Presented by
• SafetyBarbara Jordan Incident Rate 0.00 with 17,792 hours worked- Construction Industry Average Incident Rate in 2008 was 4.7- (recordable or lost time) = [(number of recordable or lost time injuries) x 200,000]/(number of hours)
• Quality- 8 non-conformance issues written to date and have been remediated
• Schedule- CPM Schedule is developed and contractor comments are being incorporated prior to CPM submission - 21 weather days to date but appears to be incorporated into the schedule logic- Current Completion Date: February 23, 2011
• MBE/WBE Minority Workforce- MBE Goal 15% Barbara Jordan to Date 24%- WBE Goal 5% Barbara Jordan to Date 4%- Minority Workforce Goal 10% Barbara Jordan to Date 47.07%
Barbara C. Jordan Building Underground (Looking North)
Plumbing Underground was started February 16 and completed March 3
Barbara C. Jordan water line was started March 4
(Looking West)
Steel Erection started March
Mock-ups started on March 18 – can be seen from 82nd Street
Load Bearing Masonry started March 19 in the Gym
Looking North
Electrical wall rough-in and underground started March 19
Mechanical hangers started April 9
Safe Entry (Overhead Protection) and recent steel erection progress (South Elevation)
What’s Next?• Concrete Slabs –
- Concrete elevated slab pours will start tomorrow - Concrete slab-on-grade will start April 29 - Concrete slabs to complete by May 21
• Structural Steel –- Roof screen steel will start upon completion of elevated slab pours- Roof deck will be placed after roof screen framing is erected- Gym and Cafeteria bar joists erection will start April 30
• Plumbing – - Water service will be completed to the building- In-wall plumbing rough-in will start in 1st floor restrooms after slab pour
• Electrical –- Electric in wall erection will start with wall framing
• Masonry –- Load Bearing Masonry in Gym and Cafeteria will complete April 30
• Building Enclosure Program- Mock-up sun screen brackets will be installed the week of April 26- Mock-up air/moisture barrier and detailing will be started the week of May 3- Exterior Building studs will start the week of May 3
• Interior - Interior partitions will start the week of May 3