April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

15
April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

Transcript of April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

Page 1: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

April 21, 2010

Barbara C. Jordan Elementary School Update

Presented by

Page 2: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

• SafetyBarbara Jordan Incident Rate 0.00 with 17,792 hours worked- Construction Industry Average Incident Rate in 2008 was 4.7- (recordable or lost time) = [(number of recordable or lost time injuries) x 200,000]/(number of hours)

• Quality- 8 non-conformance issues written to date and have been remediated

• Schedule- CPM Schedule is developed and contractor comments are being incorporated prior to CPM submission - 21 weather days to date but appears to be incorporated into the schedule logic- Current Completion Date: February 23, 2011

• MBE/WBE Minority Workforce- MBE Goal 15% Barbara Jordan to Date 24%- WBE Goal 5% Barbara Jordan to Date 4%- Minority Workforce Goal 10% Barbara Jordan to Date 47.07%

Page 3: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Page 4: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Page 5: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Page 6: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

Barbara C. Jordan Building Underground (Looking North)

Plumbing Underground was started February 16 and completed March 3

Page 7: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

Barbara C. Jordan water line was started March 4

(Looking West)

Page 8: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

Steel Erection started March

Page 9: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

Mock-ups started on March 18 – can be seen from 82nd Street

Page 10: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

Load Bearing Masonry started March 19 in the Gym

Looking North

Page 11: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

Electrical wall rough-in and underground started March 19

Page 12: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

Mechanical hangers started April 9

Page 13: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

Safe Entry (Overhead Protection) and recent steel erection progress (South Elevation)

Page 14: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

What’s Next?• Concrete Slabs –

- Concrete elevated slab pours will start tomorrow - Concrete slab-on-grade will start April 29 - Concrete slabs to complete by May 21

• Structural Steel –- Roof screen steel will start upon completion of elevated slab pours- Roof deck will be placed after roof screen framing is erected- Gym and Cafeteria bar joists erection will start April 30

• Plumbing – - Water service will be completed to the building- In-wall plumbing rough-in will start in 1st floor restrooms after slab pour

Page 15: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.

• Electrical –- Electric in wall erection will start with wall framing

• Masonry –- Load Bearing Masonry in Gym and Cafeteria will complete April 30

• Building Enclosure Program- Mock-up sun screen brackets will be installed the week of April 26- Mock-up air/moisture barrier and detailing will be started the week of May 3- Exterior Building studs will start the week of May 3

• Interior - Interior partitions will start the week of May 3