Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre Tender and Post Tender activities for Construction of Two Tunnel
(Two tubes of 4 lane each ) in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I ) ) and Construction of missing link
with viaducts from km 0/000 to 13/300 and upgradation to 8 lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-Pune
Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
ADDENDUM
Sr.
No
Clause No / Page No. As per Tender Document To be read as
1 Volume I, Section – I;
Instructions to
Consultants, Clause
5.2(ii)(a)(b)(c)(d)/ Page
13&14
ii) In case of JV
a) All the JV members shall fulfil requirement at (a),
Sr. No. 15A of Data Sheet, Vol. II, individually.
b) The Lead Member shall fulfil 60% and the other
member of JV shall fulfil 30% of eligibility
requirements at b(i) and b(ii) of Data Sheet, Vol. II.
c) The Lead Member shall fulfil 60% and the other
member of JV shall fulfil 30% (i.e jointly fulfil by
both partners in JV) of eligibility requirements at at
c(i), at Sr. No. 15A of Data Sheet, Vol. II..
d) The eligibility requirements at c(ii) and c(iii) at Sr.
No. 15A of Data Sheet, Vol. II. shall be satisfied
any partner in JV .
ii) In case of JV
a) The Lead Member shall fulfil 60% and the other member
of JV shall fulfil 30% of eligibility requirements at
(a),b(i) and b(ii) of Sr. No. 15A I of Data Sheet, Vol. II.
b) The Lead Member shall fulfil eligibility requirement at
c(i) at Sr. No. 15A of Data Sheet, Vol. II. and
c) Other member shall fulfil eligibility requirement of One
highway tunnel project of minimum 8m wide or railway
tunnel project of minimum (2 track) of aggregate length
of 2 km.
d) The eligibility requirements at c(ii) and c(iii) at Sr. No.
15A of Data Sheet, Vol. II. shall be satisfied any partner
in JV
2 Volume I, Section – I;
Instructions to
Consultants Clause
5.2.1; Key
Professionals’
qualifications and
competence for the
assignment, Sr. No. 1,
Team Leader /Page no.
16
Experience of construction supervision for at least two,
4-lane highway Bridge projects across Sea / Creek/
Estuary / or Construction supervision for at least 10m
wide Tunnel on Highway project in ICB contract with
FIDIC based contract, each having contract cost not less
than USD 100 million
Experience of construction supervision for at least two, 4-lane
highway Bridge projects across Sea / Creek/ Estuary / River /
or Construction supervision for at least 10m wide Tunnel on
Highway project in ICB contract with FIDIC based contract,
each having contract cost not less than USD 100 million.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre Tender and Post Tender activities for Construction of Two Tunnel
(Two tubes of 4 lane each ) in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I ) ) and Construction of missing link
with viaducts from km 0/000 to 13/300 and upgradation to 8 lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-Pune
Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
3 Volume I, Section – I
Instructions to
Consultants Clause
5.2.2/ Page 18 to 20
The number of points to be given under each of the
evaluation criteria
Modified requirement in clause 5.2.2. Page 18-20 shall be
read as per Annexure -II to the addendum.
4 Volume-I, Annexure -
I; Form EF- II; Details
of the Bidder; 5(d), Sr.
No. 1/ Page no. 30
Has the Bidder / constituent of the Joint Venture been
barred by the Central / any State Government, or any
entity controlled by it, from participating in any project
or otherwise.
"Has the Bidder / constituent of the Joint Venture been barred
by the State Government of Maharashtra, or any entity
controlled by it during the last five years, from participating
in any project or otherwise and the bar subsists as on the Bid
Due Date, would not be eligible to submit the BID, either
individually or as member of a Joint Venture."
5 Volume I, Clause 22.2,/
Page no. 62
The services of the Consultant shall be available till
completion of the work (including DLP) the completion
of Consultancy Service period or until all the claims/
Arbitration / court cases are settled whichever is later.
The services of the Consultant shall be available till
completion of the work (including DLP) the completion of
Consultancy Service period or until all the claims/ Arbitration
/ court cases are settled whichever is later, provided the said
court cases/ claims/ Arbitration has been invoked by the
Contractor or by other Party within the period of the PMC
Contract
6 Volume II, Data Sheet,
Sr. No. 1, The Name of
the Assignment / Page
no. 7
Appointment of General Consultant for Peer-review of
Detailed Project Report, Balance Pre Tender and Post
Tender activities for Construction of Two Tunnel (Two
tubes of 4 lane each ) in km 1/040 to km 2/790
(1.75km) and km 3/440 to 12/360 (8.92km ) for missing
link(Package -I ) and Construction of missing link with
viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under
Capacity Augmentation for Mumbai-Pune Expressway
on EPC mode
Appointment of General Consultant for Peer-review of
Detailed Project Report, Balance Pre Tender and Post Tender
activities for Construction of Two Tunnel (Two tubes of 4
lane each ) in km 1/040 to km 2/790 (Average 1.72km ) and
km 3/440 to 12/360 (Average 8.895km ) for missing
link(Package -I ) and Construction of missing link with
viaducts from km 0/000 to 13/300 (Viaduct 1 – 1.22 km with
at grade approaches, Viaduct 2 – 0.645km & Ramp – 1.0 Km)
and upgradation to 8 lane from km 32/800 to km 39/100 (
6.3Km) (Package-II) under Capacity Augmentation for
Mumbai-Pune Expressway on EPC mode
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre Tender and Post Tender activities for Construction of Two Tunnel
(Two tubes of 4 lane each ) in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I ) ) and Construction of missing link
with viaducts from km 0/000 to 13/300 and upgradation to 8 lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-Pune
Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
7 Volume II, Section-II, Data Sheet, Sr. No.
15(A), c(i)(ii)(iii)/ Page
no. 9
c) The bidder shall have provided consultancy
services for post-tender activities i.e.
construction supervision services (PMC
Services) up to substantial completion of the
project in last 7 financial years for
(i) One Highway tunnel project of minimum
10m wide tunnel of at least 10km length
costing not less than INR 13000 million at
current prices.
(ii) One bridge project (road bridge width
minimum 2+2 lanes) over sea/creek/valley
having viaduct length not less than 600m.
(iii) One bridge / Viaduct (road bridge width
minimum 2+2 lanes) involving cable stay/
Extradosed /suspended with span not less
than 300 m.
c) The bidder shall have provided consultancy services
for post-tender activities i.e. construction supervision
services (PMC Services) up to substantial completion
of the project in last 10 financial years for
(i) One Highway tunnel project of minimum 8m
wide tunnel or Railway tunnel project of
minimum 2 track of at least 4km length.
(ii) One bridge project (road bridge width minimum
2 lanes) over sea/creek/valley/ river having bridge
length not less than 600m.
(iii) One bridge / Viaduct (road bridge width
minimum 2+2 lanes) involving cable stay/
Extradosed /suspended with span not less than
100 m.
8 Volume-II ,Section-II
Data sheet Page -8
Sr No.8 Mode of giving specific assignment by giving
fixed fee.
The bidder has to offer his fixed (lump-sum) fee for
above services.
Sr No.8 Mode of giving specific assignment by giving firm
and fixed tender amount . The bidder has to offer his financial
proposal at A worked out in prescribed form given at C (
summary of Breakup of cost ) and C-1 and C-2 at Annexure
-III to the addendum.
9 Volume II, Section-II,
Data Sheet, Sr. No.
15(A), b(i)/ Page no. 9
The average annual turnover of the bidder for last three
financial years (immediate preceding financial year
2015-16 i.e. for the years 2015-16, 2014-15, 2013-14)
shall be minimum INR.1850 million.
The average annual turnover of the bidder for last three
financial years (immediate preceding financial year 2015-16
i.e. for the years 2015-16, 2014-15, 2013-14) shall be
minimum INR.1500 million.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre Tender and Post Tender activities for Construction of Two Tunnel
(Two tubes of 4 lane each ) in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I ) ) and Construction of missing link
with viaducts from km 0/000 to 13/300 and upgradation to 8 lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-Pune
Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Executive Engineer,
MSRDC Ltd, Mumbai
Superintending Engineer,
MSRDC Ltd, Mumbai
Chief Engineer,
MSRDC Ltd, Mumbai
10 Volume II, Section-II,
Data Sheet, Sr. No.
15(A), b(ii)/ Page no. 9
The bidder shall over the last 7 (seven) financial years
have received payment for consultancy services (pre-
tender and post-tender) provided for construction of
Tunnel or Vaiduct/Flyover in highway sector in Single
Project under EPC/PPP projects, such that is more than
INR 136 millions at current prices
The bidder shall over the last 10 (Ten) financial years have
received payment for consultancy services (pre-tender and
post-tender) provided for construction of Highway Tunnel or
Railway Tunnel (2 Track) or Viaduct/Flyover in highway
sector in Single Project under EPC/PPP projects, such that is
more than INR 100 million at current prices
11 Volume-II ,Section-II
Data sheet Page -10
Sr No.20 Financial Bid . The fees for Pre-tender activities (Phase I & Phase II)
are fixed amounting to INR 20 million. For Post Tender
activities (Phase-III, PMC services) the Bidder shall
quote his lump-sum offer in Financial Bid
The fees for Pre-tender activities (Phase I & Phase II) are
fixed amounting to INR 20 million. For Post Tender activities
(Phase-III, PMC services) the Bidder shall quote his firm
tender amount in Financial proposal at Annexure-III in the
prescribed Form C-1 and C-2
12 Volume II, Clause no.
8, Staffing, Phase Wise
Input in Months, Table/
Page 38 to 43
Staffing, Phase Wise Input in Months, Table Modified requirement in Volume II, Clause no. 8, Staffing,
Phase Wise Input in Months, Table/ Page 38 to 43 shall be
read as per Annexure -I to the addendum .
13 Volume III, Annexure-
III Financial proposal
and C-II
Financial proposal C-1 and C-2 Please refer Annexure -III to the addendum
14 Volume-III Appendix -
C -REMUNERATION
AND PAYMENTS
Volume-III Appendix -C -REMUNERATION AND
PAYMENTS
Modified requirement in Volume III, Appendix-C
REMUNERATION AND PAYMENTS shall be read as per
Annexure -IV to the addendum.
Note: This addendum shall be the part of tender.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
ANNEXURE-I TO ADDENDUM
Sr
.No Designation
Phase wise input in man-months
Proposed
Pier review & Tender Assistance stage
Professional (A) Staff (Pier review &Tender
Assistance)
1. Team Leader 4
2. Procurement Specialist 4
3. Senior Highway Engineer 4
4. Senior Bridge Engineer 4
5. Senior Tunnel Expert 4
6.
Senior Bridge Engineer (Sub-structure &
Foundation and Superstructure) 2
7. Construction Planner 2
8. Cost Estimator 2
9. Environmental Specialist 2
Total Professional A Staff (Pier Review &
Tender Assistance) 28
Professional (B) Staff (Pier Review & Tender
Assistance)
1. Deputy Team Leader 4
2. Geotechnical Engineer 4
3. Sr.Geologist 4
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Total Professional B Staff (TA) 12
Construction Supervision stage CS Post-CS Total
Professional (A) Staff (CS)
1. Team Leader 36 6 42
2. Resident Engineer 36 6 42
3. Geotechnical Engineer (DD review & CS) 36
36
4. Senior Q.A & Q.C. Expert 12
12
5. Highway Engineer (DD Review & CS) 24
24
6. Bridge Engineer / Foundation 1(DD Review)
Voiduct-1 6
6
7. Bridge Engineer / Foundation 2 (DD Review)
Cable stayed bridge 3
3
8. Bridge Engineer / Substructure1 (DD Review)
Vaiduct -1 6
6
9. Bridge Engineer / Substructure2 (DD Review)
Cable stayed bridge 3
3
10. Bridge Engineer / Superstructure1 (DD Review)
Vaiduct-1 6
6
11. Bridge Engineer / Superstructure2 (DD Review)
cable stayed bridge 12
12
12. Tunnel Engineer 1 (Design review) Long tunnel 36
36
13. Tunnel Engineer-2(Design review) Short tunnel 12
12
14. Tunnel Engineer 3 (CS) Long Tunnel 36
36
15. Tunnel Engineer-4(CS) Short tunnnel 36
36
16. Sr.Geologist (Both Tunnel) 36 3 39
17. Architect (DD review, TA & CS) 6
6
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
18. O&M Specialist(FS Review + TA +CS) 12
12
19. Document Specialist (TA) 6
6
20. Bridge Engineer / Foundation (CS) 24
24
21. Bridge Engineer / Foundation (CS 12
12
22. Bridge Engineer / Substructure (CS) 18
18
23. Bridge Engineer / Substructure (CS) 6
6
24. Bridge Engineer / Superstructure (CS) 24
24
25. Bridge Engineer (superstructure) C.S 12
12
26. Survey cum Instrumentation Engineer 36 3 39
27. Material Engineer 36
36
28. Pavement Engineer (CS) 10
10
29. Quantity Surveyor 36 10 46
30. Contract Specialist (CS) 24 10 34
31. Electrical Engineer (DD review & CS) 12 6 18
32. Safety & Security Specialist (CS ) 12
12
33. Environmental Specialist 12
12
34. Mechanical Engineer 12
12
35. Ventilation Expert 5
5
Total Professional (A) Staff (CS) 651 44 695
Professional (B) Staff (CS)
1. Deputy Team Leader 36 14 50
2. Q.A & Q.C. Expert (both packages) 36 8 44
3. Legal Advisor 10 5 15
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
4. Assistant Resident Engineer 36
36
5. Geotechnical Engineer 12
12
6. Highway Engineer (DD Review & CS) 6
6
7. Bridge Engineer / Foundation (DD Review) 6
6
8. Bridge Engineer /Substructure (DD Review) 6
6
9. Bridge Engineer /Superstructure (CS) 12
12
10. O&M Specialist (FS Review, BD, TA&CS) 8
8
11. Document Specialist (TA) 4
4
12. Quantity Surveyor 36 10 46
13. Quantity Surveyor 36 10 46
14. Safety & Security Specialist (CS) 36
36
15. Drainage Engineer 12
12
16. Environmental Specialist 36
36
17. Social Development Specialist 6
6
18. Inspector 1 (Temporary work) 24
24
19. Inspector 2 (Foundation & Substructure ) 24
24
20. Inspector 3 (Foundation & Substructure) 24
24
21. Inspector 4 (Highway) 18
18
22. Inspector 5 (Highway ) 18
18
23. Inspector 6 (Superstructure ) 12
12
24. Inspector 7 (Superstructure ) 12
12
25. Inspector 8 (Tunnel ) 24
24
26. Inspector 9 (Tunnel ) 24
24
27. Inspector 10 (Tunnel ) 24
24
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
28. Inspector 11 (Tunnel ) 24
24
29. Inspector 12 (Tunnel ) 24
24
30. Inspector -13(Tunnel) 24
24
31. Surveyor 1 36
36
32. Surveyor 2 36
36
33. Surveyor 3 36
36
Professional (B) Staff (CS) 718 47 765
Summary of professional Staff required
Total Professional (A) Staff (TA)
28
Total Professional (B) Staff (TA)
12
Total Professional (A) Staff (CS+Post CS )
695
Total Professional (B) Staff (CS+Post CS )
765
Total Professional Staff
1500
Support Staff
1. Office Manager (Main Office) 36 26 62
2. Office Manager 36
36
3. Secretary /Typist (Main Office) 36
36
4. Secretary / Typist 36
36
5. Accountant (Main Office) 36
6 42
6. Accountant 36
36
7. Document Controller (Main Office) 36
18 64
8. Document Controller 36
36
9. CAD Operator 1 36
36
10. CAD Operator 2 36
36
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
11. Office Assistant 1 36 24 60
12. Office Assistant 2 36 24 60
13. IT Specialist for All Offices 36 18 54
Total Support staff 468 116 584
Total Professional (A) & (B) & Support staff
2084
8.1 Scope of work of respective personnel
Detailed information on the major tasks and duties each member of the4 engineering
design team and the construction supervision team shall perform is provided as follows :
Position Major Tasks & Duties
Team
Leader
For Deputy Team
Leader
Post graduate in Civil
Engineering with 15
years of experience as
Resident Engineer and
above in construction
supervision of bridges
1. Lead the detailed design task team. Ensure all deliverables are
prepared in accordance with quality and time constraints.
2. Administrate and supervise site investigation and design and
documentation activities for civil and facility/Equipment
Installation works contracts.
3. Identify appropriate design codes and standards in collaboration
with IRC.
4. Assess road & bridge sections for detailed engineering, including
geometric features, pavement, intersecting roads, its
development plan interface with the main road to a certain
extent as agreed upon. Review available data relating to traffic,
axle loads and pavement strength.
5. Review the need for road safety measures based on the findings
of the feasibility study and road safety review of the road
environment. Identify, design and cost road accident mitigation
measures based on this review.
6. Develop the specifications for road construction in collaboration
with the MSRDC. Assist MSRDC to prepare construction schedules
showing anticipated progress of works by contract package. The
schedules should reflect seasonal climatic effects at the work
sites.
7. Based on the findings of the approved EIA, the road & bridge
designs should incorporate the EMP to mitigate adverse
environmental impacts including those encountered during
construction.
8. Ensure that deliverables comply with relevant GOI technical
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
requirements, Bank conditions and the terms of the assumptions
in the cost benefit analysis.
9. Ensure that the bid documents for road & bridge construction
works including specific provisions to minimize
disruption/damage to local settlements due to construction.
10. With assistance from the Procurement Specialist, prepare road &
bridge construction bid documents.
11. With assistance from the Procurement Specialist, prepare tender
documentation suitable for procurement under ICB with PQ in
accordance with the procurement guidelines of
GOM/MULTILATERAL FINANCIAL
INSTITUTES/GOM/MULTILATERAL FINANCIAL INSTITUTES.
12. Assist the MSRDC to appraise bids as part of the bid evaluation
process.
13. Assist the MSRDC evaluate the capacity of contractors.
14. Prepare monthly progress reports and quarterly progress reports
in a form agreed with the MSRDC and GOM/MULTILATERAL
FINANCIAL INSTITUTES (in PSR), and submit the reports within 10
days before the end of the month or quarter to which they refer.
15. Prepare a final report, which will be a compilation and
condensation of the data presented in regular monthly progress
reports, together with copies of as-built drawings within two
months from the issuance of the defects liability certificate.
16. Prepare a final report for each and all contracts.
Resident
Engineer
1. Lead the construction supervision task teams. Ensure all
deliverables are prepared in accordance with quality and time
constraints.
2. Ensure full and detailed permanent site records, which will
include site correspondence, survey data, quality acceptance
data, site diaries, measurement and certification, minutes of
meetings, and records of all other contractually relevant matters.
3. Certify advance payments in accordance with the contracts when
necessary.
4. Certify interim and final payment certificates for submission to
the employer, and assist the employer in preparing loan
withdrawal documentation for submission to
GOM/MULTILATERAL FINANCIAL INSTITUTES through MSRDC.
5. Ensure that all supervision team members undertake
comprehensive day-to-day field contract supervision, quality
assurance, measurements and administration services at the site.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
6. Provide the contractors with all necessary survey data and
reference for setting out the works.
7. Receive, assess and approve the contractors’ implementation
work plans and programs.
8. Ensure that the rehabilitation works are executed in accordance
with all the provisions of the contract, including those concerning
standards of workmanship, and other safety provisions and
protection of the environment.
Geotechnical
Engineer
Post Graduate in
Geotechnical
Engineering. Length of
profession experience
15 years
1. Provide TOR and other bid documents for the detailed geological
survey for the Detailed Design for the Project and conduct the bid
to select the capable local firms to undertake the geotechnical
survey.
2. Supervise the local contractor’s performance in the quality of the
Work and schedule and give guidance if necessary.
3. Check the output of the geotechnical survey andreport done by
the local contractor.
Sr. Highway
Engineer
1. Ensure full and detailed permanent site records, which will include
site correspondence, survey data, quality acceptance data, site
diaries, measurement and certification, minutes of meetings, and
records of all other contractually relevant matters.
2. Ensure that all supervision team members undertake
comprehensive day-to-day field contract supervision, quality
assurance, measurements and administration services at the site.
3. Provide the contractors with all necessary survey data and
reference for setting out the works.
4. Receive, assess and approve the contractors’ implementation work
plans and programs.
5. Ensure that the highway construction works are executed in
accordance with all the provisions of the contract, including those
concerning standards of workmanship, and other safety provisions
and protection of the environment.
6. Maintain regular estimates of the cost to completion and time to
completion for each contract.
7. Assess time and cost claims submitted by contractors and advise
the PMU for actions to be taken.
8. Ensure that as-built drawings are prepared for rehabilitation
works.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
9. Carry out necessary topographic surveys for design and
documentation works. Establish control points, benchmarks and
reference beacons as required to prepare detailed engineering
design that would enable calculation of construction quantity with
reasonable accuracy (+/- 10%).
10. Develop the specifications for road construction in collaboration
with the PMU. Assist the PMU to prepare construction schedules
showing anticipated progress of works by contract package. The
schedules should reflect seasonal climatic effects at the work sites.
11. Prepare practical and cost-effective pavement designs on the basis
of condition surveys, road alignment, soils, projected traffic levels,
pavement structure studies, and axle load considerations, as
determined from above activities and previous studies.
12. Prepare detailed engineering designs and bills of quantities, and
calculate detailed cost estimates for civil works, broken down into
foreign (direct and indirect) and local components as well as taxes
and duties.
13. Prepare contract drawings for the road works; including road
plans, longitudinal profiles, cross sections, etc. Road plans should
include all existing features and expected land-take based on
plotted earthwork limits if so required.
Sr. Bridge /
Structural
Engineer
1. Review the FS and assess bridge design for detailed engineering,
including the geotechnical data, the applied design codes, design
conditions including control points (eg. Navigation channel,
pipelines etc.), type of the foundation/substructure/superstructure
2. In collaboration with the highway road engineers, develop a
program of site investigation for structures and drainage works.
3. Confirm with MSRDC all design conditions including design code,
control points such as position of public utilities, and cross sections
in collaboration with Highway Engineer
4. Conduct the full basic design, mainly span arrangement, type of
superstructure/substructure/foundation based on the preliminary
structural analysis before the detailed design for the Client’s
approval
5. Conduct the detailed design of the bridges based on the approved
basic design
6. Provide guidance to the CAD operator for preparation of the
drawings and check the drawing prepared by the CAD operator.
7. Review and check the bill of quantities prepared by local bridge
engineer
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
8. Prepare the appropriate technical specifications as a part of the
bid documents for bridge structures, including miscellaneous
facilities.
9. Assist the Procurement Specialist to prepare the PQ conditions and
technical criteria to evaluate the bid documents submitted by the
bidder
10. Prepare the answers to inquiries from the bidder during the
Tender Assistance Period, and evaluate the technical part of the
bid documents together with TL and Procurement Specialist
11. Review the method statement of bridge construction submitted by
the contractor and provide comments or give no-objection.
12. Review and Check the quality of the works at site as well as
inspection sheets prepared by the inspector, and provide
necessary instruction if any.
13. Check the interim payment claim from the contractor to support
the Quantity Surveyor.
14. Provide draft variation order in bridge structure when necessary of
the design change.
15. Support the Claim specialist to analyze the claims for cost increase
or time extension from the contractor
16. Support the Team Leader to issue the Taking over certificate and
completion certificate in terms of bridge structures
17. Participate the meeting with relevant authorities/the
client/contractor when required.
18. Provide a part of the reports to be submitted to the Client in terms
of the bridge works.
19. Ensure full and detailed permanent site records, which will include
site correspondence, survey data, quality acceptance data, site
diaries, measurement and certification, minutes of meetings, and
records of all other contractually relevant matters.
20. Check the as-build drawings submitted by the contractor
21. Provide a seminar or workshop for steel bridge design and
construction as a part of the technology transfer program.
Sr. Tunnel design
Enginner
1.Review the FS and assess Tunnel design for detailed engineering,
including the geotechnical data, the applied design codes, design
conditions including control points (eg. Navigation channel, pipelines
etc.), type of the Support.
2.In collaboration with the highway , Bridge engineers, develop a
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
program of site investigation for Tunnel and drainage works.
3.Confirm with MSRDC all design conditions including design code,
control points such as position of public utilities, and cross sections in
collaboration with Highway Engineer
4.Conduct the full basic design of Tunnel based on the preliminary
structural analysis before the detailed design for the Client’s approval
5.Conduct the detailed design of the Tunnel based on the approved
basic design
6.Provide guidance to the CAD operator for preparation of the
drawings and check the drawing prepared by the CAD operator.
7.Review and check the bill of quantities prepared by local Tunnel
engineer
8.Prepare the appropriate technical specifications as a part of the bid
documents for T, including Tunnel structures and facilities.
9.Assist the Procurement Specialist to prepare the PQ conditions and
technical criteria to evaluate the bid documents submitted by the
bidder
10.Prepare the answers to inquiries from the bidder during the Tender
Assistance Period, and evaluate the technical part of the bid
documents together with TL and Procurement Specialist
11.Review the method statement of Tunnel construction submitted by
the contractor and provide comments or give no-objection.
12.Review and Check the quality of the works at site as well as
inspection sheets prepared by the inspector, and provide necessary
instruction if any.
13.Check the interim payment claim from the contractor to support
the Quantity Surveyor.
14.Provide draft variation order in Tunnel structure when necessary of
the design change.
15.Support the Claim specialist to analyze the claims for cost increase
or time extension from the contractor
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
16.Support the Team Leader to issue the Taking over certificate and
completion certificate in terms of bridge structures
17.Participate the meeting with relevant authorities/the
client/contractor when required.
18.Provide a part of the reports to be submitted to the Client in terms
of the tunnel works.
19.Ensure full and detailed permanent site records, which will include
site correspondence, survey data, quality acceptance data, site diaries,
measurement and certification, minutes of meetings, and records of
all other contractually relevant matters.
20.Check the as-build drawings submitted by the contractor
21.Provide a seminar or workshop for Tunnel design and construction
as a part of the technology transfer program.
Quality Assurance &
Quality Control
Expert
- Graduate Civil
Engineering
- Overall experience
15 years or more
- Relevant experience
10 years or more
1. Overall monitoring the construction activities in respect of the
quality of the work.
2. Ensure that the construction materials conform to the quality
norms specified in the Codes / specifications in the bid
documents.
3. Ensure that field / laboratory tests regarding the quality control
are carried out as per the norms / procedures specified in codes /
specifications in the bid documents.
4. Check the results of the field / laboratory tests regarding the
quality control and take remedial actions in case of any non-
conformity.
5. Prepare and submit the periodic Quality Control Reports to
MSRDC.
6. Conduct workshops for the site Engineers / labours to update
them about the Quality Assurance & Quality Control procedures
so as to ensure that the QA & QC norms are adhered to.
Legal Advisor
- Graduate in any
discipline with
Degree in Law
- Experience as Legal
Advisor for
Infrastructure
1. Periodically review the project proceedings from point of view of
violation of any act / law and advice MSRDC accordingly.
2. In case of any litigation, appeal in court of law/tribunals
/commissions etc. in respect of the project;advice &prepare
affidavits / rejoinders / submissions etc.
3. Attend meetings with the lawyer appointed by MSRDC in respect
of the litigation / appeal.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
projects is preferred 4. Attend the hearings in the tribunal / court / commissions.
5. Preparation of the compliance of orders of tribunal / court.
Architect 1. Review the FS and assess building plan for Operation &
Maintenance for detailed engineering, including the geotechnical
data. the applied design codes, location of the facility/building,
and requirements of the spaces for the building/facility
2. Develop a program of site investigation forbuilding/facility works.
3. Confirm with MSRDC all design conditions including design code,
requirements of building/facility design
4. Conduct the full basic design, mainly room arrangement,
necessary equipment and facilities, materials to be used before
the detailed design for the Client’s approval
5. Conduct the detailed design of the building/facility for Operation
& Maintenance based on the approved basic design
6. Provide guidance to the CAD operator for preparation of the
drawings and check the drawing prepared by the CAD operator.
7. Review and check the bill of quantities prepared by local Architect
8. Prepare the appropriate technical specifications as a part of the
bid documents for building structures/facility/equipment,
including miscellaneous facilities.
9. Assist the Procurement Specialist to prepare the PQ conditions
and technical criteria to evaluate the bid documents submitted by
the bidder
10. Prepare the answers to inquiries from the bidder during the
Tender Assistance Period, and evaluate the technical part of the
bid documents together with TL, Procurement Specialist and ITS
specialist and O&M specialist
11. Review the method statement of building construction submitted
by the contractor and provide comments or give no-objection.
12. Review and Check the quality of the Works at site, inspection
sheets prepared by the inspector, and work schedule and provide
necessary instruction/comments, if any.
13. Check the interim payment claim from the contractor to support
the Quantity Surveyor.
14. Provide draft variation order in building works when necessary of
the design change.
15. Support the Claim specialist to analyze the claims for cost
increase or time extension from the contractor
16. Support the Team Leader to issue the Taking over certificate and
completion certificate in terms of building works
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
17. Participate the meeting with relevant authorities/the
client/contractor when required.
18. Provide a part of the reports to be submitted to theClient in terms
of the building works.
19. Ensure full and detailed permanent site records, which will
include site correspondence, survey data, quality acceptance
data, site diaries, measurement and certification, minutes of
meetings, and records of all other contractually relevant matters.
20. Check the as-build drawings submitted by thecontractor.
Document/
Procurement /
Contract
Specialist
1. Assist the MSRDC to design, administrate and monitor all
procurement activities to ensure compliance with agreed
procurement frameworks.
2. Prepare Pre-Qualification (PQ) documents for ITS & O&M package
in compliance with GOM/MULTILATERAL FINANCIAL INSTITUTES
and Indian procurement guidelines. PQ documents will be
prepared for ICB for major works.
3. Assist the MSRDC in Pre-Qualification in accordance with the PQ
documents and prepare PQ reports for approval of MSRDC and
JTCA.
4. Prepare bid documents for ITS and O&M package in compliance
with GOM/MULTILATERAL FINANCIAL INSTITUTES procurement
guidelines. Bid documents will be prepared for ICB for major
works
5. Assist the MSRDC in the preparation of invitation for bids,
evaluation of bids received, and award of civil works and
equipment and facility installation contracts.
6. Evaluate the claims submitted by the contractor with support
from the engineers and provide a draft answers to Team Leader.
7. Support. to the Team Leader to issue the variation order to the
contractor and various certificates to the contractor
8. Support MSRDC to deal with DAB discussionwith the contractor’s
claim
Sr. Material
Engineer
- Graduate in Civil
Engineering /
Material Sciences
- Experience of 10
years or more
1. Investigate the suitability of locally available construction
materials, and where necessary, locate new quarries and borrow
pits and assess the quality and quantity of materials and hauling
distance.
2. Approve the equipment list for laboratory submitted by the
contractor
3. Approve the materials to be used for the Works submitted by the
contractor by checking the test results
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
4. Participate in the material testing at laboratory or factory in order
to Confirm the test procedure and its result.
5. Ensure full and detailed permanent site records, which will
include site correspondence, survey data, quality acceptance
data, site diaries, measurement and certification, minutes of
meetings, and recordsof all other contractually relevant matters.
Pavement
Engineer
- Graduate in Civil
Engineering
- Experience of 10
years or more
1. Review the results of traffic demand forecast in FS to estimate the
accumulated axle loads to a level of accuracy necessary
2. Determine the appropriate pavement structure with
specifications to fulfill the requirements identified through the
review of the FS
3. Prepare the technical specifications as a part of the bid
documents and provide the answers to inquiries from the bidder
4. Review the method statement of pavement works submitted by
the contractor and provide comments or give no-objection.
5. Review and Check the quality of the works at site as well as
inspection sheets prepared by the inspector, and provide
necessary instruction if any.
6. Check the interim payment claim from the contractor to support
the Quantity Surveyor.
7. Provide draft variation order in pavement works when necessary
of the design change.
8. Support the Claim specialist to analyze the claims for cost
increase or time extension from the contractor
9. Support the Team Leader to issue the Taking over certificate and
completion certificate in terms of bridge structures
10. Participate the meeting with relevant authorities/the
client/contractor when required.
11. Provide a part of the reports to be submitted to the Client in
terms of the pavement works.
12. Ensure full and detailed permanent site records, which will
include site correspondence, survey data, quality acceptance
data, site diaries, measurement and certification, minutes of
meetings, and records of all other contractually relevant matters.
13. Check the as-build drawings submitted by the contractor.
Quantity Surveyor
1. Ensure full and detailed permanent site records, which will
include site correspondence, survey data, quality acceptance
data, site diaries, measurement and certification, minutes of
meetings, and records of all other contractually relevant matters.
2. Review and check the inspection sheets submitted by the
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
inspectors
3. Review and check the interim payments and finalpayment claims
submitted by the contractor,particularly the bill of quantities
done by thecontractor
4. Provide or review the unit price for new work items when
necessary
5. Support the Claim Specialist to evaluate the claimssubmitted by
the contractor.
Electrical
Engineer
- Graduate in
Electrical
Engineering
- Experience of 10
years or more
1. Review the FS and assess electricity supply and lighting design for
detailed design, including the applied design codes, design
conditions including environmental requirements, and type of
lighting.
2. In collaboration with the highway road engineers, develop a
program of site investigation for confirming the electricity supply
points.
3. Confirm with MSRDC all design conditions including design code
and requirements
4. Conduct the full basic plan for electricity supply and lighting
before the detailed design for the Client’s approval
5. Conduct the detailed design of the lighting and electricity supply
based on the approved basic design
6. Provide guidance to the CAD operator for preparation of the
drawings and check the drawing prepared by the CAD operator.
7. Review and check the bill of quantities prepared by local electrical
engineer
8. Prepare the appropriate technical specifications as a part of the
bid documents for lighting design, includingmiscellaneous
facilities.
9. Prepare the answers to inquiries from the bidder during the
Tender Assistance Period, and evaluate the technical part of the
bid documents together with TL and Procurement Specialist
10. Review the method statement of lighting equipment and facility
works submitted by the contractor and provide comments or give
no-objection.
11. Review and Check the quality of the works at site as well as
inspection sheets prepared by the inspector, and provide
necessary instruction if any.
12. Check the interim payment claim from the contractor to support
the Quantity Surveyor.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
13. Provide draft variation order in bridge structure when necessary
of the design change.
14. Support the Claim specialist to analyze the claims for cost
increase or time extension from the contractor
15. Support the Team Leader to issue the Taking over certificate and
completion certificate in terms of bridge structures
16. Participate the meeting with relevant authorities/the
client/contractor when required.
17. Provide a part of the reports to be submitted to the Client in
terms of the bridge works.
18. Ensure full and detailed permanent site records, which will
include site correspondence, survey data, quality acceptance
data, site diaries, measurement and certification, minutes of
meetings, and records of all other contractually relevant matters.
19. Check the as-build drawings submitted by the contractor
Mechanical Engineer
- Graduate in
Mechanical
Engineering
- Experience of 10
years or more
1. Verification of Machinery of the contractor
2. Safety Analysis during drill and blast of Tunneling work
3. Design And Analysis of Centering/ Shuttering for lining of Tunnel
4. Co-ordination with Ventilation Expert and Electrical Activities
during Execution and Post Execution Activities
5. Design of all fabrication work during construction
6. Liasoning with Government of Maharashtra in respect of
Mechanical permission required during the execution of the work
Ventilation Expert
- Graduate in
Mechanical
Engineering and
Specialization in
Ventilation of
underground
structures
- Experience of 10
years
1. Design and Analysis of Connecting shaft in the Tunnel
2. Design of Exhaust Facilities and analysis of atmospheric pressure in
the Tunnel
3. Co-ordination with Electrical and Mechanical Engineer
4. Design and analysis of Ventilation Shaft.
5. Safety analysis for smooth functioning of the Tunnel
Safety & Security
Specialist
6. Ensure that the contractors provide sufficient safety devices and
sign boards for own safety as well as safety of general traffic and
pedestrians through the review of the method statement and
periodical site patrol.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
7. Ensure that the contractors provide sufficient safety devices to
the construction Engineers, subordinate staff &labourworking on
the site.
8. Ensure adherence to the safety norms prescribed in the relevant
codes / specifications in the bid documents.
9. Advise the Social Development Expert and Environmental Expert
to undertake environmental monitoring and take necessary
actions. Also ensure the incorporation of the findings and
supportingdata into the project completion reports.
Environmental Expert 1. Update EMP as appropriate; incorporate necessary technical specifications with design and contract documentation;
2. Assist MSRDC in obtaining the certificate for mangrove cutting from Mumbai High Court in accordance with the planned implementation schedule;
3. Assist MSRDC to implement the measures identified in the Projects Environmental Management Plan (EMP).
4. Monitor the effectiveness of EMP (and CCEP) and negative impacts on environment caused by the construction works and provide technical advice, including a feasible solution, so that MSRDC can improve situation when necessary;
5. Assist MSRDC in monitoring the compliance with conditions stated in the EMP and the requirements under EMP and GOM/MULTILATERAL FINANCIAL INSTITUTES Environmental Guidelines;
6. Assist MSRDC in facilitating stakeholder’s participation (including focus group discussions for vulnerable PAPS) and providing feedback their comments on EMP and EMOP;
7. Provide skills transfer with respect to environment, through workshops, seminars, and on-the-job training, to MSRDC staff. Review of EMP and revise it if required so.
8. At the completion of the Project, (21) undertake final environmental monitoring and evaluation against the set indicators, (b) evaluate sustainability of environmental benefits associated with road & bridge construction, taking into account both positive and negative impacts associated with roads, and (c) prepare an evaluation report for eachsubproject.
Drainage
Engineer
- Graduate in Civil
Engineering having
Experience of 5
years or Diploma in
1. Review the FS and assess drainage design for detailed design, including the applied design codes, design conditions such as design rainfall intensity, and environmental requirements on the mudflat
2. In collaboration with the highway road engineers, develop a program of site investigation for confirming the flow end treatment.
3. Confirm with MSRDC all design conditions including design code and requirements
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
Civil Engineering
having Experience of
10 years
4. Conduct the full basic plan for drainage system on the road and bridge or buildings before the detailed design for the Client’s approval
5. Conduct the detailed design of the drainage system based on the approved basic design
6. Provide guidance to the CAD operator for preparation of the drawings and check the drawing prepared by the CAD operator.
7. Review and check the bill of quantities prepared by local drainage engineer
8. Prepare the appropriate technical specifications as a part of the bid documents for drainage design, includingmiscellaneous facilities.
9. Prepare the answers to inquiries from the bidder during the Tender Assistance Period, and evaluate the technical part of the bid documents together with TL and Procurement Specialist, if necessary
10. Review the method statement of drainage and facility works submitted by the contractor and provide comments or give no-objection.
11. Review and Check the quality of the works at site as well as inspection sheets prepared by the inspector, and provide necessary instruction if any.
12. Check the interim payment claim from the contractor to support the Quantity Surveyor.
13. Provide draft variation order in drainage works when necessary of the design change.
14. Support the Claim specialist to analyze the claims for cost increase or time extension from the contractor
15. Support the Team Leader to issue the Taking over certificate and completion certificate in terms of bridge structures
16. Participate the meeting with relevant authorities/the client/contractor when required.
17. Provide a part of the reports to be submitted to the Client in terms of the drainage works.
18. Ensure full and detailed permanent site records, which will include site correspondence, survey data, quality acceptance data, site diaries, measurement and certification, minutes of meetings, and records of all other contractually relevant matters.
19. Check the as-build drawings submitted by the contractor
Inspectors
Graduate in Cvil
Engineering with 5
years construction
supervision
1. Measure the day-to-day quantities at site and confirm with the foreman or site supervisor of the contractor.
2. Keep and maintain full and detailed measurement records, which will include quantity measurement data, site diaries and other records.
3. Assist the engineer’s representative for managing quantity and cost.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
experience in
bridge/Tunnel
projects OR
Diploma in Civil
Engineering with 15
years construction
supervision
experience in
bridge/Tunnel
projects
4. Assist MSRDC for assessing contractor’s claims. 5. Undertake day-to-day field contract supervision, quality control
and measurements at the site. 6. Keep full and detailed permanent site records, which will include
site correspondence, survey data, quality acceptance data, daywork records, site diaries, measurement and other field records.
7. Prepare data presented in regular monthly progress reports. 8. Provide measurement and inspection data required for interim
payments. 9. Provide the contractors with all necessary survey data and
reference for setting out the works. 10. Ensure that the rehabilitation works are executed in accordance
with all the provisions of the contract, including those concerning standards of workmanship, and other safety provisions and protection of the environment.
11. Ensure that the laboratory of the engineer is equipped in accordance with the technical specifications.
12. Attend and supervise so that all day-to-day field and laboratory quality tests are conducted in accordance with the technical specifications and instruction of the engineer’s representative.
13. Approve or disapprove the materials to be used by the contractors in accordance with the contract and technical specifications.
14. Approve or disapprove the works executed by the contractors in accordance with the contract and technical specifications.
15. Keep and maintain full and detailed permanent site and laboratory records, which will include test data, quality acceptance data, site diaries and other qualityrelated data.
16. Assist in preparing quality assurance reports to be submitted monthly or attached to the interim certificate, if so required.
Surveyor
- Graduate in Civil
Engineering having
Experience of 5
years or Diploma in
Civil Engineering
having Experience of
10 years
1. Provide TOR and other bid documents for the detailed topographical survey for the Detailed Design for the Project and conduct the bid to select the capable local firm to undertake the topographical survey.
2. Supervise the local surveyor’s performance in the quality of the work and schedule and give guidance if necessary.
3. Check the output of the topographical survey done by the local surveyor to confirm the correctness.
4. Provide the necessary information about the coordinates related to the alignment and ROW of the Project.
5. Check the correctness of the coordinates of temporary benchmarks and alignments set by thecontractors
Construction
Planner
1. Review the FS and assess construction plan for further detailing,
including construction methods to be applied, period of each work
item, availability of equipment and machinery.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Position Major Tasks & Duties
- Graduate in Civil
Engineering or
Construction
Management
- Experience of 10
years or more
2. Develop a program of site investigation and interviews to the
contractor to confirm the available equipment and machinery, and
construction period for each work item.
3. Provide the construction plan on the basis of the output of the
detailed design, including formulation of temporary facility for the
permanent work.
4. Support the Procurement Specialist to prepare a part of the bid
documents
5. Prepare the answers to inquiries from the bidder during the
Tender Assistance Period, and evaluate the technical part of the
bid documents together with TL and Procurement Specialist, if
necessary
Cost Estimator
- Graduate in Civil
Engineering having
Experience of 5
years or Diploma in
Civil Engineering
having Experience of
10 years
1. Review the FS and assess cost estimate for further detailing,
including work item, construction methods to be applied, unit
price of each work, and bill of quantities
2. Conduct interviews/inquiries to the contractor/supplier to confirm
the available equipment and machinery, unit price of each
material,
3. Update the cost estimate on the basis of the output of the detailed
design including temporary facility plan and provide the final
Engineer’s estimate
4. Evaluate the technical part of the bid documents together with TL
and Procurement Specialist, if necessary
O&M Specialist
Graduate in Civil
Engineering and 10
years experience in
bridge/highway O&M
1. Review of O&M documentation
2. Review O&M activities and inspection, supervision, monitoring and
control
Document Specialist
Graduate and 5 years
experience in
document control
1. Oversee and Operate and Maintain the document management
system for all contracts.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
ANNEXURE - II TO ADDENDUM
5.2.2 The number of points to be given under each of the evaluation criteria are as below:-
(I) Firms relevant experience in last 10 years (preceding financial year 2015-16) 25 points Points
(a) Average annual turnover for last three years
From INR 1500 million up to INR 2000 million 03
From INR 2001 million up to INR 2500 million 04
More than INR 2501 million 05
Total 05 Points
In case of JV, for working out Turnover, weightage for Lead Member and
weightage for Other Member considered for evaluation shall be in proportion of
their share in proposed JV
(b) Experience of consultancy related Assignments
(Eligibility requirements b (ii) and c (i) to (iii) sr. no. 15A, of Data
Sheet, Vol. II.)
20 Points
(i) Received payments for construction of Tunnel or Railway
Tunnel Project (2 track) or Vaiduct /Flyover in highway
sector in single project under EPC /PPC in last 10 years
5
From INR 100 million up to INR 150 million 3
From INR 151 million up to INR 200 million 4
More than INR 201 million 5
In case of JV, for working out Total Payments received,
weightage for Lead Member and weightage for Other
Member considered for evaluation shall be in proportion of
their share in proposed JV.
(ii) Post tender services (PMC) for One Highway tunnel project
of minimum 8m wide tunnel or Railway tunnel project of
minimum 2 track of at least 4km length in last 10 financial
years
5
From 4 km up to 6 km 3
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
From 6 km up to 8 km 4
More than 8 km 5
If the work submitted against this eligibility criterion is
carried out in JV, then the member claiming experience shall
be any Member and shall hold 35% or more share in such JV.
(iii) Post tender services (PMC) for One bridge project (road
bridge width minimum 2 lane) over sea/creek/valley/ river
having bridge length not less than 600m in last 10 financial
years
5
length from 600 m up to 1000m 3
length from 1001 m up to 1500 m 4
length more than 1501 m 5
If the work submitted against this eligibility criterion is
carried out in JV, then the member claiming experience shall
be any Member and shall hold 35% or more share in such JV.
(iv) Post tender services (PMC) in last 10 financial years for One
bridge / Viaduct (road bridge width minimum 2+2 lanes)
involving cable stay/ Extradosed /suspended with span not
less than 100 m over sea/ creek/ estuary/ river/ water body
5
Cable stayed span 100-150m 3
Cable stayed span 151-200 4
Cable stayed span more than 201 5
In case of JV, number of projects of JV shall be addition of
projects by Lead Member and Other Member in proportion of
their share in proposed JV
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Annexure III to Addendum 3
Annexure-III
Name of Work: - Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each) in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I ) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8 lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-Pune Expressway on EPC mode
FINANCIAL PROPOSAL
A) Financial Offer
I/We _____________________________________ Consultant/ Consultancy Firm am / are
hereby quoting the offer for the work of providing Consultancy as per the scope of Work,
terms and contract conditions covered in the Bid Document (Volume I, Volume II and
Volume III). The offer is inclusive of all applicable taxes excluding statutory service taxes*.
(In Figures & Words)
Our Offer for Phase III consultancy services as stipulated in the Bid Document in Indian Rupees is
INR _______________________ (In Figures) (INR _____________ (In words)).
Notes:-
1) Consultancy fee for Phase I and Phase II Peer-review and balance Pre-tender
activities as stipulated in the Bid Document shall be fixed amount of INR 20
million.
2) The Bidder shall quote his offer for Phase III consultancy services only. The same
shall be derived from the amount from the breakup of Man-Month in Annexure III
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
(C-II)
* The Service tax will be reimbursed at prevailing rate.
Signature of Consultant : (Authorized Representative)
(along with seal of bidder)
Full Name :
Designation :
Address :
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Annexure-III-(Continued)
C. II) Breakup of Man- Months for Phase III (Amount in INR)
Stage Description Man-Month
Input
Rate (including
all allowances)
**
Cost Remarks
Phase – III Key Personnel
1
2
.
11
Sub-professional Staff
1
2
.
14
Support staff
1
2
DLP
(5 years)
Staff Proposed
1
2
.
Total Shall match with
cost of man-
months shown in
table C above for
Phase III
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
** No escalation shall be payable for original base period plus six months extended period
Signature : (Authorized Representative)
Full Name :
Designation :
Address :
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
ANNEXURE-IV TO ADDENDUM
Name of Work: - Appointment of General Consultant for Peer-review of Detailed Project Report,
Balance Pre Tender and Post Tender activities for Construction of Two Tunnel
(Two tubes of 4 lane each) in km 1/040 to km 2/790 (1.75km ) and km 3/440 to
12/360 (8.92km ) for missing link(Package -I ) and Construction of missing link
with viaducts from km 0/000 to 13/300 and upgradation to 8 lane from km
32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
APPENDIX “C”
REMUNERATION AND PAYMENTS
1.0 The final offer of the Consultant after negotiation is INR. …………………………………
(In words INR. ……………………………………………………………………………….).
2.0 In consideration of the performance of the contract, MSRDC shall pay to the Consultant as
consideration for his services as set forth below:
2.1 For Phase III the total fees payable would be based on the above offer accepted
during negotiations.
3.0 Breakup of Total Fees:
The fee (offer) quoted by the Bidder is for Phase III and for Phase I & II the fixed fees (total fee)
shall be INR 2,00,00,000/- (INR 20 million) inclusive of all applicable taxes excluding Service
Tax.
3.1 Payment for Pre Tender Activities (Phase-I & II)
(i) The fees would be paid in the following stages and break up of total fees shall be as
given below
Payment Schedule - Phase-I &II: Pre-tender activities
Sr.
No. Phases
% of Total Fee
of Phase I & II
Phase -I
1. Peer review of TEFS Reports prepared by previous consultant and submission of
comments for revisions, modifications etc. required including necessary revisions/
20%
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
Sr.
No. Phases
% of Total Fee
of Phase I & II
modifications, compilation of data, generating soft copies etc.
2. Traffic surveys, analysis and prediction of traffic on VBSL 5%
3. Review of cash flow based on traffic prediction, Financial assistance, submission of
proposal for approval of GoM, VGF proposal to GoI,
5%
4. Balance Pre Tender Activities as per scope of work 20%
Phase -II
5. Submission of Draft Bid Document (RFP) for appointment of Construction
Contractor on EPC basis.
10%
6. Submission of final Bid Document(RFP) for Contractor , invitation of bids for
Construction Contractor on EPC basis, , Bid process Management
20%
7. On submission and approval of Bid evaluation report (for appointment of
construction Contractor )
10%
8. Bid acceptance (issue of LOA), Signing the Contract agreement, issue of
Work Order. (for appointment of Contractor )
10%
Total 100%
Note:- Further breakup of payment schedules as per above broad breakup may be prepared by
the consultant in consultation of MSRDC.
(ii) Basic time period for Balance Pre Tender consultancy activities in Phase I&II shall be as
stipulated in Clause 13 of Appendix II of Bid volume II. Fees payable shall remain
unchanged during above basic period of 3 months and an additional handholding period
of 3 months. Fees shall be due and payable only on completion of stages as
specified in clause 3.1(i), 3.2 (ii) above. The Consultant shall provide key professional for
additional three (3) months “hand holding period” above for which no additional
payment shall be made.
During the period of consultancy, MSRDC may ask the Consultant to demobilize
and remobilize staff, in part or full, with a fifteen (15) days written notice. No extra
payment / compensation / claims shall be entertained on account of such demobilization
and remobilization.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
(iii) Penalty for Delay in Phase – I & II: Pre tender Activities:
The period for pre tender activities is specified in data sheet. If the consultant
does not complete the pre tender activities within the period as stipulated in the
data sheet, then payment due towards the Phase – I & II of pre
tender activities will be reduced by 2% for every additional week unless valid
extension is given by competent authority. If subsequent additional month is
consumed for pretender activities additional 2% shall be reduced. Such reduction shall be
limited to the 10% of the total fees.
(iv) Extension of time limit (Phase – I & Phase -II):
a) If there is genuine (for reasons not attributable to the Consultant) delay to
complete the pre tender activities by the Consultant on account of reasons beyond his
control, then the consultant will be entitled to extension for further period as approved
by the MSRDC for which payment over and above fixed amount of Rs. 30 Million as per
Data Sheet, Vol. II shall be payable on account of extension of time limit for Phase I and
Phase II by mutual agreement between MSRDC and the Consultant.
b) The reduction in the fees if any for want of valid extension made for the delay may be
released only after the valid extension is granted.
c) The decision of MSRDC for granting extension and penalty shall be final and binding.
The designate authority of MSRDC for granting extension and penalty shall be as per
Data Sheet in Vol. II.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
3.2 Payment for Post Tender Activities (Phase-III)
i) The post tender activities (Phase-III) shall come into effect from the date of work order
(award of construction contract) and shall be for the period as mentioned in Data
Sheet.
ii) The payment for this activity and during its period shall be at the percentage rates as
prescribed below:-
Payment Schedule - Phase-III - Post-tender activities
Sr.
No. Stages
% of Total
amount worked
out from actual
deployment
staff in Phase
III
1.
During actual execution of the work on a monthly basis as per
actual deployment of staff spread over a period of construction up
to issue of completion certificate
85 %
2. Preparation and submission of final bills of work with as built
drawings and maintenance Manual. 5 %
3. During defect liability period (on a quarter basis spread over entire
defect liability period on pro-rata basis). 5 %
4. On completion of Consultants assignment i.e., at the end of defect
liability / maintenance period. 5 %
Total 100%
3.2.1 Payment of amount during actual execution (Phase III) – Post Tender activities
The Phase-III payment for Consultancy (for the post tender activity) shall be divided into
two categories and paid in the following manner and ratio
a) Time related payment = 70%
b) Progress related payment = 30%
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
A) Time related payment
The time related payment shall be payable as below:
1) Payment to be paid every month
(a) The monthly payment shall be payable to the consultant as per the above formula for the
scheduled period of completion plus further period of 6 months if a valid extension is
given to the consultant, subject to conformance to TOR.
(b) If a further valid extension is given to the consultant, the time related payment payable to
the consultant every month beyond original time period plus six months extended period
subject to conformance to TOR, shall be, increased by 8% per annum. Other payment will
as per formula.
B) Progress Related Payment
The progress related payment would be paid as below: Payment to be paid every month
Where, the cumulative % progress of work done by agency shall exclude the payment made
towards price escalation, Extra Items/ variation, Mobilization Advance and Machinery Advance.
Similarly the recovery of Mobilization Advance and Machinery Advance will not be reflected in
working out the fees due to the consultant. The progress related payment shall not exceed by 30%
deployment actualon based billingmonthly ofAmount
100
85
100
70
deployment actualon based billingmonthly ofAmount
(planned)month theupto work
of progress % eCummulativ
(actual)month theuptowork
of progress % eCummulativ
100
85
100
30
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
3.2.2 Release of 15% withheld amount:
i) Payment of 5% amount withheld from monthly invoices against item no 2 of
payment schedule/ phase III/ post tender activities shall be released after submission of
final bills of work with as built drawings and maintenance manual by the construction
contractor.
ii) Payment of 5% amount withheld from monthly invoices against item no 3 of
payment schedule/ phase III/ post tender activities shall be paid in equal quarterly
installments over 5 years defects liability period
iii) Payment of 5 % amount withheld from monthly invoices against item no 4 of
payment schedule/ phase III/ post tender activities shall be paid at the end of defects
liability period.
iv) The payment towards monthly deployment of staff during the defects liability period
shall be made on the basis of actual deployment of professional staff.
4.00 Payment of fees after defect liability:
After the defect liability period if for the purpose of settlement of claims or cases the services
of S.R.E./ R.E. are to be made available to MSRDC. The payment for such services shall be at
0.15 times the man month rate for SRE (As quoted under variation) with including travel and other
incidental expenses per visit shall be payable to the consultants for every such visit. The
maximum period up-to which the consultant has to provide his services, for settlement of
court cases / claims shall be 5 years after defect liability period.
5.00 Payment For Work which are Not Covered under Offer of Consultancy
The following payments will be made separately if the activities are ordered:
i) Cost of any sub consultancy / appointment of expert required for the services which
are approved in writing by MSRDC.
ii) Cost of such further items as may be required by the consultants for the purpose of
the services as agreed in writing by MSRDC.
iii) Payment to the Consultant for the staff / provisional facility over and above stipulated in
Bid document by the Consultant to MSRDC shall be at the rate quoted under schedule
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
of variation.
6.00 Penalty for Substitution or Non Provision of key personnel
If the consultant substitutes the following key personnel without prior approval of MSRDC or
MSRDC wants the consultant to replace the personnel on ground of misconduct or
inefficiency the penalty for replacement shall be as under.
1. For Each Key Personnel except Team Leader– Reduction of Consultancy fee will be
equal to balance period in month x 10% x Rate as per schedule of variation for Senior
Resident Engineer.
2 . In case of Team Leader- if such contingency arises the reduction in fee will be twice
that of the above.
If the same Key Professional staff (as substituted) not provided for the next
month/months the reduction in monthly fees shall be increased by MSRDC and action
shall be initiated as per stipulations of the Bid Document.
6.1 If the Consultant fails to provide Key Professionals / support staff as stipulated in Clause
No.8, Appendix ‘A’ of Vol. II of the Bid Document, monthly fee for that month during
which such Key Professional / support staff was not provided shall be reduced as below.
Team Leader : 8%
Senior Resident Engineer / Senior Bridge Engineer : 7%
Other remaining each Key Professional : 2%
If the same Key / Sub Professional staff not provided for the next month/months the reduction
in monthly fees shall be increased by MSRDC and action shall be initiated as per stipulations
in the Bid Document.
8.00 i) If the work is suspended by MSRDC / Contractor, then for first 3 months, the time
related payment would be made to the agency as per the above said time related formula,
provided the consultant retains the minimum strength of the personnel as given in
data sheet for the first 3 months. Subsequently he will be paid @ 30 % of the time
related monthly payment towards the selected services which he would offer during the
period under suspension.
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
ii) The time related fee would be restored when the suspension is revoked.
iii) In case progress of the work during Construction period is not as per accepted time
schedule of the project, MSRDC reserves the right to direct the Consultant to curtail
key personnel / professional staff to be deployed with proportionate decrease in
Consultancy fees as per clause 8.1, Appendix ‘C’ of Vol.-III or as may be decided by
MSRDC from time to time.
9.00 Limitations of fees due to default of Consultant
If there is any extension in time limit in original schedule, to the period of completion and
valid extended period of completion is required to be granted to the contractor, because of the
default on the part of the Consultant, then for such period the provision of granting the monthly
payment as per the given formula or further increase (as stipulated for extension beyond 6
months) shall not be paid. Instead, for this period, as the consultant is under default his time
related monthly payment shall be reduced by 20 % for the period of default.
10.00 Mode of billing and payment
Billing and payments in respect of the Services shall be made as follows:
a) As soon as practicable as and not later than fifteen (15 days) after the end of each
calendar month during the period of the Services, the Consultants shall submit to
MSRDC, in duplicate, the bill for the services rendered by him. In case of additional
payment under clause 7, the necessary documents in support of claim shall be furnished.
Each such separate monthly statement shall distinguish that portion of the total eligible
costs which pertains to remuneration from that portion which pertains to reimbursable
expenditures.
b) The MSRDC shall cause the payment of the Consultants periodically as given above the
payment within thirty (30) days after the receipt by MSRDC of the bills supporting
documents. Only such portion of a monthly statement that is not satisfactorily supported
may be withheld from payment. Should any discrepancy be found to exist between
actual payments and costs authorized to be incurred by the consultants, MSRDC may
add or subtract the difference from any subsequent payments.
c) The final payment under this Clause shall be made only after the final report and a final
Appointment of General Consultant for Peer-review of Detailed Project Report, Balance Pre
Tender and Post Tender activities for Construction of Two Tunnel (Two tubes of 4 lane each )
in km 1/040 to km 2/790 (1.75km ) and km 3/440 to 12/360 (8.92km ) for missing link(Package -I
) and Construction of missing link with viaducts from km 0/000 to 13/300 and upgradation to 8
lane from km 32/800 to km 38/700 (Package-II) under Capacity Augmentation for Mumbai-
Pune Expressway on EPC mode
C:\Users\Antivairus SERVER\Desktop\T-1851pdf addendum -1-missing link PMC 02.01.2017\ADDENDUMPMC03.01.2017.doc
statement, identified as such, shall have been submitted by the Consultants and approved
as satisfactory by MSRDC. The services shall be deemed completed and finally accepted
by MSRDC and the final report and final statement shall be deemed approved by
MSRDC as satisfactory unless within ninety (90) days period MSRDC gives written notice
to the Consultants specifying in detail deficiencies in the Services, in the final report or
in final statement, the consultants shall there upon promptly make any necessary
corrections, and upon completion of such corrections, the foregoing process shall be
repeated. Any amount which MSRDC has paid or caused to be paid in accordance with
this Clause in excess of the amounts actually payable in accordance with the provisions of
this Contract shall be reimbursed by the Consultants to MSRDC within thirty (30) days
after receipt by the Consultants of notice thereof. Any such claim by MSRDC for
reimbursement must be made within (12) calendar months after receipt by MSRDC of a
final report and a final statement approved by MSRDC in accordance with the above.
d) No escalation is payable to PMC during the Post-tender services & thereafter in the extension
period if any (expect as stipulated in Clause 3.2.1 above).
e) Non provision of the staff / Facility (as per Clause No. 11, Appendix ‘A’ of Volume II of the
Bid Document) to MSRDC shall entitle reduction in payment to the Consultant as below.
1. Office Attendant – INR. 12,000/- per month.
2. Computer Operator cum Typist – INR. 18,000/- per month.
3. A/C Vehicle – INR. 45,000/- per month.
Note: - These reductions will be applicable also for approved extended period if any.
These deductions will be effected as and when fees as per payment
schedule are paid to the consultant.