Alignment Procedure Plf

download Alignment Procedure Plf

of 22

Transcript of Alignment Procedure Plf

  • 8/16/2019 Alignment Procedure Plf

    1/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 1

    Alignment Procedure for MSS Pumps

    Thank you for purchasing a FEDCO MSS Pump. FEDCOequipment is designed for ease of use and operation. Thefollowing procedure will provide detailed instructions for properalignment of the pump and motor. This will ensure years of

    trouble-free service.

    Once again, thank you for choosing FEDCO!!!!!!!!!

  • 8/16/2019 Alignment Procedure Plf

    2/22

  • 8/16/2019 Alignment Procedure Plf

    3/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 3

    Alignment Procedure for MSS Pumps

    Parts and Tools

    Precision level*

    Alignmentpins (2)

    Feelergauge*

    Shaftcoupling

    Motorshaft key

    Pumpshaft key

    Couplingset screws

    (2)

    Motor adapterbolt , lock washer,

    flat washer

    Coupling guardscreen (2)

    Coupling guardscreen bolts (8)

    Shims*

    * Indicates tools that canbe provided by FEDCO atadditional charge

    Anti-Seize

  • 8/16/2019 Alignment Procedure Plf

    4/22

  • 8/16/2019 Alignment Procedure Plf

    5/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 5

    Alignment Procedure for MSS Pumps

    Coupling End Assembly Animation

    The animation above shows the assembly of thecoupling end of the MSS Pump.

  • 8/16/2019 Alignment Procedure Plf

    6/22

  • 8/16/2019 Alignment Procedure Plf

    7/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 7

    Alignment Procedure for MSS Pumps

    Pump Leveling Foot Assembly Animation

    The animation above shows the assembly of theleveling foot of the MSS Pump.

  • 8/16/2019 Alignment Procedure Plf

    8/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 8

    Alignment Procedure for MSS Pumps

    STEP 1: General PreparationIf pump and motor are mounted on a skid,•Skid must be leveled and shimmed to support:

    •Weight of motor and pump.•Weight of membrane housings, process piping, and all other equipment

    installed on the skid when filled with water.

    If pump and motor are mounted on concrete foundation,•Foundation must be leveled.• Anchor bolts must be properly installed and tightened.

    Skid Shim

    Foundation

    Anchor bolt

    NOTE: If your pump has a rotated inlet, rotate the inlet to the verticalposition prior to alignment. Once alignment is complete, rotate the inletback to it required location.

  • 8/16/2019 Alignment Procedure Plf

    9/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 9

    Alignment Procedure for MSS Pumps

    STEP 2: Level the Motor

    1. Pump end and motor should not becoupled at this time.

    2. Verify motor feet sit flat on mountingsurface (no “ soft foot” ).3. Place level on motor shaft.4. Adjust motor shims until

    motor shaft is level.

    3. Tighten motor foot bolts to mountingsurface.4. Verify shaft remains level.

    NOTE: Motor must be placed at final installation location prior tostarting alignment procedure

  • 8/16/2019 Alignment Procedure Plf

    10/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 10

    Alignment Procedure for MSS Pumps

    STEP 3: Prepare for Alignment1. Install the two (2) alignment pins2. Discharge cradle halves should not

    be bolted together at this t ime.

    3. Pump end should rest on the bottomhalf of the discharge cradle to allowthe pump to slide axially duringalignment.

    4. Sl ide pump onto motor face.• Coupling NOT installed• Ensure motor adapter is fully

    engaged with motor face5. Place level across inlet .6. Adjust bottom half of pump leveling

    foot discharge cradle until levelusing adjusting nuts.

    7. Do NOT tighten down top half ofdischarge cradle at this time.

  • 8/16/2019 Alignment Procedure Plf

    11/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 11

    Alignment Procedure for MSS Pumps

    STEP 4: Ensure Mounting Flanges are Parallel

    1. Check for uniform gap between motoradapter and motor face throughout theentire interface.• If there is no gap, or gap is

    uniform, proceed to Step 5.•

    If gap is not uniform, proceed to #2below.

    2. Using feeler gauge, measure clearanceon one side of gap.

    3. Measure clearance on other side.4. Move pump discharge end sidewise

    until clearance is uniform.

    Make clearanceuniform

    Feeler gauge

  • 8/16/2019 Alignment Procedure Plf

    12/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 12

    Alignment Procedure for MSS Pumps

    STEP 5: Check Shaft Gap

    1. Install two motor adapter bolts to drawpump to motor.

    2. Measure gap between motor andpump shafts.• Gap should be between 1/8” (3

    mm) and 1/4” (6 mm).

    Shaft gap between 1/8 and 1/4inches (3 to 6 mm)

  • 8/16/2019 Alignment Procedure Plf

    13/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 13

    Alignment Procedure for MSS Pumps

    STEP 6: Lubricate Shafts

    1. Remove the two bolts installed inprevious step.2. Separate pump and motor.3. Liberally apply anti-seize to pump and

    motor shafts and coupling bores.•

    Use anti-seize provided in smallpouch.

    Apply anti-seize to these areas

  • 8/16/2019 Alignment Procedure Plf

    14/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 14

    Alignment Procedure for MSS Pumps

    STEP 7: Install Coupling

    1. Instal l key on motor shaft.2. Sl ide coupling on motor shaft.

    • Push until firmly seated.3. Install both set screws and firmly

    tighten.• Note that there are NO set screws onthe pump side of the coupling.

    Tighten both set screws

  • 8/16/2019 Alignment Procedure Plf

    15/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 15

    Alignment Procedure for MSS Pumps

    STEP 8: Insert Pump Shaft into Coupling

    1. Slide pump onto alignment pins.2. Instal l key onto pump shaft.3. Line up pump key with pump keyway

    in coupling.

    Line up pump key withcoupling keyway

    Alignment pins

  • 8/16/2019 Alignment Procedure Plf

    16/22

  • 8/16/2019 Alignment Procedure Plf

    17/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 17

    Alignment Procedure for MSS Pumps

    STEP 10: Final Installation – Motor Adapter

    1. Install two (2) motor adapter boltsand tighten *.

    2. Remove two (2) alignment pins.

    3. Install remaining adapter bolts andtighten *.

    Install and tighten all motoradapter bolts

    *For 1/2” bolts, tighten to 30 ft-lbs*For 5/8” bolts, tighten to 60 ft-lbs

  • 8/16/2019 Alignment Procedure Plf

    18/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 18

    Alignment Procedure for MSS Pumps

    STEP 11: Final Installation – Leveling Foot

    1. Place level on inlet .2. Bring top half of discharge cradle

    down to meet bottom half.3. Begin to tighten down top half ofdischarge cradle.

    4. During tightening, the cradle maydraw the pump downward.

    5. Verify that pump remains levelduring tightening.• If pump comes out of level, raise

    the bottom half of the cradle untilpump is again level.

    Repeat this process until cradleis fully secured and pumpremains level.

    6. Tighten down cradle jamb nuts.

  • 8/16/2019 Alignment Procedure Plf

    19/22

  • 8/16/2019 Alignment Procedure Plf

    20/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 20

    Alignment Procedure for MSS Pumps

    STEP 13: Coupling Guard InstallationCoupling guard

    Coupling guard screw

    Install both coupling guards andtighten the screws.

  • 8/16/2019 Alignment Procedure Plf

    21/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 21

    Alignment Procedure for MSS Pumps

    STEP 14: Piping Alignment CheckPump and pipe

    connections are aligned

    Proper gap

    A good pump-motor alignment can beruined by improper alignment of thepiping.

    Please make sure that suction anddischarge piping are concentric with thepump connections and have the propergap prior to installation of the Victauliccouplings.

    DO NOT FORCE THE CONNECTINGPIPES INTO POSITION!

    BADBAD

  • 8/16/2019 Alignment Procedure Plf

    22/22

    …making flui d energy work for you copyright © Fluid Equipment Development Company 22

    Alignment Procedure for MSS Pumps

    Alignment Completed

    YOUR ALIGNMENT IS COMPLETE!!!

    Please refer to the O&M manual for pipe connections and startupprocedures.

    If there are ANY questions, please contact FEDCO:

    +734.241.3935 (telephone)+734.241.5173 (fax)William Byrne : wbyrne @fedco-usa.comCasey Bly: [email protected]

    Thank you for using FEDCO equipment!