Alan MulakTim Guiterman Jon Osgood Jayme Woogerd. Thanks to Our Sponsors. Thanks to the Nashua City Hall and Bob Eldredge of Nashua BetterBuildings for hosting today’s event!. Workshop Agenda. “Introduction” Jayme Woogerd - GDS “Background and History of the Code” - PowerPoint PPT Presentation

Transcript of Alan MulakTim Guiterman Jon Osgood Jayme Woogerd

Page 1: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Alan Mulak Tim Guiterman

Jon Osgood Jayme Woogerd

Page 2: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Thanks to Our Sponsors

Page 3: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Thanks to the Nashua City Hall and Bob Eldredge of

Nashua BetterBuildings for hosting today’s event!

Page 4: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Workshop Agenda

4

“Introduction” Jayme Woogerd - GDS

“Background and History of the Code”Jonathan Osgood - PUC

“How to Meet or Beat the Code”Alan Mulak - PE

Lunch (12 noon)

“Major Changes in the 2009 IECC” &“Beyond Code: Green & Advanced Codes”

Tim Guiterman - Navigant Consulting

Page 5: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

The Context: Why We’re Here…• New Energy Code (IECC 2009) Became Effective April 1st, 2010.

• Assurance from Governor John Lynch that NH would achieve 90% compliance of the 2009 IECC within eight years (“hence the NH Energy Code CHALLENGE”) – linked to NH receiving $26M in ARRA-State Energy Program funds.

• 90% Statewide Compliance with the Energy Code is no small task… But Education and Training is the first Step (so thanks for being here – as the success of this important goal will depend on everyone in this room!)

5

Page 6: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

NH Building Code Compliance ProgramToday’s Training is one piece of a larger strategy of reaching the 90% compliance goal.

2009 IECC - 90% compliance by 2017 – Overall Strategy• Establish a baseline of existing compliance/enforcement

• Create a roadmap to achieve 90% compliance of the 2009 IECC by 2017

• Promote the program throughout the State

• Train and Mobilize building professionals in all areas for energy code compliance and promote above-code performance (why we’re here today)

• Develop a Public Awareness Campaign for homeowners, landlords, commercial property owners, real estate appraisers

• Update and Gather Building Code Resources in publicly accessible sites

• Develop recommended enforcement and compliance public policy option

More info on the program can be found at www.nhenergycode.com6

Page 7: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Visit www.nhenergycode.com!• Additional Training Opportunities

• NH Energy Code Related Resources

7

Page 8: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

IECC 2009 IBC 2009 chapter 13

8

You have a change to WIN a free energy code book today!

And for sale at the end of today’s workshop!

Page 9: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Demographic Survey

Page 10: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

What is your profession?

10

1. Builder2. Architect/Engineer3. Designer4. Building Official5. Energy

Consultant/Auditor6. Other

Page 11: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Why are you here?1. Learn about the new

energy code2. Learn construction

techniques to meet new code

3. Learn construction techniques to exceed new code

Page 13: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

How confident are you that a structure you built or designed prior to 2002 would survive a major natural disaster?

13

1. Very confident2. Somewhat confident3. Shaky4. Not on firm ground

Page 15: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

These building codes are mandatory in NH: International Building Code 2009, International Residential Code 2009, International

Plumbing Code 2009, International Mechanical Code 2009, International Energy Conservation Code 2009,and the National

Electrical Code 2008

15

1. True2. False

Page 16: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

When was the NH Energy Code adopted?

16

1. 19792. 19863. 19994. 2002

Page 17: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy CodeHistory

Effective August 1979Revised 1980, 1986, 1993 & 1998

State Building Code 20022006 IECC August 2007

2009 IECC April 2010

Page 18: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Where does the code apply?

1. Cities2. Municipalities with

building inspectors3. Where I’m told it

applies4. Everywhere in NH5. All of the above esp

2+3

Page 19: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Two code climate zones apply in NH:

1. True2. False

Page 20: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy CodeClimate Zones

20

Page 21: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy CodeClimate Zones Table 301.1

NEW HAMPSHIRE6A Belknap6A Carroll

5A Cheshire6A Coos

6A Grafton5A Hillsborough

6A Merrimack5A Rockingham

5A Strafford6A Sullivan

21

Page 22: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy Code

The Commercial Energy Code covers

all buildings except:

Detached one and two family dwellings (R-3)

Multi family (R-2) not more than 3 stories above grade and

Assisted living >5 and < 16 residents (R-4) not more than 3 stories above grade

Page 23: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy CodeProcess

NH architect or engineer designs structure to meet code

Signs off on plans See RSA 155-D

Page 24: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy CodeProcess

NH architect or engineer sign off:"The proposed structure has been designed and reviewed by the architect or engineer and determined to be in compliance with all applicable requirements of RSA 155-D and the

energy code adopted pursuant thereto."

Page 25: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

The contractor of a building, building component, or structure shall be responsible for meeting the minimum requirements of the state

building code.

RSA 155-A:2 VIII

1. True2. False

Page 26: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

A structure may be built to comply with the IBC 2009 Ch 13?

1. True2. False

Page 27: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy CodeIBC

Chapter 13 Section 13011301.1 Scope. This chapter governs the design and construction of buildings for energy efficiency.

1301.1.1 Criteria. Buildings shall be designed and constructed in accordance with the International Energy Conservation Code.

Page 28: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy CodeIECC 2009

501.1 Scope. The requirements contained in this chapter are applicable to commercial buildings, or

portions of commercial buildings. These commercial buildings shall meet either the

requirements of ASHRAE/IESNA Standard 90.1, Energy Standard for Buildings Except for Low-Rise

Residential Buildings, or the requirements contained in this chapter.

Page 29: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Table 502.2(1) Building Envelop Requirements

Climate Zone 5 6All others Group R All others Group R

ROOFInsulation Entirely Above Deck R-20ci R-20ci R-20ci R-20ci

Metal Buildings w R-5 Thermal Blocks R-13+R-13 R-19 R-13+R-19 R-19Attic and Other R-38 R-38 R-38 R-38

WALLS ABOVE GRADEMass R-11.4 R-13.3 R-13.3 R-15.2

Metal Buildings R-13+R-5.6ci R-13+R-5.6ci R-13+R-5.6ci R-13+R-5.6ciMetal Framed R-13+R-7.5ci R-13+R-7.5ci R-13+R-7.5ci R-13+R-7.5ci

Wood Framed and Others R-13+3.8ci R-13+3.8ci R-13+7.5ci R-13+7.5ci

WALLS BELOW GRADEBelow Grade Wall R-7.5ci R-7.5ci R-7.5ci R-7.5ci

FLOORSMass R-10ci R-12.5ci R-12.5ci R-14.6ci

Joist/Framing R-30 R-30 R-30 R-30

SLAB-ON-GRADE FLOORSUnheated Slabs N/R R-10 24" R-10 24" R-15 24"

Heated Slabs R-15 24" R-15 24" R-15 24" R-20 48"

OPAQUE DOORSSwinging U-0.70 U-0.70 U-0.70 U-0.50

Roll-up or Sliding U-0.50 U-0.50 U-0.50 U-0.50

NOTE: CAREFULLY OBSERVE ALL FOOTNOTES

Page 30: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Table 502.3 Fenestration Requirements 40% Vertical Fenestration Max

Climate Zone 5 6

FRAMING OTHER THAN METAL U-.35 U-.35

METAL FRAMINGCurtain wall/storefront U-.45 U-.45Entrance Door U-.8 U-.8All Other U-.55 U-.55

SHGC ALL FRAME TYPESProjection Factor <.25 0.4 0.4Projection Factor >.25 NR NR

SKYLIGHTS 3% MaxU Factor 0.6 0.6SHGC ALL FRAME TYPES 0.4 0.4

Page 31: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Commercial Structure under 4000sq ft:

1. Doesn’t need to comply

2. Envelope may comply with Residential Code

3. Can comply with ASHRAE 90.1-2007

4. 2 and 3 only

Page 32: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy Code EC-1 Form

32

Page 33: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

EC-1 Form (page 2)

33

Page 34: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy CodeDevelopment Process

International Code CouncilAccepts amendments from public

Assigned to CommitteesHold Code Development Hearings

Hold Final Action HearingsPublish Revised Code

Page 35: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Building CodeAdoption Process

Building Code Review BoardRSA 155-A:1016 members

Meets monthly

Page 36: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Building CodeIECC 2009

General Court must confirm within 2 years

36

Page 37: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Building CodeAdoption Process

This cycleDiscussions began in February 09

IEEC moved in MarchPublic Hearing in May

Adopted May 8, 09

Page 38: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Building CodeAdoption Process

This cycleIECC 2009

IBC 2009Effective April 1, 2010

Page 39: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Energy codes will get stronger.

1. Yes2. No

Page 40: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Building CodeAdoption Process

2012 cycleComplete

Group A IBC, IRCFinal action hearings held

May 15-23, 2010

Page 41: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Building CodeAdoption Process

IECC, IRC-EnergyFinal Action Hearings held

October 28- November 1, 2010

Page 42: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Building CodeAdoption Process

IECC 200912-15% less energy use

IECC 2012Additional 15% savings

Page 43: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

www.puc.nh.gov

Page 44: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

Energy Code Page

Page 45: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy CodeIECC 2009 Sec 104.8 Approval.After the prescribed tests and

inspections indicate that the work complies in all respects with this

code, a notice of approval shall be issued by the code official.

Page 46: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy Code

?’s

Page 47: Alan MulakTim Guiterman Jon Osgood    Jayme Woogerd

N.H. Energy Code

Jon [email protected]