AES ELETROPAULO SMART GRID PROGRAM · Projeto Estruturante Demonstrativo de Redes Inteligentes ......

12
Cisco IoE Center of Innovation • Rio de Janeiro • June 23-24, 2015 Maria Tereza Vellano, Revenue Management Director, AES Eletropaulo AES ELETROPAULO SMART GRID PROGRAM

Transcript of AES ELETROPAULO SMART GRID PROGRAM · Projeto Estruturante Demonstrativo de Redes Inteligentes ......

Cisco IoE Center of Innovation • Rio de Janeiro • June 23-24, 2015

Maria Tereza Vellano, Revenue Management Director, AES Eletropaulo

AES ELETROPAULO SMART GRID PROGRAM

© 2013 Cisco and/or its affiliates. All rights reserved. 2

Brazil

Brazil

São Paulo

State

Energy

Sold

Consumer Units

Concession

Area

GDP 1

AES

Eletropaulo

% of

Brazil

46 (TWh)

11%

6,8 (million)

9%

4,526 (km2)

0,05%

381 (USD$ trillion)

17%

1: The World Fact Book, 2014 Brazil’s GDP official exchange rate

2014 Figures

AES Eletropaulo

© 2013 Cisco and/or its affiliates. All rights reserved. 3

MARKET

Demand

An extremely dense market (metropolitan area; high concentration)

SP is the main financial center of Brazil

High demand for power quality

OPPORTUNITY

for Innovation

There is opportunity to create an environment of continuous innovation for sistematic evaluation of new concepts and solutions, with a view to its implementation in business

EFFECTIVENESS

of

Investments

The process of testing and implementing innovations through isolated projects have been inefficient and with local results, making it necessary to have a systemic vision

PRODUCTIVITY

Constant search for productivity gains,

Technological innovation

Best practices for business sustainability

Smart Grid Project – Motivation

© 2013 Cisco and/or its affiliates. All rights reserved. 4

1-Reduce technical and commercial

losses (fraud);

2-Improve the service quality;

3-Reduce operational

costs;

4-Improve planning of grid

expansion;

5-Improve assets management;

6-Promote energy

efficiency;

7-Stimulate innovation and

technology industry;

Smart Grid Project – Main Benefits

8-Grid will be

appropriate to connect

micro-generation (eolic

and solar)

9-Customers will be able

to manage their own

consumption using

Client Portal.

© 2013 Cisco and/or its affiliates. All rights reserved. 5

Create a deployment model replicable throughout the concession area,

Prepare an appropriate Technology and Strategic Road Map.

Objective:

Smart Grid Project – Overview

Implementation

Period

Kickoff meeting – january/2013

Project End– december/2017

P&D ANEEL

Projeto Estruturante Demonstrativo de Redes

Inteligentes

Lote Pioneiro de Solução de Medição

Research Entities : USP / Enerq / Sinapsis e FITec

Investments R$75 millions

Fund: P&D ANEEL / FINEP

Project:

Video

© 2013 Cisco and/or its affiliates. All rights reserved. 6

Barueri Vargem Grande + Caucaia do Alto ▪ 62.000 Clients

▪ Annual consumption – 1.2 millions MWh

▪ 304 Km of MV overhead power grid

▪ Complete project

▪ Smart Grid concept proof

▪ 32.289 Clients

▪ Annual consumption – 178.000 MWh

▪ 374 Km of MV overhead power grid

• Self-Healing and Fault detection functionalities

Reasons for selecting the sites

AES Eletropaulo representative model:

- Metropolitan area

- Similar client profile

- Consumption

- Power grid (short feeders and mesh)

- Similar performance indicators

AES Eletropaulo different characteristics:

- Rural area

- Environmental Protected Area

- Long circuits = 100 km

- Isolated feeders = 23 kV

- Bad performance indicators

Smart Grid Project – Sites selected for the field test

© 2013 Cisco and/or its affiliates. All rights reserved. 7

Project Structure

Governance

Metrics

Roadmap for Rollout

Training

Blueprint

Bench-marking

Project management

Advanced Automation

Fault

Detector

Volt/Var Control

Self-Healing

Portal

Client Interation

Resources

Portal

Show Room

Supply Alternatives

Critical Regions

Distributed Generation

Microgrids

Smart Metering

Advanced Metering

Infrastructure

Smart Metering solution

Low-income communities

RF/PLC technology

Telecomunication

Wimax Network

© 2013 Cisco and/or its affiliates. All rights reserved. 8

Macro Steps

Jan/2013

Dez/2013

2014

2015

2016

2017

kickoff

meeting

• Metrics Methodology

• SmartInfo-benchmarking

• Blueprint

• Training

• Plan. WiMax

• Board RF+ PLC for meter

• Meters Aquisition

• AMI acquisition (RF+PLC)

• Automation Portal

• Supply Alternatives – Vargem

Grande

• AMI tests

• Self Healing field tests and deployment

• Fault Detectors field tests and deployment

• Volt Var Control field tests and deployment

• Smart Home

• Upgrade SCADA

• Telecom (AMI + Wimax)

• Prototype Meter with RF+PLC

• Smart meter installation (start)

• Balance meter installation (start)

• MDM / MDC

• Legacy systems integration

• Training

• Client Portal

• Smart meter installation (end)

• Balance meter installation (end)

• Metrics - Field Data Analises

• Roadmap for Rollout

© 2013 Cisco and/or its affiliates. All rights reserved. 9

Existing Infrastructure

Metering Center

9

DMS

AMI

NMS

EMS / SCADA

OMS MWM

GE

ALSTOM

Eletropaulo Digital Project Challenges

Automatic

Reclosers Fault Detectors

Energy Balance Metering Router Smart Meter

Telecom last mile

WiMax + Fiber optic

Digital

Substations

Smart Grid Program

System Architecture

Commercial System

Operational System

Measuring System

MDC / MDM

RF + PLC

I

n

t

e

g

r

a

t

i

o

n

© 2013 Cisco and/or its affiliates. All rights reserved. 10

Telecom Infrastructure for Smart Grid

Operational

Center

Substation

Fiber optic

Substation

950MHz IEEE P1901.2

Metering

Center

CISCO Router

Smart meters

with hybrid

communication

board RF+PLC

© 2013 Cisco and/or its affiliates. All rights reserved. 11

Meter with redundant communication x Adequate price

Smart meter x Approval period of INMETRO

Telecom solution x Adequate availability

Integration with legacy systems x Expected performance

Current Grid infraestructure x Advanced automation

Relationship with traditional x Smart grid customer

Cyber security: current risks x With smart grid

Rollout: investiments x Regulatory acceptance

Rollout: current process x With smart grid

Chalenges and sinergies

Smart Energy Services

Demand Response

Distributed generation

Electrical vehicle

Energy management

Energy efficiency

consultance

Smart public lighting

Sharing infrastructure

Cisco IoE Center of Innovation • Rio de Janeiro • June 23-24, 2015

Maria Tereza Vellano, Revenue Management Director, AES Eletropaulo

AES ELETROPAULO SMART GRID PROGRAM

[email protected]