Advanced Planning from Standard MPS/MRP

18
Advanced Planning from Standard MPS/MRP Darren Swindells Hills Industries Limited 16 August 2010 The most comprehensive Oracle applications & technology content under one roof

description

Using Multi-facility MPS/MRP, it it possible to group demand into production (or purchasing) cycles to increase operational efficiency. This presentation shows how to achieve this workaround with standard R3483 though use of the Processing Options and Data Selection Item Branch data and Shop Floor Calendar.

Transcript of Advanced Planning from Standard MPS/MRP

Page 1: Advanced Planning from Standard MPS/MRP

Advanced Planning from Standard MPS/MRP

Darren SwindellsHills Industries Limited

16 August 2010

The most comprehensive Oracle applications & technology content under one roof

Page 2: Advanced Planning from Standard MPS/MRP

The Situation

• JDE (rel. 8.10)being implemented as ERP solution across Hills Group • Orrcon had unique requirement and was next!

• Product manufactured in Cycles at Orrcon

• Budget and time-frame would not allow an off-the-shelf ‘APS’ solution

Page 3: Advanced Planning from Standard MPS/MRP

About Orrcon – Racing Team

• .. Oh, and on the side we make steel pipe & tube as well …

Page 4: Advanced Planning from Standard MPS/MRP

About Orrcon – Tube Mills

• Manufacturers of steel Pipe & Tube Large division of Hills Industries Limited Local manufacturing in Brisbane, Adelaide & Wollongong

Page 5: Advanced Planning from Standard MPS/MRP

About Orrcon – Make in Cycles

• Set-up time is significant– Each change of profile incurs set-up

• To reduce downtime – roll groups of products once every 4 weeks

Page 6: Advanced Planning from Standard MPS/MRP

About Orrcon – Changeovers

Full-Changeover

1/4-Changeover

1/2-Changeover

Page 7: Advanced Planning from Standard MPS/MRP

Problem with Standard MPS/MRP

• R3483 (Master Planning Schedule-Multi-Plant)

• Plans Work Orders for Date of Need (& Demand is dated daily)

• Orrcon groups Planned WOs into pre-published Rolling Cycles for each Product Family– Only make each product once per Cycle

Page 8: Advanced Planning from Standard MPS/MRP

The Solution – Create MPS/MRP Cycles – Step 1 (Buyer Number)

• Link each Item Number to a Cycle using the ‘Buyer Number’

• Buyer 201 = Cycle 1

• Buyer 202 = Cycle 2

• Buyer 203 = Cycle 3

• Buyer 204 = Cycle 4

Page 9: Advanced Planning from Standard MPS/MRP

The Solution – Create MPS/MRP Cycles – Step 2 (Cycle B/Ps)

• Create ‘Branch Plants’ for each Cycle

• B/P 241=Cycle 1• B/P 242=Cycle 2• B/P 243=Cycle 3• B/P 244=Cycle 4

Page 10: Advanced Planning from Standard MPS/MRP

The Solution – Create MPS/MRP Cycles – Step 3 (Cycle Calendars)

• Create ‘Shop Floor Calendars’ for each Cycle

• B/P 241=Cycle 1• B/P 242=Cycle 2• B/P 243=Cycle 3• B/P 244=Cycle 4

• ‘W’ Working Day - only in one week from Cycle

Page 11: Advanced Planning from Standard MPS/MRP

The Solution – Create MPS/MRP Cycles – Step 4 (Create MPS Versions)

• Create versions of MPS that are linked with ‘Branch Plant’ Shop-floor Calendars for each Cycle– One version for each Cycle

• Continued …

Page 12: Advanced Planning from Standard MPS/MRP

The Solution – Create MPS/MRP Cycles – Step 4 (Create MPS Versions)

• Data Selections (only select items that belong to the Cycle)• MCU = Cycle SFC

(to get records)• BUYR = Cycle

group from

Item Branch

• Continued …

Page 13: Advanced Planning from Standard MPS/MRP

The Solution – Create MPS/MRP Cycles – Step 4 (Create MPS Versions)

• Processing Options (call Shop-Floor Calendar for Cycle)

• Multi-Facility Tab• 1. Date Branch = Cycle Branch Plant• MPS then uses the Shop Floor Calendar from this Branch

Plant

• This is what makes the Cycles possible!

• Continued …

1. Date Branch

This was actually designed to reduce processing time when Multi-Facility MPS/MRP was generated – however it also achieves Cycle Planning when used for this Work-Around

Page 14: Advanced Planning from Standard MPS/MRP

The Solution – Create MPS/MRP Cycles – Step 5 (Generate MPS)

• Generate MPS (R3483)

• Note: ALL Cycles are generated each week – to create correct projected requirements for components

Page 15: Advanced Planning from Standard MPS/MRP

The Solution – Create MPS/MRP Cycles – Step 6 (Detailed Message Review)

• Planned Order Messages now group so each product is only made once per week in Detailed Message Review

• Note: Request Date

Changes from 30/08/10

to 29/09/10 – jump of

4 weeks

Page 16: Advanced Planning from Standard MPS/MRP

Summary• Work-around: using R3483 ‘Date Branch’ feature designed

to save Processing Time to achieve some ‘APS’ functionality of grouping Item production into correct weekly buckets

• Requires set-up of Branch Plants, Shop-Floor Calendars and one MPS/MRP version for each Cycle

• Can also be used for Manufacturing AND Purchasing

• ACHIEVES OBJECTIVE = one setup for each product family every 4 weeks

Page 17: Advanced Planning from Standard MPS/MRP

Questions?

Page 18: Advanced Planning from Standard MPS/MRP

Tell us what you think…

• http://feedback.insync10.com.au