Chap006a - Advanced MRP
-
Upload
priambodo-ariewibowo -
Category
Documents
-
view
12 -
download
3
description
Transcript of Chap006a - Advanced MRP
Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
Manufacturing Planning and Control
MPC 6th Edition
Chapter 6a
6a-2
Advanced Material Requirements Planning
After the initial phase of Material Requirements Planning (MRP) is complete, advanced issues become the new focus of the firm.
6a-4
Determining Manufacturing Order Quantities
A number of quantity-determination (lot-sizing) procedures have been developed
The primary consideration in MRP lot-sizing procedures is the nature of the net requirements dataRequirements don’t reflect the independent
demand assumption of constant uniform demandRequirements are discreteRequirements can be lumpy
6a-5
MRP Lot-Sizing Assumptions
All requirements occur at the beginning of the period
All future requirements must be met (no backorders)
Ordering decisions occur at regular intervals Requirements are appropriately offset for
manufacturing lead times Component requirements are satisfied at a
uniform rate during each period
6a-7
Economic Order Quantity (EOQ)
Simple, widely used technique Assumes constant, uniform demand
May require adjustment when demand is lumpy
CostHoldingC
PeriodperDemandAverageD
CostOrderingC
C
DCEOQ
H
p
H
p
2
6a-8
Periodic Order Quantity (POQ)
Uses EOQ formula to compute time between orders (TBO)
Lot-size varies based upon the forecast requirements for the coverage period
Doesn’t allow for combining orders during periods of light demand
6a-9
Part Period Balancing (PPB)
Attempts to equalize the costs of ordering and holding inventory
Considers alternate coverage periods and the scenario where ordering and inventory costs are most nearly equal
Won’t always identify the cost-minimizing plan
6a-10
Wagner-Whitin Algorithm
Optimizing procedure to identify the cost-minimizing plan for a time-phased schedule
Requires much more computational effort May not identify optimal plan under all
conditions
6a-11
Buffering against Uncertainty
Buffering can be effective when uncertainty is unavoidableBuffering should not be used to
accommodate a poorly performing MRP system
Uncertainty has two main sourcesDemand–timing and quantitySupply–timing and quantity
6a-12
Safety Stock and Safety Lead Time
There are two basic ways to buffer uncertaintySafety stock–additional stock intended to
cover unanticipated requirementsSafety lead time–releasing orders earlier than
necessary to ensure receipt before the required due date
6a-13
Performance of Safety Stock vs. Safety Lead Time
Timing Uncertainty Quantity Uncertainty
Safety lead time outperforms safety stock under timing uncertainty
Safety stock outperforms safety lead time under quantity uncertainty
6a-14
Other Buffering Techniques
Scrap allowances–useful if scrap is significant and unavoidable
Reduce uncertaintyIncrease forecast accuracy, improve system parameter
accuracy (BOM, inventory), reduce lead times, improve product quality.
Provide system slackAdditional production capacity to allow for unplanned
requirementsSlack costs money
6a-15
Nervousness
Nervousness occurs when even small changes to higher-level MRP records or the master production schedule leads to significant changes in the MRP plans
Nervousness is most damaging in MRP systems with many levels in the product structure
Some lot-sizing techniques (such as POQ) can amplify the nervousness
6a-17
Principles
MRP enhancements should be attempted only after a basic MPC system is in place.
Discrete lot-sizing procedures can reduce inventory costs, but the complexity shouldn’t outweigh the savings.
Safety stocks should be used when uncertainty is related to quantity.
Safety lead times should be sued when uncertainty is related to timing.
6a-18
Principles
MRP system nervousness can result from lot-sizing rules, parameter changes, and other causes. Precautions should be taken to dampen the amplitude and impact.
Uncertainty needs to be reduced before implementing complex procedures.
MRP system enhancements should follow the development of ever more intelligent users.
6a-19
Quiz – Chapter 6a
What is the primary consideration when selecting a lot-sizing procedure?
In a situation where the main source of uncertainty is due to timing of customer orders, which buffering strategy would be expected to perform best?
In a situation where the main source of uncertainty is due to quantity of demand, which buffering strategy would be expected to perform best?