ADDENDUM NO. 1 DATE ISSUED: July 29 th , 2015 PROJECT: T15-227 – Johns Family Nature Conservancy Trail Construction & Improvements The Contract Documents for this work are revised as noted herein. All such revisions become a part of the work and shall be included in your proposal. No consideration will be allowed for extras due to the contractor not being familiar with this addendum. 1. REFERENCE: Answers to Questions Received The following are answers to questions received: Q1 Can you please clarify what bonding is required on this Invitation to Tender? A1 No performance bond, labour and material payment bond or maintenance bond is required under this Invitation to Tender or resulting contract. However, tenders are to be accompanied by the 10% Bid Security, as listed on the Form of Tender (section 4.1.2). The % amount for Bid Security is detailed in Instructions to Tenderers Part II, Section 5 – Tender Requirements of MMCD 2009. 2. REFERENCE: Area 3, Stream Crossing, Rock Drain The requirements for the Rock Drain in area 3 have been amended. As a result, the following documents have been revised as follows: DELETE: Form of Tender Appendix 1 – Schedule of Quantities REPLACE WITH: Form of Tender Appendix 1 – Schedule of Quantities - Revised in Addendum No.1 Note: only change is to item 3.4.1 DELETE: Form of Agreement, Schedule 2, Drawing No L4 (Revision Date 2015-07-13) REPLACE WITH: Form of Agreement, Schedule 2, Drawing No L4 (Revision Date 2015-07-29) – Revised in Addendum No.1 END OF ADDENDUM NO. 1

Transcript of ADDENDUM NO. 1 - Regional District of Central …...ADDENDUM NO. 1 DATE ISSUED: July 29th, 2015...

Page 1: ADDENDUM NO. 1 - Regional District of Central …...ADDENDUM NO. 1 DATE ISSUED: July 29th, 2015 PROJECT: T15-227 – Johns Family Nature Conservancy Trail Construction & Improvements

ADDENDUM NO. 1 DATE ISSUED: July 29th, 2015 PROJECT: T15-227 – Johns Family Nature Conservancy Trail Construction & Improvements The Contract Documents for this work are revised as noted herein. All such revisions become a part of the work and shall be included in your proposal. No consideration will be allowed for extras due to the contractor not being familiar with this addendum.

1. REFERENCE: Answers to Questions Received

The following are answers to questions received:

Q1 Can you please clarify what bonding is required on this Invitation to Tender?

A1 No performance bond, labour and material payment bond or maintenance bond is required under this Invitation to Tender or resulting contract. However, tenders are to be accompanied by the 10% Bid Security, as listed on the Form of Tender (section 4.1.2). The % amount for Bid Security is detailed in Instructions to Tenderers Part II, Section 5 – Tender Requirements of MMCD 2009.

2. REFERENCE: Area 3, Stream Crossing, Rock Drain

The requirements for the Rock Drain in area 3 have been amended. As a result, the following documents have been revised as follows: DELETE: Form of Tender Appendix 1 – Schedule of Quantities REPLACE WITH: Form of Tender Appendix 1 – Schedule of Quantities - Revised in Addendum No.1

Note: only change is to item 3.4.1 DELETE: Form of Agreement, Schedule 2, Drawing No L4 (Revision Date 2015-07-13) REPLACE WITH: Form of Agreement, Schedule 2, Drawing No L4 (Revision Date 2015-07-29) – Revised in Addendum No.1

END OF ADDENDUM NO. 1

Page 2: ADDENDUM NO. 1 - Regional District of Central …...ADDENDUM NO. 1 DATE ISSUED: July 29th, 2015 PROJECT: T15-227 – Johns Family Nature Conservancy Trail Construction & Improvements

FT – PAGE 1UNIT PRICE CONTRACT

T15-227 Johns Family Nature Conservancy Trail Construction and ImprovementsSCHEDULE OF QUANTITIES AND PRICES - BASEBID

OWNER: Regional District of Central OkanaganCONSULTANT: MMM Group

BID MMCD UNIT TOTALITEM DESCRIPTION REF. UNIT QUANT. PRICE PRICE

BASE BID WORK SPEC UNIT QTY. UNIT PRICE TOTAL PRICEGENERAL REQUIREMENTS

0.0 Mobilization / Site Access xxxxxxx l.s. 1 $ $

AREA 1 Trail Improvements1.1 Remove existing cattle guard and re-establish road trail 32 15 00-S l.s 1 $ $

AREA 2 Trail Improvements2.1

2.1.1 Clear brush along ex. trail to 2.5m width (955m length) 31 11 01 sq.m. 2,390 $ $2.1.2 Trail Grading, Rock/boulder relocation (20% of trail area) 32 15 00-S sq.m. 286 $ $2.1.3 Install water bars along section of trail to minimize erosion 33 15 00-S ea. 3 $ $2.1.3 Supply, install, grade and compact 50mm depth of crusher fines for 1.5m wide ex. Trail (955m

length)32 15 00-S m3 75 $ $

AREA 3 Trail Improvements3.1

3.1.1 Clear brush along ex. trail to 1.5m width (1,110m length) 31 11 01 sq.m. 1,670 $ $3.1.2 Trail Grading, Rock/boulder relocation (20% of trail area) 32 15 00-S sq.m. 115 $ $

3.23.2.1 Remove section of fencing and stabilize existing posts. 32 15 00-S l.s 1 $ $3.2.2 Clear brush along ex. trail to 1.5m width (448m length) 31 11 01 sq.m. 675 $ $3.2.3 Trail grading, rock/boulder removal, and compaction for new 0.5m wide trail (448m length) 32 15 00-S sq.m. 224 $ $

3.33.3.1 Re-establish natural vegetation per detail (50m length) 32 15 00-S sq.m 75 $ $

3.43.4.1 Construct a Rock Drain with on-site rock material with flat walking surface 32 15 00-S l.s 1 $ $

AREA 3A Trail Improvements3A.1

3A.1.1 Rock removal for new crib steps (estimate 20% of total crib stairs) 32 15 00-S each 6 $ $3A.1.2 Regrading for new crib steps 32 15 00-S each 30 $ $3A.1.3 Supply, install, backfill and compact 0.9m wide tread crib steps 32 33 00-S each 30 $ $

AREA 3B Trail Improvements3B.1

3B.1.1 Rock removal for new crib steps (estimate 20% of total crib stairs) 32 15 00-S each 10 $ $3B.1.2 Regrading for new crib steps 32 15 00-S each 50 $ $3B.1.3 Supply, install, backfill, and compact 0.9m wide tread crib steps 32 33 00-S each 50 $ $

AREA 4 Trail Improvements4.1

4.1.1 Clear brush along ex. trail to 2.5m width (642m length) 31 11 01 sq.m. 1,610 $ $4.1.2 Trail Grading, Rock/boulder relocation (20% of trail area) 32 15 00-S sq.m. 195 $ $4.1.3 Supply, install, grade and compact 50mm depth of crusher fines for 1.5m wide ex. Trail (642m

length)32 15 00-S m3 50 $ $

AREA 4A Trail Improvements4A.1

4A.1.1 Supply and install guard rail fence 32 31 00-S l.m 42 $ $4A.1.2 Supply and install 'Heritage Farm Gate' 32 31 00-S ea. 1 $ $

SUBTOTAL BASE BID: $

Form of Tender - Appendix 1 (REVISED IN ADDENDUM NO.1)

PROJECT: Johns Family Nature Conservancy - Trail Construction and Improvements

Upgrade existing trail to Type 3: 1.5m wide native material

Upgrade existing trail to Type 3: 1.5m wide native material

Fencing / Gates

Upgrade existing trail to Type 4: 0.5m wide native material

New trail Type 4: 0.5m wide native material

Stream crossing

Crib steps

Crib steps

Trail decommissioning

Page 3: ADDENDUM NO. 1 - Regional District of Central …...ADDENDUM NO. 1 DATE ISSUED: July 29th, 2015 PROJECT: T15-227 – Johns Family Nature Conservancy Trail Construction & Improvements

FT – PAGE 2UNIT PRICE CONTRACT

T15-227 Johns Family Nature Conservancy Trail Construction and ImprovementsSCHEDULE OF QUANTITIES AND PRICES - OPTIONAL WORK

OWNER: Regional District of Central OkanaganCONSULTANT: MMM Group

BID MMCD UNIT TOTALITEM DESCRIPTION REF. UNIT QUANT. PRICE PRICE

OPTIONAL WORK SPEC UNIT QTY. UNIT PRICE TOTAL PRICE

AREA 1 Trail Amenities1.1 Supply and install 'Wayfinding Blaze Post' 32 15 00-S ea. 7 $ $1.2 Supply and install 'Direction Post' 32 15 00-S ea. 2 $ $

AREA 2 Trail Amenities2.1 Supply and install 'Wayfinding Blaze Post' 32 15 00-S ea. 4 $ $2.2 Supply and install 'Direction Post' 32 15 00-S ea. 2 $ $2.3 Supply and install 'Location Sign' (Footing and saddle only) 32 15 00-S ea. 1 $ $

AREA 3 Trail Amenities3.1 Supply and install 'Wayfinding Blaze Post' 32 15 00-S ea. 11 $ $3.2 Supply and install 'Direction Post' 32 15 00-S ea. 4 $ $

AREA 4 Trail Amenities4.1 Supply and install 'Wayfinding Blaze Post' 32 15 00-S ea. 4 $ $4.2 Supply and install 'Direction Post' 32 15 00-S ea. 1 $ $4.3 Supply and install 'Lectern' (Footing and saddle only) 32 15 00-S ea. 1 $ $

AREA 5 Trail Amenities 5.1 Supply and install 'Wayfinding Blaze Post' 32 15 00-S ea. 13 $ $5.2 Supply and install 'Direction Post' 32 15 00-S ea. 2 $ $

AREA 5 Trail Improvements5.1

5.1.1 Clear brush along ex. trail to 2.5m width (1,099m length) 31 11 01 sq.m. 2,750 $ $5.1.2 Trail Grading, Rock/boulder relocation (20% of trail area) (1,099m length) 32 15 00-S sq.m. 330 $ $5.1.3 Install water bars along section of trail to minimize erosion 33 15 00-S ea. 3 $ $5.1.4 Supply, install, grade and compact 50mm depth of crusher fines for 1.5m wide ex.

Trail (1,099m length)32 15 00-S m3 85 $ $

5.25.3.1 Install 4m long x 1.5m wide boardwalk stream crossing 32 34 00-S each 1 $ $

AREA 5A Trail Improvements5A.1

5A.1.1 Supply and install guard rail fence 32 31 00-S l.m 30 $ $5A.1.2 Supply and install 'Standard Farm Gate' 32 31 00-S ea. 1 $ $

SUBTOTAL OPTIONAL WORK: $

Fencing / Gates

Form of Tender - Appendix 1 (REVISED IN ADDENDUM NO.1)

PROJECT: Johns Family Nature Conservancy - Trail Construction and Improvements

Upgrade existing trail to Type 3: 1.5m wide native material

Stream crossing

Page 4: ADDENDUM NO. 1 - Regional District of Central …...ADDENDUM NO. 1 DATE ISSUED: July 29th, 2015 PROJECT: T15-227 – Johns Family Nature Conservancy Trail Construction & Improvements

Form of Tender - Appendix 1 (REVISED IN ADDENDUM NO.1) FT – PAGE 3UNIT PRICE CONTRACT

T15-227 Johns Family Nature Conservancy Trail Construction and ImprovementsSCHEDULE OF QUANTITIES AND PRICES - SUMMARY SHEET

OWNER: Regional District of Central OkanaganCONSULTANT: MMM Group

SUBTOTAL BASE BID WORK $

SUBTOTAL OPTIONAL WORK $

5% GST: $

TOTAL TENDER PRICE: $

PROJECT: Johns Family Nature Conservancy - Trail Construction and Improvements

Page 5: ADDENDUM NO. 1 - Regional District of Central …...ADDENDUM NO. 1 DATE ISSUED: July 29th, 2015 PROJECT: T15-227 – Johns Family Nature Conservancy Trail Construction & Improvements

çç çç çç çç çç çç çç çç çç çç çç çç

çççççççççççççççç

6

6

66

6

666

66

66

"

Y

""

"

LegendConservancy Boundary

Existing Wetlands

Existing Streams

Existing Trails

ESA Level - Very High

Trail Construction and Improvements

6 Wayfinding Blaze Post

" Direction Post

Y Water Crossing

çççççççççççç Crib StepsStart of Area 3

Direction Post (typ.)- Detail 1/L10

New Trail Construction - Class 4 - Detail 2/L8

End of Area 3

Area 3 - Existing Conditions

Area 3 - Crib Step Location

1L4

Area 3Scale 1:2,000 (m) ´

Enlargement - Area 3A

Trail Class:Trail Length (new construction):Trail Length (improve existing):Wayfinding Blaze Post:Direction Post:Water Crossing:Crib Steps:

4 - Nature448 linear metres1,110 linear metres124180 count

Quantities - Area 3Refer to MMCD referenced Schedule ofQuantities for detailed information.

Crib Steps (30 risers w/ 0.9m wide tread)- Detail 4/L8 (similar)- Steps are shown schematically for drawing clarity. - Number of steps to be confirmed on site.

çç çç çç çç çç çç çç çç çç çç çç çç çç çç çç çç çç çç çç çç çç çç çç çç

2L4

Area 3AScale 1:250 (m) ´

Crib Steps (50 risers w/ 0.9m wide tread)- Detail 4/L8 (similar)- Steps are shown schematically for drawing clarity. - Number of steps to be confirmed on site.

Area 3 - Water Crossing

Enlargement - Area 3B

Water run-off area- Construct a rock drain with on-site rock material.- Ensure flat walking surface.

3L4

Area 3BScale 1:250 (m) ´

End of Area 3 End of Area 3

Start - New Trail Construction

End - NewTrail ConstructionStart - ExistingTrail Improvement

End - ExistingTrail Improvement

End - ExistingTrail ImprovementExisting Trail Improvement- Class 4 - Detail 2/L8

Existing Trail Improvement- Class 4 - Detail 2/L8

Wayfinding Blaze Post (typ.)- Detail 4/L9

Remove section of fencing for trail passageand stabilize existing posts

Trail Decommissioning- Detail 1/L11

Lebanon Creek Linear Park

KEY PLAN - 1:40,000

540 Leon Ave, Kelowna, BC, V1Y 6J6t. 250.869.1334 | f. 250.862.4849 | www.mmm.ca

L4

REGIONAL DISTRICT OFCENTRAL OKANAGAN

AREA 3

drawn

revision

A 2015-05-13 Issued for Review LCno date description by

client

drawing title

project no.file name

sheet no.

figure

5115010-0005115010_L4_Area-3

4 of 11scale

LC

date 2015-07-29

approved RF

JOHNS FAMILYproject title

NATURE CONSERVANCY

As Noted

B 2015-07-13 Issued for Tender LCB 2015-07-29 Addendum 1 LC