Page 1: ACORDE FOR TPC TEST Status report. Top Modules Bottom Modules.

ACORDE FOR TPC TESTStatus report

Page 2: ACORDE FOR TPC TEST Status report. Top Modules Bottom Modules.

Top Modules

Page 3: ACORDE FOR TPC TEST Status report. Top Modules Bottom Modules.

Bottom Modules

Page 4: ACORDE FOR TPC TEST Status report. Top Modules Bottom Modules.

Electronic system

Page 5: ACORDE FOR TPC TEST Status report. Top Modules Bottom Modules.

User Interface

Page 6: ACORDE FOR TPC TEST Status report. Top Modules Bottom Modules.

Status

• All the 20 ACORDE modules, electronics cards and cables have been tested before the instalation on the structure.

• The top and bottom structures are inside the clean room.

• The 10 ACORDE modules on top have been tested inside the clean room.

• The ACORDE user interface has been finished.

• The last test with the top and bottom modules will be made next week.

• ACORDE will be ready for the TPC test on the 1st May.