ABUTMENT DISTRESS INVESTIGATION - BMIP
Transcript of ABUTMENT DISTRESS INVESTIGATION - BMIP
October 15-17, 2018
ABUTMENT DISTRESS INVESTIGATION - BMIP
October 15-17, 2018
Frank Estrada III, P.E. – TxDOTGregory Kochersperger, P.E. - HDR
October 15-17, 2018
October 15-17, 2018
Table of contents
3
4-8
9
10
11-17
18-34
1-3
35
Introduction/Safety
History/Background
Possible Causes of Distress
BMIP Project Scope of Work
Condition Assessment
Evaluation
Recommendations for Detailing Changes
1
2
3
4
5
6
7
36Moving Forward – What’s Next?8
October 15-17, 2018
History/Background
Abutment Distress to Backwalls– Backwall to Wingwall Connection– Statewide Phenomenon
Cause Investigated– Repair Difficult
Consultant - HDR– Forensic Investigation– Assessment of Bridges for BMIP – 29 bridges evaluated in the Fort Worth District– Years Built: 1976-2002– Skew Angle: 0 through 42 degrees– Foundation Types: Drilled Shafts & H-Piles– Founded Into: Sandstone, Limestone, Shale, Clay
4
October 15-17, 2018
Abutment Corners w/o Forward Wingwalls
5
October 15-17, 2018
Abutment Corners with Forward Wingwalls
6
October 15-17, 2018
Abutment Corners w/o a Cheeckwall – Previously Repaired
7
October 15-17, 2018
Abutment Corners with Backwalls – Isolated from Retaining Walls
8
October 15-17, 2018
Possible Causes of Distress
INITIAL ASSUMPTIONS: Concentrated forces Backfill Earth pressure loads Environmental Loads applied through the Approach Slab Localized loading
9
October 15-17, 2018
BMIP Project Scope of Work
Condition Assessment– Perform condition assessment of the abutments of all 29 bridges– Perform geotechnical borings at 8 representative locations
Evaluation– Evaluate trends in distress of 29 bridges– Survey other districts and State DOT’s– Identify possible sources of distress– Investigate possible sources with FEA models– Identify most likely root cause and make recommendations for repair– Provide recommendations for possible modification to statewide
standards
10
October 15-17, 2018
Condition Assessments
Inspected 29 bridges across FTW over 5 days in January ‘18
Documentation of every abutment corner– Took photos– Mapped crack patterns– Measured large cracks– Measured rotations– Noted evidence of
settlement
11
October 15-17, 2018
Condition Assessments - Summary
12
NBI # (Name)Type and Observed Damage by Corner
Begin (Left) Begin (Right) End (Left) End (Right)
02-127-0-0259-05-069US 67 over CR 801 (B-07)
Cat 1 - Severe Cat 1 - Severe Cat 1 - Severe Cat 1 - Moderate
02-127-0-0259-05-072US 67 over CR 805
Cat 1 - Severe Cat 1 - Severe Cat 1 - Severe Cat 1 - Severe
02-127-0-0259-05-074BUS 67 over US 67
Cat 1 - Severe Cat 1 -Moderate Cat 1 - None Cat 1 - None
02-127-0-0422-03-032US 67 SB over W. Buffalo Creek (B-06)
Cat 1 - Severe Cat 1 - Severe Cat 1 - Moderate Cat 1 - Severe
02-220-0-0008-13-337Campus Dr over IH 20
Cat 1 - Early Cracking
Cat 1 - Early Cracking
Cat 1 - Minor Cat 1 - Moderate
02-220-0-0008-13-354IH 20 EB over UPRR
Cat 1 - Severe Cat 1 - Early Cracking
Cat 1 - Minor Cat 1 - Early Cracking
02-220-0-0008-13-421IH 35W Conn A over IH 35W & Sycamore Creek
Cat 1 - None Cat 1 - Early Cracking
Cat 3 - Early Cracking
Cat 1 - Minor
02-220-0-0008-13-422IH 20 Conn B over IH 35W, IH 20 & Sycamore Trib
Cat 1 - Early Cracking
Cat 3 - None Cat 3 - Early Cracking
Cat 4 - Minor
02-220-0-0008-13-423IH 35W Conn C over IH 35W & Sycamore Creek (B-05)
Cat 3 - Early Cracking
Cat 3 - Early Cracking
Cat 3 – Early Cracking
Cat 3 – Early Cracking
02-220-0-0008-13-424IH 20 Conn D over IH 35W, IH 20 & Sycamore Trib
Cat 3 - Early Cracking
Cat 3 - Early Cracking
Cat 4 - None Cat 1 - Minor
02-220-0-0008-14-208IH 820 WB over BNSF (FWD RR) (B-01)
Cat 2 - Moderate Cat 2 - Minor Cat 2 - Moderate Cat 2 - Early Cracking
02-220-0-0008-14-260IH 820 WB over Navajo Trail
Cat 2 - Early Cracking
Cat 2 - Early Cracking
Cat 2 - Early Cracking
Cat 2 – Early Cracking
02-220-0-0008-14-261IH 820 EB over Navajo Trail
Cat 2 - Minor Cat 2 - Minor Cat 2 - Minor Cat 2 - Minor
02-220-0-0008-15-227IH 820 NB over Clifford St (B-02)
Cat 2 - Moderate Cat 2 - Early Cracking
Cat 2 - Severe Cat 2 - Severe
02-220-0-0008-15-228IH 820 SB over Clifford St
Cat 2 - Severe Cat 2 - Minor Cat 2 - Severe Cat 2 - Moderate
NBI # (Name)Type and Observed Damage by Corner
Begin (Left) Begin (Right) End (Left) End (Right)
02-220-0-0008-15-254IH 820 SB over Silver Creek Rd
Cat 2 - Moderate Cat 2 - Moderate Cat 2 -Moderate
Cat 2 - Minor
02-220-0-0008-15-255IH 820 NBL over Silver Creek Rd
Cat 2 - Minor Cat 2 - Moderate Cat 2 -Moderate
Cat 2 -Moderate
02-220-0-0008-15-296IH 820 NBL over Chapin Rd
Cat 2 - Early Cracking
Cat 2 - Minor Cat 2 - Severe Cat 2 - Minor
02-220-0-0008-16-305IH 20 WB Collector over UPRR & Walnut Creek
Cat 2 - Moderate Cat 2 - Moderate Cat 2 -Moderate
Cat 2 -Moderate
02-220-0-0008-16-322IH 20 EBL over IH 820 SB & SBFR (B-04)
Cat 2 – None Cat 3 - Minor Cat 2 - Early Cracking
Cat 3 - Minor
02-220-0-0008-16-327IH 20 Connection L over IH 20 & IH 820
Cat 2 - Moderate Cat 2 - Minor Cat 2 - Early Cracking
Cat 2 - Minor
02-220-0-0008-16-328IH 20 Connection M over Ramp T & IH 820 SBFR
Cat 1 - Minor Cat 2 - Moderate Cat 2 -Moderate
Cat 2 - Minor
02-220-0-0353-03-183SH 114 EB over Kimball Ave
Cat 1 - Severe Cat 1 – Minor Cat 1 - Minor Cat 1 - Severe
02-220-0-0353-03-184SH 114 WB over Kimball Ave (B-08)
Cat 1 - Severe Cat 1 - Severe Cat 1 - Severe Cat - Severe
02-220-0-1068-02-107Ballpark Way over IH 30
Cat 1 - Severe Cat 4 - Minor Cat 1 - Minor Cat 4 - Minor
02-220-0-1068-02-330Bridgewood Dr over IH 30 Conn (B-03)
Cat 1 - Moderate Cat 1 - Moderate Cat 1 - Minor Cat 1 - Severe
02-220-0-1068-02-332Bridgewood Dr over IH 30 Conn J
Cat 1 - None Cat 1 - None Cat 1 - Severe Cat 1 - Severe
02-220-0-1068-02-348IH 820 NB Coll over IH 30 Conns H &C
Cat 4 - None Cat 3 - Early Cracking
Cat 4 - Early Cracking
Cat 3 - Early Cracking
02-220-0-1068-02-375Conn B over IH 820 & IH 30
Cat 3 - Early Cracking
Cat 3 - Early Cracking
Cat 4 - None --
Cat 1 – Normal WingwallsCat 2 – Forward WingwallsCat 3 – Previous RepairsCat 4 – No Wingwalls
October 15-17, 2018
Condition Assessment – Other Observations
Pavement Relief Joints – SH114 at Kimball Ave
13
January 17th, 2018Temperature below 50 degrees
May 10th, 2018115 degree pavement temperature
October 15-17, 2018
Condition Assessment – Other Observations
Riprap Movement
14
Significant riprap settlement Voids under riprap
October 15-17, 2018
Condition Assessment – Other Observations
Lateral Ground Movements
15
October 15-17, 2018
Condition Assessment – Geotechnical Work
Borings were taken behind the abutment backwall at 8 locations
Voids were not observed underneath the approach slab during the geotechnical investigation– Voids were observable through the backwall
at some locations during the condition assessments
– Results are inconclusive for whether voids are present
16
October 15-17, 2018
Condition Assessment – Geotechnical Work
Results: Any embankment settlement has already occurred (Newest Bridge was built
in 2002) Underlying soils do not appear to be highly susceptible to settlement The source of the observed riprap and approach slab settlement is likely the
embankment settlement, or erosion
17
October 15-17, 2018
Evaluation – Survey of TxDOT Districts and Other States
TxDOT District survey– Received responses from 9 of 25 Districts
State Survey– Initial screening of states’ details and standard practices revealed 7
states with details similar to TxDOT (Stub Abutments, Non-integral)– Sent to 7 States, 6 surveys returned
Also performed a review of literature associated with backwall damage, embankment movements, and pavement growth
18
October 15-17, 2018
Evaluation – Survey Results - TxDOT
19
DistrictSimilar
Distress Observed
% of Bridges Other Comments
Beaumont Yes 20% Mostly CRCP approaches, suspect pavement growth. Also experiencing significant settlement (>2”) at end of approach slab
Brownwood No 0% ½” to 1” settlementBryan Yes 5% No CRCPChildress Yes 10% Observed with both asphalt pavement and
CRCP. 1” to 2” of settlementDallas Yes 60%** Observed with asphalt, jointed concrete, and
CRCP approaches. 1” to 2” of settlement at end approach slab
Paris Yes <1% No significant issuesPharr Yes 5% Asphalt approach pavement, distress has been
associated with local erosion of backfillTyler Yes 7% Asphalt approach pavementWichita Falls Yes 2% Both asphalt pavement and CRCP approach
October 15-17, 2018
Evaluation – Survey Results – Other States
20
StateSimilar
Distress Observed
% of Bridge Approach Slab Detail Other Comments
Arkansas Yes Not provided 36ft approach slab supported on bracket, free to rotate
Suspect pavement growth
Georgia Yes <1% 30ft approach slab supported on bracket, free to rotate
Jointed pavement or asphalt pavement, wingwall is set outside of bridge rail
Iowa Yes <10% 20ft approach slab supported on bracket, free to rotate
Most damage to backwalls is attributed to de-icing fluid.
Louisiana Yes 10% 20ft – 40ft depending on approach fill condition
Jointed concrete pavement
Missouri Yes <10% 20ft approach slab, pinned at top of backwall
Jointed approach pavement.
Oklahoma Yes 10% 30ft approach slab, pinned at top of backwall
Rail supported on approach slab, inside of wingwall. Asphalt or jointed concrete pavement approaches.
October 15-17, 2018
Evaluation – Survey Results - Themes
Approach settlement is common nationwide Pavement growth is suspected, although there is anecdotal evidence of
distress without CRCP Other states allow approach slab rotation at the top of the backwall
21
Florida Detail with Dowels at Approach Slab Connection
October 15-17, 2018
Evaluation – 3D Finite-Element Analysis
Used LUSAS for modelling Linear 8 node solid elements, Frame
elements and Multi-linear Springs Captures soil-structure interaction with
p-y springs
22
October 15-17, 2018
Evaluation – 3D Finite-Element Analysis
Backwall Plate Study– Evaluate the effect
of uniform load or moment applied at top of idealized backwall
– 3 sided support
23
October 15-17, 2018
Evaluation – 3D Finite-Element Analysis
24
October 15-17, 2018
Evaluation – 3D Finite-Element Analysis
Probable Load Cases for Analysis– Primary Drilled Shaft Differential Settlement– Wingwall Drilled Shaft Settlement/Downdrag– Excessive Lateral Earth pressures– Pavement Growth– Ground Movement– Live Load Applied to an Unsupported Approach Slab
25
October 15-17, 2018
Evaluation – 3D Finite-Element Analysis
Live Load Applied to an Unsupported Approach Slab
26
October 15-17, 2018
Evaluation – 3D Finite-Element Analysis - Results
Primary Drilled Shaft Differential Settlement
27
October 15-17, 2018
Evaluation – 3D Finite-Element Analysis - Results
Wingwall Foundation Settlement/Downdrag
28
October 15-17, 2018
Evaluation – 3D Finite-Element Analysis - Results
Excessive Lateral Earth pressures – At Rest Pressures
29
October 15-17, 2018
Evaluation – 3D Finite-Element Analysis - Results
Excessive Lateral Earth pressures – Passive Pressures (Expansive Soil)
30
October 15-17, 2018
Evaluation – 3D Finite-Element Analysis - Results
Pavement Growth – ¾” Movement applied to back of approach slab
31
October 15-17, 2018
Evaluation – 3D Finite-Element Analysis - Results
Ground Movement
32
October 15-17, 2018
Evaluation – 3D Finite-Element Analysis - Results
Live Load Applied to an Unsupported Approach Slab
33
October 15-17, 2018
Evaluation – Conclusion from Analysis
Analysis indicates two probable root-causes– Pavement growth– Settlement combined with live load on unsupported approach slab
Some pavement relief joints are open Settlement of the approach slabs was consistent
34
The most probable cause of the distress seen in the 29 FTW bridges appears to be loss of support of the approach slab due to settlement of embankment material or erosion of backfill material followed by the application of live load on the approach slab.
October 15-17, 2018
Recommendations for Detailing Changes
Two recommendations for potential revisions to current details:– Reduce Stiffness (Florida DOT detail):
• Single row of dowels to connect the approach slab to backwall• Set wingwalls outside of edge of deck and install rail on the approach slab
– Increase Stiffness (Houston District detail):• Support approach slab on the wingwalls• Utilize a secondary approach slab to provide addition movement
35
Both options limit applied moments at top of backwall and prevent water infiltration of backfill material.
October 15-17, 2018
Moving Forward – What’s Next?
Bridge Division (BRG)– Apply Recommendations– Action Plan Coming– Contact BRG Division if a District would like to try some of the
recommendations What repairs do we continue to use moving forward?
– Continue to use the TxDOT Concrete Repair Manual
36
October 15-17, 2018 37
THANK YOU
QUESTIONS