About AS/RS (1/7)

23
About AS/RS (1/7)

description

About AS/RS (1/7). About AS/RS (2/7). Research areas Storage locations assignment Storage and retrieval policy Physical design. About AS/RS (3/7). Storage locations assignment Randomized Uniformly Closest open location Class-based Turnover ratio Dedicated. About AS/RS (4/7). - PowerPoint PPT Presentation

Transcript of About AS/RS (1/7)

Page 1: About AS/RS (1/7)

About AS/RS (1/7)

Page 2: About AS/RS (1/7)

About AS/RS (2/7)

Research areasStorage locations assignment

Storage and retrieval policy

Physical design

Page 3: About AS/RS (1/7)

About AS/RS (3/7)

Storage locations assignment Randomized

Uniformly Closest open location

Class-based Turnover ratio

Dedicated

Page 4: About AS/RS (1/7)

About AS/RS (4/7)

Storage and retrieval policySingle command (SC)

First-come-first-serve

Dual command (DC) First-come-first-serve Dynamic TSP problem

Assignment problem (static & dynamic) Nearest neighbor

Page 5: About AS/RS (1/7)

About AS/RS (5/7)

Physical design Configurations of rack

Height & Length Velocity

Acceleration & Deceleration Dwell point

Bozer & White(1984) E(SC)=[ ] T

E(DC)=[ ] T

2b3

11

32

30

1b2

1

3

4b

Page 6: About AS/RS (1/7)

About AS/RS (6/7)

Performance measureTravel time

Throughout

Page 7: About AS/RS (1/7)

About AS/RS (7/7)

Load typesMini-load

Unit-load

Page 8: About AS/RS (1/7)

Effects of relocation to AS/RS storage location policy with production quantity variation

Page 9: About AS/RS (1/7)

Introduction Experiment design Simulation Result Conclusion

Page 10: About AS/RS (1/7)

Introduction

The performance of will not be good if production quantity variation and current storage policy is kept

Find the tolerance limits and appropriate strategies for storage policy when production plan change

Random,2 and 3 class-based will be examined

Page 11: About AS/RS (1/7)

Experiment design (1/3)

There are 20 items in the production plan

Production quantities vary between 10-80% Items are assumed as end products

For 2 class-based storageTop four items: first class

Page 12: About AS/RS (1/7)

Experiment design (2/3)

For 3 class-based storage Top four items: first class Next six items: second class

For random storage 1500, 5000 and 95000 unit storage time

Relocation process will be done whenever the crane idles

Page 13: About AS/RS (1/7)

Experiment design (3/3)

Page 14: About AS/RS (1/7)

Simulation (1/4)

GPSS

Simulated for 900,000 unit time

Warn up 300,000

300,000~600,000 unit time: original

Repeat 10 times

Page 15: About AS/RS (1/7)

Simulation (2/4)

Page 16: About AS/RS (1/7)

Simulation (3/4)

Page 17: About AS/RS (1/7)

Simulation (4/4)

Page 18: About AS/RS (1/7)

Result (1/3) Random storage

Page 19: About AS/RS (1/7)

Result (2/3) 2 class-based

Page 20: About AS/RS (1/7)

Result (3/3) 3 class-based

Page 21: About AS/RS (1/7)

Result(4/4)

Page 22: About AS/RS (1/7)

Conclusion (1/2)

Page 23: About AS/RS (1/7)

Conclusion (2/2)

Class-based storage policies perform better but have a lower tolerance

Class-based would be better if performance is the most critical issue

If performance is not critical and frequent production plan changes are expected, random storage would be better