AA-mid antenna element initial design - SKA Indico (Indico) · 2010-11-04 · ragt 4-11-2010 SKA...
Transcript of AA-mid antenna element initial design - SKA Indico (Indico) · 2010-11-04 · ragt 4-11-2010 SKA...
Jo
han
H. P
rag
t
4-11-2010 1SKA Station Design
AA-mid antenna element initial design
The Advanced Instrumentation Program in the SKA Aperture Array system
SKA WP2 Meeting at Oxford UKOctober 28, 2010
Johan Pragt, ASTRONon behalf of the AAVP team
Contributions from: Dion Kant, Mark Ruiter, Raymond van den Brink, Pieter Benthem,
Hiddo Hanenburg, Eric v.d.Wal, e.a.
Jo
han
H. P
rag
t
Topics
• Scope of this talk is limited to AA-mid antenna
• AA-mid antenna technical progress– EMBRACE cost evaluation
– Passive Cooling
– LNA concept changes
– RF-connection lines, main board
– Foil and Foam technology
– Other techniques
Jo
han
H. P
rag
t
AA-Mid Antenna definition focus in this talk
..
Sparse AA
Dense AA
..
Mass Storage
TimeStandard
Central Processing Facility - CPF
User interfacevia Internet
...
To 250 AA Stations
...
DSP
...
DSP
To 1200 Dishes
...
12-15m Dishes
Co
rrelator –
AA
& D
ish
16 Tb/s
80 Gb/s
Control Processors
& User interface
Post Processor
Data
Time
Control
70-450 MHzWide FoV
0.4-1.4 GHzWide FoV
1.0-10 GHzSingle Pixel
Tile &Station
Processing
Jo
han
H. P
rag
t
AA-mid organization, Timeline
AAVS2 AAlow
Sub-system
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
AAVS1 AAlow
demonstrator
construction,
commissioning &
shared-risk obs.
AAVS1 AAmid
Key technol.
demonstrated
detailed design &
pre-construction
1nd gen. instr.
construction,
commissioning &
shared-risk obs.
SKA1 science operations
Q1 2015
Milestone
AAVS2 AAmid
Multiple station
Q1 2013
Milestone
detailed design & pre-constr.1nd gen.
Match with SKA schedule,
SPDO plans
Jo
han
H. P
rag
t
BFC
13%
Other
9%
Center-board
9%
Sub Frame 8%
Feed-board 8%
profile 3%
Hex-board
39%
Coax 2%
Antenna 9%
assembly 5%
Test setup 4%
EMBRACE cost evaluation
Jo
han
H. P
rag
t
Embrace Cost Evaluation
• Control on cost drivers. By modifications and changes in:
• Design
• Assembly, Integration
• Reduction of type of parts
• Part cost and purchase
• production process.
• Main part is in electronics
But: mechanics, assembly, testing should reduce proportional
• Functional key components: antenna, LNA, signal distribution, beamforming. Rest is support. Keep 70/30 share.
• Re use developments and knowledge from:LOFAR HBA,EMBRACEAPERTIF2PAD, FLOWPAD
Jo
han
H. P
rag
t
Specifications AAVS2 AAmid• Technical specs
– Frequency range: 400 MHz - 1421 MHz
– Polarisation: Dual polarisation (Linear)
– Physical Collecting Area: ~2000 m2
– Aeff / Tsys: 40 m2/K
– Electronic scan range: +-45 deg
– Tsys: <50K @ 1GHz
– Nr. of analog beams: 1
– Instantaneous Array Bandwidth: 100 MHz
– Dynamic range A/D Converter: 8bits max (designed for low RFI environment)
– FOV: 108 sq. degr.
(Derived from DS8_T1: Aperture Arrays for the SKA, Rev.0.1, 1 Feb 2010, Sources:SKADS white paper DS8T1R0.91, DoWR0.9)
• Cost goals AAmid Antenna (extrapolated to SKA size and wavelength, today's knowledge):– For the AAVS1 AAmid antenna a cost of 1500 euro as goal.
– Design for AAVS2 AAmid antenna at level of <1000 euro/m2 AA-mid antenna.
Jo
han
H. P
rag
t
Passive Cooling
• Validation of thermal simulation,
• sun radiation input load for different materials.
• Radiation output load of the materials
• Develop passive cooling concepts, using ground as thermal mass
Jo
han
H. P
rag
t
LOFAR HBA, 20000 M2
Europe
Jo
han
H. P
rag
t
Aluminum Large Plates
4-11-2010 10SKA Station Design
Multiple vivaldi antennas in one sheet
LNA close to pick-up point
Plastic support to keep tops in place
Jo
han
H. P
rag
t
Aluminum Large Plates
4-11-2010 11SKA Station Design
Metal-Metal joining by clinching
Assembled together laying down or standing up
Also expandable (connectable) in other direction
Jo
han
H. P
rag
t
Application in APERTIF1 M2 on dish of 25 M = 200 M2 (effect.)
Jo
han
H. P
rag
t
Aluminum Large Plates
4-11-2010 SKA Station Design 13
Signal transmission through small (cheap) PCBs.
Jo
han
H. P
rag
t
EMBRACE, 170 M2
Netherlands, France
Jo
han
H. P
rag
t
Aluminum Large Plates
4-11-2010 SKA Station Design 15
Vacuum formed “tile” bottom for six modules
(approx. 1.5 x 2m)
Shape to fit poles
Placement in field by forklift or crane, like
LOFAR HBA.
Jo
han
H. P
rag
t
Aluminium Plates Station
4-11-2010 SKA Station Design 16
• XX “tiles” in a substation.• Every substation slightly tilted.• Substation closed by EPS wall en top.• Passive cooling by ground connection through poles.
• SKA station formed by multiple substations.• Walkable spaces between substations.• 56m diameter
Jo
han
H. P
rag
t
Foils
4-11-2010 SKA Station Design 17
Foils put together with conductive glue or paste, or connection based
on capacity coupling
Flat transportation, for assembly folded like an accordeon.
EPS bottom with PCB (transmission line) spaces
Foil groundplane
Jo
han
H. P
rag
t
FLOWPAD, 2PAD 4M2
Netherlands, United Kingdom
Jo
han
H. P
rag
t
Next StepsAA-mid
• Other Workpackages: crucial input required
– Open for any LNA. LNA is crucial and we fully support new developments from any group or industry
– Beamformer: We rely on developments at Nancay, fall back is actual EMBRACE LNA (not preferred)
– Selection of front-end antenna principle based on technical input: ORA, Vivaldi?
– Backend, data processing: Shared interface with AA-low, need to match AA-low and AA-mid specs and keep close contacts with Backend developments
– Same for control software
– Same for verification and data reduction software (LOFAR like??)
– Need specific knowledge from candidate sites to define environmental details and use local contacts for radome housing design (temp., wind, animal protection, ..)
Jo
han
H. P
rag
t
Next StepsAA-mid
• NEXT steps:
– low cost electronical parts
– Detailing electronic subsystems for cost reduction,
– RF line internal connections, new designs and developments
– Tile size definition
– Competion aluminium – foil antenna
– Low-cost tile assembly
– Cooling concept toward design
• Industralisation as in LOFAR (AAVS2)
Jo
han
H. P
rag
t
Summary
• AAVS - AAmid will make a next step into design to SKA
• concentrating on cost with the technical knowledge of EMBRACE and other instruments and demonstrators
• We are not yet there and need a few years for some significant steps
• Industry is our partner
• Questions?