A K Srivastava_Essar Power
-
Upload
vishal-singh -
Category
Documents
-
view
219 -
download
0
Transcript of A K Srivastava_Essar Power
-
7/31/2019 A K Srivastava_Essar Power
1/13
1Essar Power Limited
A positive a++itude
ESSAR POWER
CONFERENCE ON THE POWER MARKET
POST ELECTRICITY ACT 2003
15th October 2003
INDEPENDENT POWER PRODUCERS PERSPECTIVE
A K SrivastavaMD - ESSAR POWER LTD.
-
7/31/2019 A K Srivastava_Essar Power
2/13
2Essar Power Limited
ESSAR OIL LTD
EXPLORATION &
PRODUCTION
REFINING
MARKETING
ESSAR
CONSTRUCTIONS
TURNKEY
PROJECTS
- Marine
- Pipeline
* Water line* Gas line
- Industrial Plant
- Civil & Irrigation
- Roads & Highways
Group Business Structure
ESSAR GROUPESSAR GROUP
STEELSHIPPING
& TERMINALOIL & GAS POWER TELECOM CONSTRUCTIONS
ESSAR SHIPPING
OIL TANKERS
BULKERS
OFFSHORE
SUPPLY VESSELS
TERMINAL
FACILITIES
ESSAR POWER
HAZIRA
515 MW CC
VADINAR POWER
COMPANY
JAMNAGAR
77 MW COGEN
HUTCHISON ESSAR
JV with HUTCHISON
- Delhi
- Mumbai
- Chennai
- Kolkata
- Gujarat
- Andhra Pradesh
- Karnataka
- Haryana
- Rajasthan
- East UP
- Punjab
HAZIRA
OPERATIONS
- Hot Briquetted Iron
- Hot Rolled Coils
- Down Stream
Complex
VIZAG OPERATIONS
HY-GRADE PELLETS
JV with STEMCOR
- Pellet Plant
- Beneficiation plant
- Slurry pipeline
INDONESIA
OPERATIONS
P T ESSARDHANANJAYA
- Cold Rolling Mill
-
7/31/2019 A K Srivastava_Essar Power
3/13
3Essar Power Limited
PROJECT CONFIGURATION
Capacity : 515 MW Combined Cycle Power Plant.
Commissioning Dates
First & Second GT - Aug 95
Third GT - Nov 95
Combined Cycle - October 97
Comprises of :
3 Gas Turbines ( GE Make Frame 9E)
of 110 MW each.
3 HRSG (KHIC Make)
1 Steam Turbine ( GE Make)
of 185 MW.
Multi Fuel capability(Naphtha/ NGL/NG/HSD)
Instrumentation & Controls (Siemens Make)
Hazira
-
7/31/2019 A K Srivastava_Essar Power
4/13
4Essar Power Limited
POWER PURCHASE AGREEMENT
GEBESSAR
STEEL
ESSAR
POWER
515 MW
300 MW215 MW
-
7/31/2019 A K Srivastava_Essar Power
5/13
5Essar Power Limited
SALIENT FEATURES OF PPA WITH GEB & ESTL
Allocated Capacity - 300 MW for GEB & 215MW for ESTL
Effective date - 1st July 1996 for GEB & 1st April 1996 for ESTL
PPA : in accordance with GOI guidelines - Two Part tariff Structure
Recovery of Fixed Charges at 68.49% PLF. ROE @ 16% at PLF of 68.49% PLF,Incentives @ .575% per % increase in PLF upto 80%.
Approved Capital Cost Rs. 957 Crores for GEB & Rs. 810 Crores for ESTL
Deemed Generation - 80% PLF average through the year
Deemed Non-Generation - applicable if Essar not able to generate as per the
declared availability
-
7/31/2019 A K Srivastava_Essar Power
6/13
6Essar Power Limited
PLANT PERFORMANCE 1998-2003
-99 99 -99 99 -99 99 -9 99 9 -9 99
Plant A vailability (%) 99 99 99 99 99
PLF(%) 99 99 99 99 99
PLF (GEB ) (%) 99 99 99 99 99
PLF (Essar Steel) (%) 99 99 99 99 999
-
7/31/2019 A K Srivastava_Essar Power
7/13
7Essar Power Limited
FINANCIAL PERFORMANCE 1998-2002
(Rs. in Crs.)Parameters 98-99 99-00 00-01* 01-02
Total Income 718 829 1034 648
EBIDTA 422 451 614 454
Interest 271 273 372 293
Depreciation 111 114 173 119PBT 39 64 69 42
Tax 0 1 6 3
PAT 39 63 62 39
* for 18 months
-
7/31/2019 A K Srivastava_Essar Power
8/13
8Essar Power Limited
OUR EXPERIENCE AS IPPS
Lot of Clearances were required to set up the project such
as Environmental Clearance
State & Central Government Clearances
Techno-economic Clearance of Central Electricity
Authority (CEA)
PPA Finalisation was a long drawn processProblems encountered during implementation of PPA
States are not honouring commitment given in PPAs
concerning Payment Security Mechanisms
Deduct rebate for timely payment even though payment is
not made in time Due to non-payment of dues to IPPs and mounting of
overdue
-
7/31/2019 A K Srivastava_Essar Power
9/13
9Essar Power Limited
OUR EXPERIENCE AS IPPS
Most of the IPPs are defaulting to FIs / Banks
Do not have enough fund for O&M of plant
FIs / Bank tend to charge penalty & LD for not paying in time
which is not recoverable in tariff
Though the plants are supposed to be Base-Load
station, gas-based plants are asked to be back-down off &
on which results in Frequent Starts & Stops
Higher heat rate due to part load operation and frequent
startups
Most of the states have started reopening & re-negotiation
of PPA . This is threatening the viability of projects.
-
7/31/2019 A K Srivastava_Essar Power
10/13
10Essar Power Limited
IMPACT OF ELECTRICITY BILL 2003 FOR DEVELOPMENT OF POWER SECTOR
Provisions and intent of EC 2003 is a step forward in
Power Sector reforms such as Power Generation is de-licensed except hydro
Open access system in Transmission
Open access in Distribution
Generators can supply Power directly to bulk consumers
Electricity Regulators role is defined and enlargedHowever the above mentioned good intentions may be
difficult to realise in practice in near future
Open Access as of now would be an As-is-Where-is
As-Available-When-Available
For Supplying Power to bulk consumers directly, anelement of Surcharge in lieu of cross subsidy would be
levied. How long cross subsidy would continue?
What would be the basis of Surcharge?
-
7/31/2019 A K Srivastava_Essar Power
11/13
11Essar Power Limited
IMPACT OF ELECTRICITY BILL 2003 FOR DEVELOPMENT OF POWER SECTOR
What issues EC 2003 has not addressed?
Power is in concurrent list. Each State, as a source of
revenue has imposed Electricity Duty on Power to
Consumers which varies from Ps. 5/unit to Ps. 50/unit
If Electricity Act 2003 does not provide any guidelines to
States on Electricity Duty, then States may impose such
Duty rates which may nullify good intentions of PowerSector reforms
As a suggestion, EC 2003 can specify that Electricity Duty
rates as prevailing on 10th June 2003 shall be the cap.
Ideally it should be uniform throughout the Country.
Electricity Duty should be scrapped on Captive PowerUsers.
-
7/31/2019 A K Srivastava_Essar Power
12/13
12Essar Power Limited
ROAD AHEAD
For increasing and encouraging the generation in Private Sector
Generators should be encouraged to take up Distribution ofElectricity
To mitigate existing IPPs financial problems, they may be given
preference in allocation of Distribution Circles.
Open Access in Transmission and Distribution need to be
given on fixed basis
Surcharge for supplying to the bulk consumers should bereasonable and abolished in definite period
Electricity Duty to be rationalised
Power trading needs to be encouraged
Tariff should be decided based on competitive bidding and cost-
plus method should be discouragedElectricity boards needs to be restructured to make them
financially viable units
-
7/31/2019 A K Srivastava_Essar Power
13/13
13Essar Power Limited
THANK YOU