JOURNEY TO POWER INTELLIGENT IT—BIG DATA EMPLOYED

Mohamed SohailImplementation Specialist, EMC

Denis CantyTechnical Test Architect, EMC

Omar AboulfotohTechnical Support Engineer, EMC

Page 2: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 2

Table of Contents

Executive Summary ................................................................................................................... 3

Preface ...................................................................................................................................... 4

Steps to a Power Intelligent Data Center.................................................................................... 7

Power Smart Analytic Software .............................................................................................. 7

Virtualization Impact ..............................................................................................................11

Sustainable Power Cost Savings ...........................................................................................12

Location and Design Considerations .....................................................................................14

Air Management ....................................................................................................................15

Right-Sizing and Energy Star ................................................................................................17

NSIDC “National Snow and Ice Data Center” Project: ...........................................................19

Case Study: EMC Durham Cloud Data Center ..........................................................................23

Overview ...............................................................................................................................23

Why EMC decided to build Durham Data Center? .................................................................24

Design and Construction .......................................................................................................25

Durham Data Center Architecture ..........................................................................................26

Migration Process ..................................................................................................................27

Awards ..................................................................................................................................28

Case Study: “Iceland”................................................................................................................29

Appendix ...................................................................................................................................30

Biographies ...............................................................................................................................32

Disclaimer: The views, processes, or methodologies published in this article are those of the

authors. They do not necessarily reflect EMC Corporation’s views, processes, or

methodologies.

Page 3: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 3

Executive Summary

Being environmentally sustainable is a big challenge with this global recession and stretch

economy not just for cash saving, but also for saving the globe. No one can ever ignore the

tremendous growth of the exchanged data through the internet and the cloud, and not too much

people are aware about what is happening in the backend of this process or what is behind a

datacenter.

Sustainable data centers ensure that every watt IT consumes delivers the greatest business

benefit. Today’s data centers have become increasingly large and consume a large amount of

energy, leading to a greater amount of carbon emissions. It has become critical for data center

architects to consider best practices when building a new data center. Many organizations such

as ASHARE “American Society of Heating, Refrigerating, and Air-Conditioning Engineers” and

LEED “Leadership in Energy and Environmental Design” organizations have set rules to be

followed to be compliant and sustainable.

This Knowledge Sharing article concentrates on best practices where “Cloud meets Big Data” in

our journey to optimize power efficiency. We highlight a winning idea in the EMC annual

innovation showcase 2012; “EMC Power Smart: Energy Usage Big Data Model for EMC

Products Worldwide” “A Smart Energy Monitoring and Reporting System”. We also illustrate

best practices into the modern and “sustainability compliant” data centers which will help us in

our journey towards green IT. The article will also introduce the importance of air management,

free cooling, and the virtualization impact from the inside steps prospective. Additionally, we

discuss data center location and design considerations. Lastly, we introduce some role models

who applied innovative technologies to achieve fantastic results like the Snow and Ice data

center and EMC Durham Center of Excellence data center.

Page 4: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 4

Preface

One of the modern challenges these days is saving our earth and being sustainable. A very

important factor that affects the decisions of the IT managers is the power consumption and the

emission of carbon. A power intelligent data center is defined as one in which the mechanical,

lighting, electrical, and computer systems are designed for maximum energy efficiency and

minimum environmental impact.

In the graph below are some of the reasons why we should be sustainable:

Figure 1-1: Reasons for adopting sustainable solutions

While many IT shops operate low-profile data centers safe from public scrutiny. For many

industries, data centers are one of the largest sources of greenhouse gas emissions.

Companies may be required to report data center carbon emissions in the near future.

The majority of data centers, both old and new, continue to waste energy at a prodigious rate.

There are many, including the big players, who have made gigantic strides for both themselves

and the industry in developing energy efficient designs and operations that would have been

Page 5: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 5

considered impossible just a few years ago, but they are still the exception, although not quite

so rare of an exception as they once were.

“People are almost universally unaware of what it really costs to transmit, store and

retrieve the incalculable amount of data they create when they widely distribute and

replicate all the stuff we all now do on a daily basis.”

Robert McFarlane - Data center power and cooling expert

The power-waste problem has three major causes. One is running processors 24/7/365 that do

little to nothing. However, most servers have the ability to run in energy-saving mode, indicating

that the manufacturing industry has tried to take steps to reduce the problem. Still, IT managers

are afraid to invoke them out of fear that something won't respond as quickly as expected if it

takes a couple of extra nanoseconds to reach full power. However, there are two bigger reasons

that are, frankly, unforgivable:

1. Most companies are willing to consider energy conservation only if there is no additional

capital cost. Long-term savings, both of energy and cost, may be given lip service, but in

the end they often become much less important. This is partly due to our being held

hostage to quarterly results, and partly because energy conservation is still driven

almost entirely by dollars rather than environmental responsibility. A high percentage of

data centers still don't even know their power consumption or costs.

2. Too many engineering firms don't really understand energy efficient data center design,

which is different than the design of other energy efficient buildings, particularly where

mission-critical operations are involved. There is no excuse today for the power and

cooling infrastructures of new data centers to remain so energy inefficient , even if their

owners are unwilling to pay for the greater efficiencies that could be achieved with

today's equipment and techniques.

Changing the perception that data transmission is "free" is a matter of public education, which

articles like this may at least start to provide to a small number of people. However, as long as

there is resistance even to using energy-efficient light bulbs in our homes, we are unlikely to

limit our indulgence in all the "fun stuff" to which we have become addicted.

Page 6: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 6

Some facts about the data centers

"The industry dirty secret?" I've been writing and talking about it for more than 10 years

now, as have many other commentators. Sure, IT has been trying to keep it quiet, as

they know their organizations would not be very happy to find that 90% of the energy

going in to a data center is just wasted. Without a good plan as to how to move this

more to the below 50% level, only a brave IT director would say, "Hey, guess what? I'm

in charge of a system that is less than 10% efficient, and I don't have a clue what to do

about it."

Clive Longbottom - Service Director at Quocirca

Longbottom’s quote was made pre-virtualization and cloud. Now, virtualized systems can easily

run at greater than 50% utilization rates, and cloud systems at greater than 70%. Cooling

systems no longer have to keep a data center at less than 68 degrees Fahrenheit; data centers

can now run at close to 86 degrees Fahrenheit with little problem.

UPS systems are far more efficient now and can often replace the need for generators to fire up

when the power outage is only for a short period of time. All of these aspects mean that not only

can the IT hardware be more effective, but also the amount of energy used to support the data

center can be minimized. Consequently, a complete rework of a data center can move its PUE

from greater than 2.5 to less than 1.5—a massive shift in data center efficiency.

However, there is a downside of this: Carrying out such a rework means throwing out everything

that is already there. Few organizations would be happy to throw out several million dollars of

equipment and buy several million dollars more. Therefore, the majority of data centers are in a

state of change at the moment. Old hardware is still in service as new hardware is being

brought in, with the old equipment planned for replacement as its effective end of life is reached.

As such, over a period of five to 10 years a major shift will take place in the efficiency of private

data centers as they are reworked to adopt newer technologies. New data centers will be built to

LEED “Leadership in Energy and Environmental Design”, and ASHRAE “(American Society of

Heating, Refrigerating, and Air-Conditioning Engineers)” standards and few will have PUEs

above 1.3.

in addition, there is the increasing move towards co-location—sharing the data center facility

and making the most of economies and effectiveness of scale from UPS's and generators

involved in a massive facility—even where the equipment being installed for a single customer

Page 7: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 7

is relatively small. More co-location providers are now insisting that customer racks and rows

are engineered to latest standards to optimize the overall effectiveness of the facility and the

equipment it houses.

Then there is cloud. A cloud provider must be efficient, else their business model will not work. It

is simply smart business to create a data center that has a low PUE, and where the equipment

is being run to the most optimum utilization rates.

Finally, there are the government mandates themselves. For example, the Carbon Reduction

Commitment Energy Efficiency Scheme in the United Kingdom has caused many organizations

to focus on energy efficiency to avoid large "taxes" on their carbon emissions.

Steps to a Power Intelligent Data Center

“A large data center can consume as much power as 8,200 homes. Increasing its efficiency by

30% is equivalent to taking 4,700 cars off of the road.”

Dick Glumac founder of Glumac Full-Service Consulting Engineering Company

The idea is not a complicated one. It will contribute on two wings:-

1. Working smartly with the most important elements of the data center from ‘inside’—the

storage and the servers—may be extended to the rest of the elements depending on the

nature of the equipment. Running smart software and reporting tools employing big data

analytics help reduce the power consumed by the data center components.

2. Working smartly on the data center from ‘outside’—i.e. choosing the data center

location, using alternative power sources, and how this can affect the power

consumption of the data center.

Power Smart Analytic Software

The data explosion that is evident today has shown that data is the currency of the digital age,

and data can be classed as being the new electricity. In the 19th century, electricity turned from

being a science experiment into a necessity for human existence and advancement. The same

can be said for data today.

A major application for utilizing data is in monitoring power consumption of our systems. Our

products need to become smarter in how they are profiled in relation to energy use.

Page 8: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 8

A proposition is to provide tools that measure power consumption at the device level to manage

energy the way they manage other aspects of storage. Kilowatt and kilowatt per hour are

standard energy metrics. When applied to storage, we can get an accurate way to measure the

kilowatt/terabyte. A more common metric at this point is kilowatt per rack. Due to increased

density, data centers today are pushing beyond 4 kilowatt per rack; at 6 kilowatt per rack,

they're getting into a heat danger zone.

An individual drive uses 5W to 15W of power depending on its capacity, rotation speed, form

factor, and operating state. However, "you can't just multiply the number of drives in an array by

some average power rating to get a total," says Mark Greenlaw, senior director, Storage

Marketing at EMC. Power consumption of the array is more than the sum of the power used by

the individual drives. For instance, controllers and other components also consume power. This

leads to storage density measurements of terabytes per square foot and terabytes per kilowatt.

Storage managers must also consider SAN switch power and cooling. Switches consume less

power in the data center than servers or storage mainly because there are relatively fewer

switches. Still, the power consumption of a switch is significant. "A large switch will use 1,000W

[1 kW] or more," says Ardeshir Mohammadian, senior power systems engineer at Brocade

Communications Systems. Higher port density and performance increases switch power and

cooling consumption. Thus, don't be surprised to see new “power measurements”, such as

kilowatt per port and kilowatt per gigabyte.

After getting such accurate data, we can use our backend smart software to determine the

components that consume more power and apply best practices to reduce this power, or seek

the peak power saving from the device depending on the real data acquired from the data

center components. The data can be collected by connecting it to a private cloud at the

customer’s side and then can be reported to a specialized service provider, i.e. EMC to develop

the ways to optimally run the arrays together to reach the best state of power consumption.

Analysis of the current configuration of each device reflects the customer’s power consumption

and current device configuration. The retrieved data can be analyzed further by EMC experts to

modify the design architecture, microcodes, and the installed software on these arrays to reduce

power consumption and maximize power utilization as much as possible to comply with the

global initiative of going green.

Page 9: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 9

How data center managers interact with systems in regard to power consumption metrics must

evolve. Semi self-managing systems should be researched, whereby the system manages a

portion of its power consumption based on a series of readings taken from the system itself.

System power consumption depends on a hybrid mesh of interactions between software and

hardware components. Suppose that data collected were to include sensor readings from

PSU’s, c-state analysis of CPU’s, wake up cause analysis of operating systems, and power

consumption increases from software execution. Intelligent algorithms could then consider

historical performance and system/engineer interaction to adjust lower level system settings to

reduce the power consumption of the system. These algorithms could be system or cloud

hosted, but their data flow would come from a custom built cloud-based data warehouse.

By utilising the data warehouse further, it is possible to trend system performance based on

environmental, demographic, and time-based metrics to predict future outages and

inefficiencies. This would further enhance the ROI model to a potential customer.

Naturally, this would require building the historical data of the system, but over time, the

systems themselves would become more power intelligent. One area of concern is that having

machine based algorithms adjusting system settings could lead to inefficiencies and even

critical processes being closed. However, by utilising a priority system, whereby both software

processes and hardware are tagged as critical, the algorithms would not have control over

them.

The idea of having a system energy usage data warehouse also offers to the potential for EMC

to group and classify its customer’s data centers into pods, where similar customers could then

adopt the system settings that exist already to their own architecture.

Given that a large percentage of software executed on EMC systems is custom EMC software,

the concept of green software can be adopted. This would enable systems to provide feedback

to our development teams on energy use by our software applications, which lead to greener

software and increased software value for our customers.

Benefits of this approach:

Accurately determine the power consumption of every EMC product using a Big Data

approach to collect and analyze the necessary data to reach optimal results through

predictive means or otherwise.

Page 10: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 10

Measure the efficiency of the architecture design of the devices with different

configurations. This is a challenge if we have a full configuration, as we have many

factors in measuring the consumed power.

Reduce energy use by our products + reduce data center cooling power = cost reduction

for our customers. This will help open the door for a new generation of energy efficient

products.

Leverage innovation in EMC’s technologies to help conserve power consumed by EMC

and non-EMC products for customers. Future customers will also have a vision about

the expected power savings and benefits using EMC’s “cloud and big data approach”

giving EMC priority when it comes to data center planning.

The Customer will consider TCO of the products, not only the initial price.

This will help the customers become sustainable, decrease emissions, and be compliant

with the rules which contribute to limiting global warming.

C

Power

Consumption

Metric

Data

10

01

10

01

10

0110

01

Customer

Power Smart

Customer

Report

EMC

Power Smart

Software

EMC Power Smart Cloud with Analytics

10

0110

01

EMC Software Developer

10

01

10

01

10

01

10

01

10

0110

01 Power Smart

Developer

Report

Software

Value

Figure 1-2: EMC Power Smart Solution Illustration

For further insight, please see EMC Power Smart – Sustainability Award Winner at the 2012

Innovation Showcase – Innovator: Denis Canty MIEI BEng MENC MEngSc

Page 11: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 11

Virtualization Impact

A virtualization and consolidation project is often a step in the right direction toward sustainable

computing. Research indicates that a server often only utilizes between 5 and 15% of its

capacity to service one application. With appropriate analysis and consolidation, many of these

low utilization devices can be combined into a single physical server, consuming only a fraction

of the power of the original devices and saving on costs, as well as taking a step toward a more

environmentally friendly data center environment. The basic concept of virtualization is simple:

encapsulate computing resources and run on shared physical infrastructure in such a way that

each appears to exist in its own separate physical environment. This process is accomplished

by treating storage and computing resources as an aggregate pool which networks, systems,

and applications can leverage on an as-needed basis.

Virtualization provides Data Center Consulting Services which drive business agility by

simplifying business infrastructure to create a more dynamic and flexible data center.

Virtualization is a key strategy to reduce data center power. With virtualization one physical

server hosts multiple virtual servers. Virtualization enables data centers to consolidate their

physical server infrastructure by hosting multiple virtual servers on a smaller number of more

powerful servers, using less electricity and simplifying the data center. Besides improving

hardware use, virtualization reduces data center floor space, makes better use of computing

Page 12: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 12

power, and reduces the data center’s energy demands. Many enterprises are using

virtualization to curb the runaway energy consumption of data centers.

Sustainable Power Cost Savings

“A large data center can consume as much power as 8,200 homes. Increasing its

efficiency by 30% is equivalent to taking 4,700 cars off of the road.” Dick Glumac, founder

of Glumac Company.

Figure 1-3: Cost influence curve

The data center industry is on the rise again, but with a different focus. In the 90's, it was

construction speed; this time around it is operating efficiency. Data center owners have had to

learn the hard way that operating costs can quickly outweigh construction costs. Glumac has

developed an exciting new data center design process with the efficiency issue at its core. This

translates into huge savings for our clients.

Large corporations are moving away from piecemeal green activities and are adopting

broader strategies to cope with the environmental issues that affect their business. For

Page 13: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 13

the IT director this means less work on isolated green "hobbies", and more joined-up

thinking with peers to create sustainable policies.

Geoff Lane, partner, sustainable business solutions at accounting and consulting firm Price

Waterhouse Coopers and former head of environmental policy at the Confederation of British

Industry, reports that more clients are seeking advice on how to benchmark their green activity.

"Companies regularly come to us and say, 'We have recycling programs or duplex printing

policies in place but we want to raise our game'."

A fresh focus for IT departments in all organizations is how to make the data centers

environmentally sustainable. Computing power per square foot may have increased with the

use of multicore chips and blades, but this concentration of hardware also generates more heat

and the problem of how to dissipate it.

According to analyst firm Gartner, most large enterprises' IT departments spend about 5% of

their total IT budgets on energy. This could rise by two to three times within the next five years.

One way to decrease power consumption is to better integrate facilities teams and engineers

with the IT department. "The typical engineer does not look past the power supply or the

gateway to the IT piece," says Patrick Fogarty, director of consultant engineering practice,

Norman Disney and Young, and a speaker at Datacenter Dynamics' Next Big Datacenter

Challenge energy summit in London in February.

Similarly, the IT team is predisposed to consume all available power to keep its applications

running, according to several delegates at the summit.

"If we could do it all over again without the legacy datacenter architecture, we would take a

more holistic view. From the CPU to the actual transmission, there are a lot of inefficiencies

leaked through cabling, plus the massive inefficiencies in the ways we cool IT," says Fogarty.

CIOs and their staff in many organizations are turning to the data center to try to plug these

leaks.

"One of the biggest issues around power consumption in IT is the datacenter," says Ben Booth,

global chief technology officer at research firm Ipsos which has data centers scattered around

the globe, ranging from vast server farms to machines stuffed into back offices. Booth is

Page 14: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 14

reviewing ways to consolidate these in order to reduce the bill, reduce numbers, and provide a

round-the-clock service to customers.

Location and Design Considerations

“Site selection can mean the difference between a data center costing $3 million or $11

million a year in utility costs".

Chien Si Harriman, Energy Modeling expert

When a company buys land, it is important to consider the property’s suitability to house a

server environment. The most desirable location is one that supports the data center site

selection objectives to safeguard data server equipment and accommodate growth and change

of the data center.

The location of a data center can be as critical as the services offered there. Many companies

need access to their servers on a 24/7/365 basis.

Data center requirements have changed dramatically in the last few years. Earlier, the main

concern in choosing a location for data center revolved around network accessibility, as fiber

networks connecting data centers were concentrated in the main cities. This is still a concern.

However, the growth of high-speed network infrastructure and remote access capabilities allows

data centers to be built in any location. Nevertheless, selecting the physical location of the data

center still forms an integral part of data center strategy, keeping in mind a lot of other factors

that have a bearing on the total cost of ownership (TCO) of the organization.

Data center location continues to play a pivotal role in deciding its operational costs and

ensuring its smooth functioning. An improper data center location not only results in high

operating costs but may also lead to loss of revenue due to disruptions in data center

operations.

The other consideration is power. With power consumption on the rise, blackouts are becoming

a common problem in areas with poor power infrastructure. As data centers require enormous

amounts of power—failure of which can cause unexpected downtime—availability of abundant

low cost power is an important consideration. Companies today are looking at alternative

sources of energy such as hydroelectric power and biofuel that significantly reduce operational

costs.

Page 15: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 15

Power-intelligent data centers are an obvious answer to efficient power management as

environmental consciousness has become a key corporate parameter. Besides, data centers

built in cooler climates can reduce costs because outside air can be used to keep it cool

automatically.

Air Management

Improving "air management"—optimizing the delivery of cool air and the collection of waste heat

—can involve many design and operational practices. Air cooling improvements can often be

realized by addressing:

• Short-circuiting heated air over the top or around server racks.

• Cooled air short-circuiting back to air conditioning units through openings in raised

floors such as cable openings or misplaced floor tiles with openings.

• Misplacement of raised floor air discharge tiles.

• Poor location of computer room air conditioning units.

• Inadequate ceiling height or undersized hot air returns plenum.

• Air blockages such as often happens with piping or large quantities of cabling under

raised floors.

• Openings in racks allowing air bypass (“short-circuit”) from hot areas to cold areas.

• Poor airflow through racks containing IT equipment due to restrictions in the rack

structure.

• IT equipment with side or top-air-discharge adjacent to front-to-rear discharge

configurations.

• Inappropriate under-floor pressurization - either too high or too low.

The general goal for achieving better air management should be to minimize or eliminate

inadvertent mixing between cooling air supplied to the IT equipment and collection of the hot air

rejected from the equipment. Air distribution in a well-designed system can reduce operating

costs, reduce investment in HVAC (heating, ventilation, and air conditioning) equipment, allow

Page 16: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 16

for increased utilization, and improve reliability by reducing processing interruptions or

equipment degradation due to overheating.

Figure 1-4: Data Center Design and Air Flow

Solutions to common air distribution problems include:

• Use of "hot aisle and cold aisle" arrangements where racks of computers are stacked

with the cold inlet sides facing each other and similarly the hot discharge sides facing

each other. (Figure 1-3)

Page 17: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 17

• Blanking unused spaces in and between equipment racks.

• Careful placement of computer room air conditioners and floor tile openings, often

through the use of computational fluid dynamics (CFD) modeling.

• Collection of heated air through high overhead plenums or ductwork to efficiently return

it to the air handler(s).

• Minimizing obstructions to proper airflow.

Right-Sizing and Energy Star

The U.S. Environmental Protection Agency (EPA) recently extended its Energy Star program to

include rack servers.

Energy Star is a way to provide forced information about products so that consumers can make

better decisions. People might want to choose high-efficiency products, but they don't know how

to compare the efficiencies among products in a standardized way. There is a lot of confusion

about trying to buy high-efficiency products in the data center. [The Energy Star program] is a

huge challenge because it's so difficult to compare two servers as to their function; all the

benchmarks for server usage are so hotly disputed between the vendors.

[The EPA] has been working on this for about 5 or 6 years. The genesis for doing this came out

of a charrette, a group of experts getting together to work on a problem, done by the Rocky

Mountain Institute. They brought people together from the data center industry to think about

this problem of energy efficiency well in advance of the current wave of interest. They wrote a

report where one of the results was to push the government to consider extending Energy Star

to servers and other data center related products. I think it's a great idea.

I think it can go further. Half of the power that comes in from the utility companies never even

makes it to the server. Rather, it's wasted in power systems and cooling systems, the kinds of

products that APC makes. We have a huge responsibility to fix that. How would that be

measured?

Energy Star has other programs besides these product level certifications where they recognize

efficient organizations. They try to recognize solutions that are exceptional in their field for

performance. It's not benchmarked against others. I think that's a good way to start when we

Page 18: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 18

have a difficult problem; just select solutions that we know have done a better job. As we get

better, understand it.

I think they should start doing that for complete data center infrastructure designs. If each part is

efficient, it doesn't necessarily make the data center efficient. I can still make a bad data center

out of efficient parts. Though part-level qualifications are nice, if I take very efficient servers and

throw 18 million of them in a data center when I only needed six, I'm going to waste a lot of

power. It's not just the parts. We have to look at the complete system. Perhaps something like

what LEED (Leadership in Energy and Environmental Design) does?

I totally agree with that, because one of things that people are going to find is what will they do

with all the junk from the data center after it is retired in 12 years? Can it be recycled? LEED

thinks about those kinds of things; recyclability, disposability, etc. A lot of people aren't thinking

about that today but the day will come when they will be thinking about it for sure. While today

we can throw a lot of things away in a dumpster and get away with it, that is going to be less

likely in the future. All of the sudden it's going to be a big deal for people to think about the

environmental friendliness of the data center overall, not just energy efficiency.

If we look at the opportunity to save energy, most of the opportunity is in bad system design, not

in the parts. The key to energy efficiency in the data center is right-sizing. The number one

driver of waste in the data center—whether it's servers, power systems, cooling systems—is

over-sizing whatever it is we're looking at. And the amount of over-sizing that occurs within data

centers at all levels is rampant.

People oversize because it's so difficult to scale. Thus, people build a giant thing first and hope

that it's going to fill up. But while it's filling up, it's inefficient. Typically, a data center is expected

to survive for about 12 years and that number is increasing. If expected to last 12 years, it must

be built for a 12- year forward looking goal. That's the logic being used, but how does one know

what they're going to need in 12 years. So what do they do? They know that they've been

growing, so they over-design these things, make them huge, and start out with a small load of IT

equipment and gradually grow it over time. Very inefficient.

Storage managers can deploy storage in more energy-efficient ways. If high performance is not

needed, deploy 7,200 rpm or 10,000 rpm disks rather than 15,000 rpm models, as the slower

speeds use less energy. Similarly, smaller form-factor (2.5-inch) disk drives require only 5 volts

Page 19: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 19

vs. 12 volts for standard 3.5-inch form-factor drives. Small form factors, however, usually have

smaller capacity (see "Energy tradeoffs").

Figure 1-5: Energy tradeoffs

National Snow and Ice Data Center (NSIDC) Project

The Green Data Center project, funded by the National Science Foundation (NSF) under its

Academic Research Infrastructure Program, with additional support from NASA, shows NSIDC's

commitment to reducing its impact on the environment, and that there is significant opportunity

to improve the efficiency of data centers in the U.S.

Coolerado and Modeling an Application of the Maisotsenko Cycle written by Benjamin A.

Weerts has been approved for the Department of Civil, Environmental and Architectural

Engineering University of Colorado Boulder. It included the conclusion of one of the Master's

students at Colorado Univeristy (Ben Weerts) who worked on the project.

The innovative data center redesign slashed energy consumption for data center cooling by

more than 90 percent, demonstrating how other data centers and the technology industry can

save energy and reduce carbon emissions. The heart of the design includes new cooling

technology that uses 90 percent less energy than traditional air conditioning, and an extensive

rooftop solar array that results in a total energy savings of 70 percent. The new evaporative

cooling units not only save energy, but also offer lower cost of maintenance.

Page 20: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 20

This project was a successful effort by a consortium of university staff, a utility provider, and

Federal research organizations to significantly reduce the energy use of an existing data center

through a full retrofit of a traditional air-conditioning system. Cooling energy required to meet the

constant load has been reduced by over 70% for summer months and over 90% for winter

months.

The National Snow and Ice Data Center recently replaced its traditional cooling system with a

new air conditioning system that utilizes an economizer and Coolerado air conditioning units of

the Maisotsenko cooling cycle. A data logging system was installed that measured the data

center's power consumption before and after the cooling system was replaced. This data was

organized and used to prove a 90% cooling energy reduction for the NSIDC. The data logging

system also collected temperatures and humidity of inlet and outlet air of a Coolerado air

conditioner. After using these data to validate a theoretical model developed by researchers at

the National Renewable Energy Laboratory, the model was used to simulate slightly modified

heat and mass exchanger designs of the Coolerado system to improve performance. Sensitivity

analysis was performed and found a few design parameters that are important to the

thermodynamic performance of the Coolerado system, while others were proved insignificant.

Channel heights, sheet size, and ambient pressure have the most significant impact on

performance.

Overall, it was found that the current design performs reasonably well and with minor

modifications could perform optimally, as suggested by the theoretical model. The key

performance indicator used was the coefficient of performance (COP) which is defined in

Equation 18. The COP is a robust performance metric that by definition incorporates cooling

power, product air temperature, product air flow rate, and total air flow rate. If any of these

variables change, the COP will reflect that change. Note that only the product air mass flow rate

can be counted in the cooling power. Working air is very humid, almost saturated, and would be

uncomfortable in an occupied space; therefore, it is exhausted and not used for any useful

cooling. Although it's not a design variable per se, the ambient pressure, or elevation, has the

greatest impact on the performance, with over 11% increase at 2200 feet (from Boulder,

Colorado’s 5800 feet), and over 21% increase at sea level. It should be noted that the low

channel heights’ sensitivity simulation ranks between these two elevation impacts, signifying

that channel height is also a major performance driver with over 14% increase in COP

compared to the base case as both product and working air channel heights are decreased by

0.5mm (0.02"). This value was selected as a maximum change because Coolerado claims that

Page 21: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 21

changing the channel heights more than this amount requires additional time to dial in the

proper flow and speed of the machine used in the manufacturing line. It is also interesting to

note that the Low Wet Wall simulation (reduced working air channel height) resulted in more

than double the change that the Low Dry Wall simulation showed. This implies that it is more

important for the working air channel height to be small and optimally sized for maximum

evaporation rate than it is for the product channel height.

Project results in terms of energy savings, financial savings, or other environmental or

resource use benefits

In the past, cooling the computer room required more than 400,000 kWh of energy/year, enough

to power 50 homes. With the new system in place, the cooling power levels in the summer of

2011 were reduced by 95%. In the winter, the eight patented indirect evaporative cooling

technology (IECT) units operate as highly efficient computer room humidifiers. Using the air

economizers enables the data center to meet or exceed all ASHRAE environmental

specifications. Electricity savings are estimated to be $54,000/year, not including the solar

array. If the owner replaced the existing 30-ton computer room air conditioning (CRAC) unit with

a similar unit, the estimated replacement cost would have been about $160,000. The

maintenance costs for the CRAC unit were about $15,000/year. The new cooling system cost

$250,000, but maintenance costs for the new system will be about $2,000/year. Payback on the

cooling system is well under three years, with costs over that time equaling $367,000 for the

CRAC compared to $256,000 for the new system. In 2011, the project was presented an award

for high-impact research by a local consortium of scientific organizations. The project team was

recognized for its innovative data center redesign that slashed data center energy consumption

for cooling by more than 90%, demonstrating how similar facilities and the technology industry

at large can save energy and reduce carbon emissions. A new web-based monitoring system

allows the public to monitor power use in real time. The monitoring system includes

temperature, humidity, airflow, and electrical power measurements that enable characterization

of the heat gain from the equipment, the heat removed by the cooling system, the energy

consumption of the cooling equipment, and the uniformity of conditions within the data center.

The solar phase of the project under construction and should be complete by April 2012.

Currently under construction, a 50kW solar array, when complete, will make the data center

effectively a zero-carbon facility.

Page 22: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 22

Total reduction in carbon emissions or kW used from the original configuration

In 2009, the total power used by the data center operations was 120kW. Today, the retrofitted

data center uses about 38kW. Once the 50kW solar array is installed, the daytime carbon

footprint and energy usage should drop to zero. The old system had an annual average Power

Utilization Effectiveness (PUE) of 2.03 (PUE is the total data power divided by computer

hardware power used). From August-December 2011, the new system had an average PUE of

1.28. (The PUE would have been lower but for an inefficient UPS system.) Since October 2011,

the monthly PUE has been below 1.20 due to the airside economization of cool fall and winter

temperatures. The PUE will to continue to decrease through the spring, until outdoor

temperatures rise. The new cooling system used less than 2.5 kilowatts of power on average for

the month of October 2011. The average cooling power usage is almost 95% less than that

used in October 2010 (during which the IT load was slightly higher and outdoor conditions were

very similar). The average cooling power during the upcoming winter months of November

2011-February 2012 should be similar because the winters in the region are generally very cool.

Page 23: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 23

Case Study: EMC Durham Cloud Data Center

Overview

In today’s world, the trend is to use new technologies and products that are green to reduce

power consumption.

EMC, one of the IT companies working on this initiative to help enhance storage and IT

products in going green, selected Durham, North Carolina to build its new cloud data center, a

100% Virtual Data Center. Virtualization is a technique that significantly reduces power

consumption and is widely used in all green data centers.

Top View of EMC Durham Data Center

Page 24: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 24

Why EMC decided to build Durham Data Center

EMC is the latest in a series of leading technology companies that have chosen North Carolina

as major data center location, joining companies such as Google, Apple, and Facebook.

This new data center will replace the existing data center in Westborough, Massachusetts. EMC

migrated more than 6PB from the Westborough location to the new virtualized data center in

Durham. Though a formidable challenge, all application migrations were completed in less than

two years. Another huge challenge regarding Data Center Kick-Off, Site Selection, Construction,

and Application Migration was to finish everything in less than four years.

A major reason for building the Durham Cloud Data Center was the high cost of power incurred

in the Westborough Data Center.

Expense comparison between Westborough and Durham

Westborough Durham

Owner Rented EMC is the Owner

Power $.12/KWH $.05/KWH

Space 15,0002 Ft 20,0002 Ft

Physical or Virtual Legacy physical

32% Virtual

Private Cloud

100% Cloud

Providing a 46% power reduction and accommodating an increase in IT resource demand by

97%, the Durham Cloud Data Center represents a perfect example of high energy efficiency to

deliver IT as a Service.

This data center is designed to meet all requirements for enhancing power consumption by

using multiple sustainable design innovation ideas, such as:

Achieving high rate of energy reduction over the existing facilities

Producing exceedingly energy-efficient savings in all operations

Using of outside air (free cooling)

Page 25: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 25

o A cold-aisle containment system to manage airflow within the data center, and

flywheel UPS systems to save space and reduce reliance on batteries

Reducing carbon emissions for both the operation and development of the facility.

Reducing or eliminating operational disruption

Design and Construction

Moving from a physical to a highly-virtualized IT infrastructure is the key for cloud computing.

The Durham data center supports the requirements for cloud with architecture that leverages

the latest information infrastructure technologies.

Built with leading technology solutions from EMC, VMware, and VCE, the 100 percent highly

virtualized Durham data center is the foundation for EMC IT’s cloud vision and transition to

Infrastructure as a Service (IAAS). It delivers all requirements—flexibility, agility, and

scalability—to meet today’s needs and those of the future.

EMC concentrated on enhancing and developing a data center with sustainability as a primary

design criterion. Energy conservation was a primary focus as were efficiency ideas such as a

rooftop water collection system, use of outside air (free air-cooling) for approximately 57 percent

of the year, a col-aisle containment system to manage airflow within the data center, and

Flywheel Uninterrupted Power Supply system technology used to eliminate needing the storage

battery in the UPS systems.

EMC kept the exterior of the 45,000 square foot building and is using a three-phased modular,

“box within a box” approach to complete the facility 150,000 square feet at a time.

Cooling and power are installed independently with each module; Also, cooling and air-handling

are built offsite to very tight tolerance and then placed in the premises.

Cold aisle containment is a new way used in Durham to increase cooling control and efficiency.

Also, although the Durham data center will have many more servers and storage than before,

EMC IT managed to save 280 watts per server with virtualization and has reduced power

consumption per terabyte of storage by 82 percent.

Page 26: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 26

EMC has chosen VCE vBlock® which integrates VMware software, EMC products, and Cisco

UCS blade server and network technologies for Unified VM provisioning and simplified workload

management.

Durham is the first EMC data center to host all application and platforms on Top Layer “VMware

Vphere” as its virtual data center. EMC IT will be able to modify, move, or relocate workloads

easily and transparently anywhere within it for maximum performance, utilization, and efficiency.

Features

Latest EMC and VMware tools will be used to manage the virtual infrastructure of the

data center. An energy-efficient HVAC cooling system combines water cooling and air

cooling.

Automatic lighting control systems are implemented enhance energy efficiency.

There are two separate underground pathways to deliver voice and data services; each

terminates at one of two main communication rooms for further redundancy.

Durham Data Center Architecture

It is fully virtualized Data center on VMware vSphere, built using the VCE VBlock converged

Infrastructure. This Virtual Infrastructure provides the cloud foundation that will enable

workloads to be located and easily moved transparently within the data center for maximum

efficiency, performance and utilization.

Page 27: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 27

The data center includes.

Network: 4 Redundant 10 GB/s WAN links, Cisco Nexus 7000 core network

Compute: Cisco UCS x86 servers, 100% virtualized

Storage: EMC Symmetrix® VMAX®, EMC VNX® (VBlock)

Backup: NetWorker®, Data Domain® and Avamar®

As seen in the components listed above, EMC uses many backup solutions as backups are

created locally in the data center, then replicated to the remote data center to provide high data

protection.

Migration Process

The Durham migration needed to be a showcase for EMC’s private cloud vision. It was a big

challenge to migrate all of the data without doing a physical move.

Traditionally, data centers are moved the same way you move to a new house. You have to

carefully pack and load everything into a lorry (or truck), drive to your new location, and unpack

and set up everything again in the new location. This operation is a major disruption. Today,

since business runs 24/7, moving the production data center should be non-disruptive.

To minimize risk and disruption to the business, EMC decided to migrate and transform a new

private cloud, built on VCE vBlock and virtual machines on VMware vSphere. Hardware was not

relocated to the new location as part of the data center migration process.

All data and applications were moved across four redundant 10 Gb/s WAN links. Many

application physical server architectures were rebuilt to new virtualized cloud architectures.

Migrating applications and data in a virtual environment minimizes downtime. The migration

process is shown in the following diagram.

Page 28: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 28

Awards

EMC’s Durham facility is the latest Global Center of Excellence (COE). Others are located in

India, China, Egypt, Israel, Ireland, and Russia. COE performs services for EMC business units

including Technical Support, Customer Service, Research and Development, Engineering, and

IT.

In March 2013; EMC COE in Durham was awarded LEED (Leadership in Energy and

Environmental Design) GOLD. Highlights of the certificate included recognition of a 34% overall

energy saving and reduced carbon footprint of nearly 100,000,000 pounds of CO2.

The Certificate also included:

Utilize “Free Cooling” 57 percent of the year

Reduced potable water use of 78 percent

Page 29: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 29

Case Study: “Iceland”

Iceland wants to be your haven

Imagine having your backup data center powered by hydroelectric and geothermal energy--

water and hot springs. Sounds like something Jules Verne would have written about if he had

heard about data centers, right?

It would be fitting for Verne to then talk about the Invest in Iceland Agency, because Iceland is

where his Journey to the Center of the Earth novel began. The agency, which is part of the

Icelandic government, will soon start trying to lure companies from Europe and the U.S. to build

their backup data centers in Iceland. The attractions are stable temperatures, a stable economy,

and yes, cheap power, thanks to the country's hot springs and waterfalls.

"The price can vary highly depending on what kind of quantity and stability in electricity you

need," said Thortur Hilmarsson, general manager of the agency. "As an example, a heavy

industry with 10-to-15 megawatts can have prices of 3.5 cents per kilowatt hour. If you're a

smaller consumer, then you're looking at 6, 7, 8 cents per kilowatt hour."

About 72% of Iceland's energy consumption comes from hydroelectric and geothermal energy.

The only fossil fuels used are for cars and fishing vessels. Temperatures are cold but stable,

between 32 degrees and 55 degrees Fahrenheit throughout the year. Plus, the corporate tax

rate in Iceland is about 18%, less than half of the 39% in the U.S., according to figures from the

Congressional Budget Office.

Hilmarsson said the agency is working on a comprehensive study about just this topic. The

study will look at latency issues from Iceland to Europe and Iceland to the U.S. That said, it

would still have to convince data centers that it is worth the extra effort to locate there.

Page 30: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 30

Appendix

Robert McFarlane is a principal in charge of data center design for the international consulting

firm Shen Milsom and Wilke LLC. McFarlane has spent more than 35 years in communications

consulting, has experience in every segment of the data center industry and was a pioneer in

developing the field of building cable design. McFarlane also teaches the data center facilities

course in the Marist College Institute for Data Center Professional program, is a data center

power and cooling expert, is widely published, speaks at many industry seminars and is a

corresponding member of ASHRAE TC9.9, which publishes a wide range of industry guidelines

Clive Longbottom is the co-founder and service director at Quocirca and has been an ITC

industry analyst for more than 15 years. Trained as a chemical engineer, he worked on anti-

cancer drugs, car catalysts and fuel cells before moving in to IT. He has worked on many office

automation projects, as well as Control of Substances Hazardous to Health, document

management and knowledge management projects.

Snow and Ice Datacenter http://nsidc.org/about/green-data-center/

Snow and Ice data center, Weerts, B., D. Gallaher, R. Weaver, O. Van Geet, 2012: Green Data

Center: Energy Reduction Strategies: Airside Economization and Unique Indirect Evaporative

Cooling. IEEE Green Technologies Conference Proceedings, Tulsa

Uptime Institute http://uptimeinstitute.com/

Uptime Institute, an independent division of The 451 Group, provides education, publications,

consulting, certifications, conferences and seminars, independent research, and thought

leadership for the enterprise data center industry and for data center professionals.

Data center selection by John Rath www.Datacenterlinks.com

U.S. Environmental Protection Agency http://www.epa.gov/greenpower/index.htm

Site Selection Online http://www.siteselection.com/issues/2002/mar/p118/

Glumac http://www.glumac.com

Page 31: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 31

Leveraging Renewable Energy in Data Centers

Present and Future

Keynote Summary

Ricardo Bianchini

Department of Computer Science

Rutgers University

[email protected]

Air Management and capitalize on free cooling. Best Practices for Data Centers: Lessons Learned from Benchmarking 22 Data Centers

Steve Greenberg, Evan Mills, and Bill Tschudi, Lawrence Berkeley National Laboratory

Peter Rumsey, Rumsey Engineers

Bruce Myatt, EYP Mission Critical Facilities

Rocky Mountain Institute http://www.rmi.org/sitepages/pid17.php (Copyright ©1990-2012

Rocky Mountain Institute. ® All rights reserved.

Computer World http://www.computerweekly.com/news/2240080415/Solving-storage-power-

and-cooling-concerns

Iceland example http://searchdatacenter.techtarget.com/news/1246999/Iceland-wants-your-

backup-data-centers

http://smma.com/project/mission-critical/emc-durham-cloud-data-center

http://www.datacenterknowledge.com/archives/2011/09/15/emc-opens-new-cloud-data-center-

in-nc/

EMC Durham Data center - Energy efficient design and construction

[email protected]

EMC Durham Cloud DC, Powering EMC IT’s cloud vision ref.

https://www.emc.com/about/news/press/2013/20130314-01.htm

Page 32: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 32

Biographies

Mohamed Sohail

Implementation Delivery Specialist

Mohamed has over 9 years of IT experience in operations, implementation, and support; 4 of

them with EMC. Mohamed previously worked as a Technical Support Engineer at Oracle Egypt

and was a Technical Trainer at Microsoft. Mohamed holds a Bsc. in Computer Science from

Rome University Sapienza Italy and a B.A in Italian from Ain Shams University Egypt.

Mohamed holds EMC Proven Professional Backup Recovery certification.

Denis Canty

Principal Test Architect

Denis is a Principal Test Architect in the Data Domain BRS division of Global External

Manufacturing (GEM). Having been in the IT industry for 9 years, Denis previously worked for

Alps Electric, a Japanese automotive electronics company. Denis earned a degree in Electronic

Engineering from Cork Institute of Technology (CIT), a Masters in Computer Science from

Dublin City University (DCU), and a Masters in Microelectronic Design from University College

Cork (UCC).

Denis holds EMC Proven Professional Information Storage and Management certification.

Omar Aboulfotoh

Technical Support Engineer

Omar is a Technical Support Engineer working in the Unified Storage Division, Global Technical

Support GTS, EMC Egypt COE. He has been in the IT industry for 3 years.

He holds a degree in Electronics and Communications Engineering and is currently studying in

a Master program at Faculty of Engineering, Cairo University.

Omar holds EMC Proven Professional Specialist certification in VNX and SAN and is also VCP

and vCloud Certified.

Page 33: A Journey to Power Intelligent IT - Big Data Employed

2014 EMC Proven Professional Knowledge Sharing 33

EMC believes the information in this publication is accurate as of its publication date. The

information is subject to change without notice.

THE INFORMATION IN THIS PUBLICATION IS PROVIDED “AS IS.” EMC CORPORATION

MAKES NO RESPRESENTATIONS OR WARRANTIES OF ANY KIND WITH RESPECT TO

THE INFORMATION IN THIS PUBLICATION, AND SPECIFICALLY DISCLAIMS IMPLIED

WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE.

Use, copying, and distribution of any EMC software described in this publication requires an

applicable software license.