Growth and Cost Challenges (ppt, 4024KB)

11
Growth and cost challenges Gro Kielland , Managing Director of BP Norge

Transcript of  Growth and Cost Challenges (ppt, 4024KB)

Page 1: Â Growth and Cost Challenges (ppt, 4024KB)

Growth and cost challenges

Gro Kielland , Managing Director of BP Norge

Page 2: Â Growth and Cost Challenges (ppt, 4024KB)

2

Topics to be covered

• BP- from a middle sized to Supermajor

• North Sea Cost Challenge

• BP Norway significant growth

Page 3: Â Growth and Cost Challenges (ppt, 4024KB)

3

Who we are

BP is an oil, gas, refining & marketing and renewables company

We employ 96 200 people

We have operations on 6 continents and in over 100 countries

...one for the largest E&P companies in the world

...over 28 500 service stations worldwide

...serving 13 million customers every day

...one of the largest producer of solar panels

Page 4: Â Growth and Cost Challenges (ppt, 4024KB)

4

Reserves replacement

Reserves replacement for subsidiaries + associates, excludes the effects of

acquisitions & divestments, SEC basis

5 year moving average

0

20

40

60

80

100

120

140

160

85 86 87 88 89 90 91 92 9394 95 96 97 98 99 00 0102 03 04 05 06

%

Page 5: Â Growth and Cost Challenges (ppt, 4024KB)

5

McKinsey 2006 North Sea Benchmarking

0

20

40

60

80

100

120

140

160

180

200

1990 1995 2000 2005 2010 2015

Opex per barrel for producing fieldsIndexed to 100 in 2006

Historical Forecast

Netherlands

UK

Norway

Netherlands

UK

Norway

3,976

2004

4,389

2005

+10%

1,838

2004

1,717

2005

-7%

2.16

2004

2.56

2005

+18%

Lifting Cost*$ Million

ProductionMillion boe

Unit Lifting cost$/boe

*Lifting cost includes partner billed OPEX, excluding tariff and transport costs (Consistent group of 35 assets in Denmark, UK and Norway from the McKinsey Benchmarking exercise)Source: McKinsey analysis; McKinsey 2006 North Sea Benchmarking; Wood MacKenzie

Page 6: Â Growth and Cost Challenges (ppt, 4024KB)

6

2007 BP’s North Sea Cost Map

c. $5bn of gross external spend

Seismic

Drilling & Wells

Operations

Business Services

Major Project

s

Subsea

Logistics

15%

11%

21%

5%

26%

21%

Page 7: Â Growth and Cost Challenges (ppt, 4024KB)

7

• Partner in 13 licenses

• Operator at 10 of these

• Operator of five producing fields; Ula,Tambar, Valhall,Hod and Skarv

• Partner in the Draugen field

• New field center at Valhall

• Skarv Idun field development

• Connecting the Blane field to Ula

= Core Areas

Our activities offshore Norway

Page 8: Â Growth and Cost Challenges (ppt, 4024KB)

8

BP Norway production profile

Source: 2007-2009 : NB08, 2010-2017 : RNB2007

-

10

20

30

40

50

60

70

80

90

100

2 007 2 008 2 009 2 010 2 011 2 012 2 013 2 014 2 015 2 016 2 017

mbo

ed n

et

Total BP Net

Page 9: Â Growth and Cost Challenges (ppt, 4024KB)

9

Key facts Skarv Idun development

Production start Accommodation Oil production Gas production Topsides Hull Turret/mooring system Wells Sub sea templates

3kv. 2011100 single bed cabins85 000 b/d15 mill sm3/d16 000 tonne40 000 tonne 4 000 tonne165

• 16,8 mill Sm3 oil & condensate

• 48,3 billion Sm3 gas

• Investments ca .31 billion NOK

• Phased development with early oil production

• 80km long 26" spur line to Åsgard Transport System

Page 10: Â Growth and Cost Challenges (ppt, 4024KB)

10

Overview Valhall Field Development

Flank South

Flank NorthEkofisk

Lista

Valhall Complex

New PH

Pipeline from HOD

HVDC Cable

Oil Pipeline to Ekofisk

Page 11: Â Growth and Cost Challenges (ppt, 4024KB)

11

BP in Norway

•Long term perspective, at least to yr 2050

•Progressive user of new technology

•$ 6-7 billion gross to be invested the next 4 yrs