7 Project Budgeting

download 7 Project Budgeting

of 19

Transcript of 7 Project Budgeting

  • 7/31/2019 7 Project Budgeting

    1/19

    EMM - MSRSAS 1

    Session 6

    7.0 ESTIMATING & BUDGETING

    Session Speaker

    V G S Mani

  • 7/31/2019 7 Project Budgeting

    2/19

    EMM - MSRSAS 2

    Session Objectives & Topics

    At the end of this session the delegate would have

    understood

    Preparing Cost estimates for a project; costbreakdown structure

    S curve for monitoring projects

    Assessing progress of projects (cost & time) through

    earned value concepts Analysis of cost variances and ratios

  • 7/31/2019 7 Project Budgeting

    3/19

    EMM - MSRSAS 3

    Core Processes-Planning

    Scope

    planning

    Scope

    definition

    Activity

    definition

    Activity

    sequencing

    Resource

    planning

    Cost

    estimating

    Scheduledeveloping

    Cost

    Budgeting

    Project plan

    development

    Activity

    Duration

    estimating

  • 7/31/2019 7 Project Budgeting

    4/19

    EMM - MSRSAS 4

    Cost Estimating & Pricing

    Cost Estimating

    Developing an approximation of the costs of the resources

    needed to complete project activities

    How much it will cost the organisation to provide the productor services

    Pricing(a business decision)

    How much the organisation will charge for the product or

    services

    The estimate is only one factor in the decision

  • 7/31/2019 7 Project Budgeting

    5/19

    EMM - MSRSAS 5

    Profit Equation

    Cost + Profit = Revenue ----- Old

    Gross profit = RevenueCosts ---- Now

    Revenue = Sales volume x Selling price

    Cost = Variable costs + Fixed costs

    Variable cost = Sales volume x unit Variablecost

  • 7/31/2019 7 Project Budgeting

    6/19

    EMM - MSRSAS 6

    Cost Vs Price

    System driven Market driven

    COST PROFIT PRICE

  • 7/31/2019 7 Project Budgeting

    7/19

    EMM - MSRSAS 7

    Cost Breakdown Structure

    Labour: Cost of people employed by the parent

    company

    Materials: Incorporated or consumed Plant & equipment: Used but not consumed

    Sub-contract: As above but provided by outside

    contractors

    Management: Directly attributed to project management

  • 7/31/2019 7 Project Budgeting

    8/19

    EMM - MSRSAS 8

    Cost Breakdown Structure

    Overheads & admin: Shared costs & absorption

    Fees & taxation: Insurance, licenses, finance,,

    taxation etc. Inflation: Not always included except in fixed

    price tenders & where differential between cost &

    revenue inflation expected

    Contingency: May be added as blanket figure or

    calculated according to risk

  • 7/31/2019 7 Project Budgeting

    9/19

    EMM - MSRSAS 9

    Versions Of Estimates

    Three versions of estimates:

    Base lineamount communicated to project team

    Most likelyamount project manager expects to spend Budgetamount owner is willing to spend

    Budget - typically 1020% higher than base line

    Most likelyhalf way between

  • 7/31/2019 7 Project Budgeting

    10/19

    EMM - MSRSAS 10

    Input to Cost Estimating

    Work Breakdown Structure

    Organise cost estimates

    Ensure all work has been estimated

    Resource requirements(type & qty.) Resource rates for each resource

    Staff cost per hour, equipment rates per hour etc.

    Material costs, overhead recovery rate

    Activity duration estimates

    Historical information

    Cost breakdown structure

  • 7/31/2019 7 Project Budgeting

    11/19

    EMM - MSRSAS 11

    Types of Estimate

    Proposal - appraise viability to start feasibility study

    Accuracy: +/- 30 to 50%, Effort:0.02 to 0.10 % of project cost

    Budgetappraise viability to start systems design

    Accuracy: +/- 20 to 35%, Effort:0.10 to 0.30 % of project cost

    Sanction - appraise viability to approve project, obtain

    funding, allocate resources

    Accuracy: +/- 10 to 25%, Effort:0.40 to 0.80 % of project cost

  • 7/31/2019 7 Project Budgeting

    12/19

    EMM - MSRSAS 12

    Types of Estimate

    Controlmeasure progress, assign resources

    Accuracy: +/- 5 to 15%, Effort:1.0 to 3.0 % of project

    cost Tenderprepare tender

    Accuracy: +/- 2 to 5%, Effort:5.0 to 10.0 % of project

    cost

  • 7/31/2019 7 Project Budgeting

    13/19

    EMM - MSRSAS 13

    Source of Estimating Data

    Suppliers quotations

    Trade literature, technical literature, textbooks

    Company historical data, standard costs

    Computer systems

    Black books

    Government figures & statistics

  • 7/31/2019 7 Project Budgeting

    14/19

    EMM - MSRSAS 14

    Cost Estimating Methods

    Analogous estimating

    Using actual costs of similar previous activities

    A form of Expert Judgment using historical data Parametric modeling

    Using mathematical models to predict costs

    Computer spreadsheets, specialist packages

    Bottom-up estimating

    Using cost of individual elements to build up total

    estimate(industry data base)

  • 7/31/2019 7 Project Budgeting

    15/19

  • 7/31/2019 7 Project Budgeting

    16/19

    EMM - MSRSAS 16

    Types of Project Budget

    Short projects may occur within a single time

    period. The period is often one month. Budget

    values are for the project duration Small projects may have only a single work

    package. Budget values for whole project.

    Most projects have several work packages and

    extend over several budget periods. Budget values

    are produced for each package for each period

  • 7/31/2019 7 Project Budgeting

    17/19

    EMM - MSRSAS 17

    Expenditure Profiles

    Determines when expenditure takes place with in an

    activity

    Uniform

    Constant rate of expenditure Front-end loaded

    All or most of cost at start of activity

    Rear-end loaded

    All or most of cost at finish activity Variable

    Regular(triangular or other distribution)

    Irregular or intermediate

  • 7/31/2019 7 Project Budgeting

    18/19

    EMM - MSRSAS 18

    Cost Apportioning

    Distribution

    1 2 3 4 5 6

    25% 50% 25%

    0

    Uniform

    Uniform

    Uniform

    Variable

    Rear-end

    loaded

    Periods

    100%

    100%

    50% 50%

    0% 0% 100%

  • 7/31/2019 7 Project Budgeting

    19/19

    EMM - MSRSAS 19

    Cumulative Cost(S) Curve

    Time

    RsPeriod cost

    Cumulative cost

    Budgeting & control is carried out an a cumulative cost basis