7 Project Budgeting
-
Upload
adityajain1188 -
Category
Documents
-
view
223 -
download
0
Transcript of 7 Project Budgeting
-
7/31/2019 7 Project Budgeting
1/19
EMM - MSRSAS 1
Session 6
7.0 ESTIMATING & BUDGETING
Session Speaker
V G S Mani
-
7/31/2019 7 Project Budgeting
2/19
EMM - MSRSAS 2
Session Objectives & Topics
At the end of this session the delegate would have
understood
Preparing Cost estimates for a project; costbreakdown structure
S curve for monitoring projects
Assessing progress of projects (cost & time) through
earned value concepts Analysis of cost variances and ratios
-
7/31/2019 7 Project Budgeting
3/19
EMM - MSRSAS 3
Core Processes-Planning
Scope
planning
Scope
definition
Activity
definition
Activity
sequencing
Resource
planning
Cost
estimating
Scheduledeveloping
Cost
Budgeting
Project plan
development
Activity
Duration
estimating
-
7/31/2019 7 Project Budgeting
4/19
EMM - MSRSAS 4
Cost Estimating & Pricing
Cost Estimating
Developing an approximation of the costs of the resources
needed to complete project activities
How much it will cost the organisation to provide the productor services
Pricing(a business decision)
How much the organisation will charge for the product or
services
The estimate is only one factor in the decision
-
7/31/2019 7 Project Budgeting
5/19
EMM - MSRSAS 5
Profit Equation
Cost + Profit = Revenue ----- Old
Gross profit = RevenueCosts ---- Now
Revenue = Sales volume x Selling price
Cost = Variable costs + Fixed costs
Variable cost = Sales volume x unit Variablecost
-
7/31/2019 7 Project Budgeting
6/19
EMM - MSRSAS 6
Cost Vs Price
System driven Market driven
COST PROFIT PRICE
-
7/31/2019 7 Project Budgeting
7/19
EMM - MSRSAS 7
Cost Breakdown Structure
Labour: Cost of people employed by the parent
company
Materials: Incorporated or consumed Plant & equipment: Used but not consumed
Sub-contract: As above but provided by outside
contractors
Management: Directly attributed to project management
-
7/31/2019 7 Project Budgeting
8/19
EMM - MSRSAS 8
Cost Breakdown Structure
Overheads & admin: Shared costs & absorption
Fees & taxation: Insurance, licenses, finance,,
taxation etc. Inflation: Not always included except in fixed
price tenders & where differential between cost &
revenue inflation expected
Contingency: May be added as blanket figure or
calculated according to risk
-
7/31/2019 7 Project Budgeting
9/19
EMM - MSRSAS 9
Versions Of Estimates
Three versions of estimates:
Base lineamount communicated to project team
Most likelyamount project manager expects to spend Budgetamount owner is willing to spend
Budget - typically 1020% higher than base line
Most likelyhalf way between
-
7/31/2019 7 Project Budgeting
10/19
EMM - MSRSAS 10
Input to Cost Estimating
Work Breakdown Structure
Organise cost estimates
Ensure all work has been estimated
Resource requirements(type & qty.) Resource rates for each resource
Staff cost per hour, equipment rates per hour etc.
Material costs, overhead recovery rate
Activity duration estimates
Historical information
Cost breakdown structure
-
7/31/2019 7 Project Budgeting
11/19
EMM - MSRSAS 11
Types of Estimate
Proposal - appraise viability to start feasibility study
Accuracy: +/- 30 to 50%, Effort:0.02 to 0.10 % of project cost
Budgetappraise viability to start systems design
Accuracy: +/- 20 to 35%, Effort:0.10 to 0.30 % of project cost
Sanction - appraise viability to approve project, obtain
funding, allocate resources
Accuracy: +/- 10 to 25%, Effort:0.40 to 0.80 % of project cost
-
7/31/2019 7 Project Budgeting
12/19
EMM - MSRSAS 12
Types of Estimate
Controlmeasure progress, assign resources
Accuracy: +/- 5 to 15%, Effort:1.0 to 3.0 % of project
cost Tenderprepare tender
Accuracy: +/- 2 to 5%, Effort:5.0 to 10.0 % of project
cost
-
7/31/2019 7 Project Budgeting
13/19
EMM - MSRSAS 13
Source of Estimating Data
Suppliers quotations
Trade literature, technical literature, textbooks
Company historical data, standard costs
Computer systems
Black books
Government figures & statistics
-
7/31/2019 7 Project Budgeting
14/19
EMM - MSRSAS 14
Cost Estimating Methods
Analogous estimating
Using actual costs of similar previous activities
A form of Expert Judgment using historical data Parametric modeling
Using mathematical models to predict costs
Computer spreadsheets, specialist packages
Bottom-up estimating
Using cost of individual elements to build up total
estimate(industry data base)
-
7/31/2019 7 Project Budgeting
15/19
-
7/31/2019 7 Project Budgeting
16/19
EMM - MSRSAS 16
Types of Project Budget
Short projects may occur within a single time
period. The period is often one month. Budget
values are for the project duration Small projects may have only a single work
package. Budget values for whole project.
Most projects have several work packages and
extend over several budget periods. Budget values
are produced for each package for each period
-
7/31/2019 7 Project Budgeting
17/19
EMM - MSRSAS 17
Expenditure Profiles
Determines when expenditure takes place with in an
activity
Uniform
Constant rate of expenditure Front-end loaded
All or most of cost at start of activity
Rear-end loaded
All or most of cost at finish activity Variable
Regular(triangular or other distribution)
Irregular or intermediate
-
7/31/2019 7 Project Budgeting
18/19
EMM - MSRSAS 18
Cost Apportioning
Distribution
1 2 3 4 5 6
25% 50% 25%
0
Uniform
Uniform
Uniform
Variable
Rear-end
loaded
Periods
100%
100%
50% 50%
0% 0% 100%
-
7/31/2019 7 Project Budgeting
19/19
EMM - MSRSAS 19
Cumulative Cost(S) Curve
Time
RsPeriod cost
Cumulative cost
Budgeting & control is carried out an a cumulative cost basis