Results from HSS Assessments in 20 Townships (Infrastructure) Dr. Thida Kyu Deputy Director(Planning) DOH

Transcript of 5.total infrastructure (dr thida kyu)

Page 1: 5.total infrastructure (dr thida kyu)

Results from HSS Assessments in 20 Townships

(Infrastructure)

Dr. Thida KyuDeputy Director(Planning)

DOH

Page 2: 5.total infrastructure (dr thida kyu)

Conditions of RHCs in 20 TownshipsSr No

Name of Townships

No; of RHCs

RHC Building Need Renovation

Need NewConstruction

Labour room

+

Electri-city(EPC)Good Bad

1 Lewe 8 4 4 2 1 2 42 Yedashe 8 7 1 0 1 5 33 Shwe Gu 5 2 3 3 0 3 14 Bamaw 6 2 3 3 1 3 05 Pyinmana 5 4 0 0 1 0 1

6Nyaung Shwe 7 4 3 3 0 3 0

7Tharyarwaddy 6 4 2 2 0 1 2

8 Tha Htone 5 4 1 1 0 3 09 Mudon 6 5 1 1 3 3

10 Hsipaw 5 3 2 2 0 5 0Total 61 39 20 16 5 28 14

Page 3: 5.total infrastructure (dr thida kyu)

Conditions of RHCs in 20 TownshipsSr No

Name of Townships

No; of RHCs

RHC Building Need Renovation

Need NewConstruction

Labour room

+

Electri-city(EPC)

Good Bad

1 Myeik 5 4 1 1 0 5 2

2 Kyaing Tone 5 4 1 1 0 3 2

3 Kaw Hmu 5 2 2 2 0 5 3

4 Nga Putaw 5 2 2 2 0 4 0

5 Hakha 4 3 1 0 1 1 0

6 Hlaing Bwe 8 5 3 3 0 7 0

7 Hti Lin 5 4 1 1 0 0 0

8 Demawsoe 7 1 6 5 1 0 1

9 MaungDaw 9 7 2 2 0 1 1

10 Ye Oo 6 4 2 0 0 6 0

Total 59 36 21 17 2 32 9

Page 4: 5.total infrastructure (dr thida kyu)

RHCs which need renovation /new construction in HSS 20 TS

Page 5: 5.total infrastructure (dr thida kyu)

Total No: of RHCs which need renovation / new construction in HSS 20 TS

Total No; of RHCs- 120 in 20TSNeed Renovation -33Need New Construction -7

Page 6: 5.total infrastructure (dr thida kyu)

Sub-centres with No Building in HSS 20 TS

Township No SC building

Bamaw 1

Shwegu 1

Demawsoe 13

Hlaingbwe 10

Hakha 0

Thaton 6

Mudon 8

Maungdaw 8

Nyaung-Shwe 0

Kengtong 10

Township No SC building

Hsipaw 1

Ye-U 6

Pyinmana 4

Lewe 8

Htilin 1

Yedeshay 18

Thayawady 3

Kawhmu 2

Ngaputaw 6

Myeik 11

Total 117

Page 7: 5.total infrastructure (dr thida kyu)

Appointed MWs who have no SC building in 20 TS

TownshipMW

AssignedNo SC

building

Bamaw 27 1

Shwegu 23 1

Demawsoe 41 13

Hlaingbwe 47 10

Hakha 24 0

Thaton 43 6

Mudon 35 8Maungdaw 32 8Nyaung-Shwe 35 0

Kengtong 34 10

TownshipMW

AssignedNo SC building

Hsipaw 19 1

Ye-U 32 6

Pyinmana 17 4

Lewe 38 8

Htilin 28 1

Yedeshay 31 18

Thayawady 33 3

Kawhmu 24 2

Ngaputaw 29 6

Myeik 32 11

Total 624 117

Page 8: 5.total infrastructure (dr thida kyu)

Name of Townships No; of RHCs Labour Room + Electricity(EPC) Myeik 5 5 2Kyaing Tone 5 3 2Kaw Hmu 5 5 3

Nga Putaw 5 4 0

Hakha 4 1 0Hlaing Bwe 8 7 0

Hti Lin 5 0 0

Demawsoe 7 0 1

MaungDaw 9 1 1

Ye Oo 6 6 0

Lewe 8 2 4

Yedashe 8 5 3

Shwe Gu 5 3 1

Bamaw 6 3 0

Pyinmana 5 0 1

Nyaung Shwe 7 3 0

Tharyarwaddy 6 1 2

Tha Htone 5 3 0

Mudon 6 3 3

Hsipaw 5 5 0

Total 120 60 23

Labour Room attached RHCs & Electricity from EPC in HSS 20 TS

Page 9: 5.total infrastructure (dr thida kyu)

RHCs with attached Labour Room and Electricity from EPC

Page 10: 5.total infrastructure (dr thida kyu)
Page 11: 5.total infrastructure (dr thida kyu)
Page 12: 5.total infrastructure (dr thida kyu)

Nyaung Shwe

Page 13: 5.total infrastructure (dr thida kyu)

MUDON

Kamaroat S/C

In Mudon township -Totally 6 RHCs & 24 sub centers - 3 RHCs have labour room attached- 8 sub centers do not have sub-centre building, even no demarkated land space for S/C.

Page 14: 5.total infrastructure (dr thida kyu)

Kawt Kha Pon RHC attached at Village Authority’s building

Kawtkhapon RHC in Mudon has no building and it has to be opened at the local authority’s office in the morning.

Page 15: 5.total infrastructure (dr thida kyu)

PyinmanaAmong 5 RHCs in Pyinmana township, 1 RHC (Boe-ma) and 4 sub centres have no building, 1 sub centre is being constructed.

Temporary building for We’ Gyi S/C

Midwives who do not have sub centre building, have to stay in village administration offices or stay attached to village head’shome.

Page 16: 5.total infrastructure (dr thida kyu)

Shwegu

2 out of 5 RHC have good building. 3 RHCs need renovation. Only 3 RHCs have labour room ; Need to build one sub center

2 out of 5 RHC have good building. 3 RHCs need renovation. Only 3 RHCs have labour room ; Need to build one sub center

Page 17: 5.total infrastructure (dr thida kyu)

Yaydarshae

Aye Gye S/C does not have sub centre building and has to open at local authority officeOne local person from the village willing to give his own land to construct S/C

Kyun Pin Su S/C

Hle Pwe lay RHC has no RHC Building 18 sub centres have no sub-center buildings.

Page 18: 5.total infrastructure (dr thida kyu)

Bamaw township

Naung Lite SC under Ma au pin RHC

Naung Lite SC under Ma au pin RHC

3RHCs have labour room attached.

Page 19: 5.total infrastructure (dr thida kyu)

Thaton

2 sub centers Kyarpun RHC (Duyin Seik and Gaw ), 1 sub cencre (Thein Seik -2) under the Thein Seik RHC, 2 sub centres (Kadaik Lay and Tawgyi ) under Kadaikgyi RHC and Naungbo subcenter under Painetaw RHC have no building.

Page 20: 5.total infrastructure (dr thida kyu)

Hsipaw

One out of 14 sub-centers and 3 special region clinics ( Pan Hone, Nar Nyu and Ohn mu) had building that need major renovation and need to construct1 SC . 5 RHCs have labor rooms.

Page 21: 5.total infrastructure (dr thida kyu)

Conclusion • Infrastructures are needed for motivation of midwives

to work in the community especially in HTR areas

• Infrastructures for working and living have to be fulfilled

• Prioritization have to be done for those in real need than those that can wait for the construction of sub center

• Similarly for renovation, HSS program could take care of a few: but in the CTHP, gaps for refurbishment were mentioned for donors and other interesting parties concern and contribution.