57774801 RBI Methodology

download 57774801 RBI Methodology

of 2

Transcript of 57774801 RBI Methodology

  • 7/30/2019 57774801 RBI Methodology

    1/2

    RISK BASED INSPECTIONMETHODOLOGY

    INTRODUCTION

    Risk Based Inspection (RBI) provides for the first time the

    requisite information to prioritise inspection activities on

    the basis of a risk benefit approach.

    RBI examines each of the equipment items in the process

    by calculating the risk of operation as the product of theLikelihood of Failure (LoF) and the Consequence of

    Failure (CoF) if such a failure should occur. High risk

    items can receive more attention, while low risk items can

    receive a lesser, more appropriate level of inspection.

    DNV AND RBI

    DNV facilitated and supported the development of the

    Risk Based Inspection methodology for refineries and

    petrochemical plants for the American Petroleum Institute

    (API), producing the Base Resource Document API 581and software. Similarly, DNV has become involved in a

    Joint Industry Project (JIP) to develop an industryaccepted offshore RBI methodology

    DNV has applied

    the RBI

    methodology on

    numerous chemical

    and petrochemical

    facilities worldwide,

    both onshore and

    offshore.

    INTRODUCTION TO RBIMETHODOLOGY

    The RBI process is an integrated method of analysis to:

    Identify the driving parameters for both likelihoodand consequence of failure (leaks or loss of

    containment).

    Risk rank all pieces of equipment included in thestudy using safety or business interruption as the risk

    measure.

    Provide an inspection plan guideline and detailedequipment inspection plans.

    The basis of all RBI studies is:

    Identification of the system to be analysed. Identification of the type of hazard involved. Separate calculation of the failure consequence and

    likelihood.

    Calculation of the risk.The Key Concepts of RBI

    RISK = Likelihood of Failure XConsequence of

    FailureGeneric

    Failure

    Frequency

    Item Technical

    Module

    SubFactor

    X

    Age

    Damage

    type/rate

    Inspectioneffectiveness

    Damage area

    Item repair

    Other repairs

    Injury

    Business interruption

    Environment clean up

    SYSTEM DEFINITION

    A quantitative RBI study, undertaken by DNV, comprises

    a comprehensive scenario based approach. For eachequipment item it considers:

    Equipment design data. The operating conditions (normal and upset) and fluid

    properties.

    The material of construction, the damage mechanismsand the severity of damage mechanism.

    The unique equipment item inspection history.The methodology includes:

    Pressure vessels, piping, heat exchangers, pumps,

    compressors, furnaces, reactors and storage tanks.

    LIKELIHOOD OF FAILURE (LOF)

    The probability of each equipment item failure is based on

    DNVs extensive Generic Failure Frequency (GFF)

    database. A modification factor is then applied for each

    specific damage mechanism. This factor is based on the

    strength of the component, the operating load, the active

    damage mechanism(s) and the inspection

    history/effectiveness. The methodology makes use of

    probabilistic and statistical methods to allow for the

    uncertainties in the parameters involved.

  • 7/30/2019 57774801 RBI Methodology

    2/2

    DET NORSKE VERITAS

    Typical damage mechanisms included:

    Thinning (general and localised). External (thinning and cracking) Stress Corrosion Cracking High Temperature Hydrogen Attack (HTHA) Fatigue Brittle FractureTechnical supplements can be used to establish damage

    mechanism rates /severities if actual data is not available.

    CONSEQUENCE OF FAILURE (COF)

    The failure of pressure containing equipment and

    subsequent release of hazardous materials can lead to

    many undesirable effects. Four basic risk categories are

    considered:

    Flammable (jet fire, pool fire, explosion) Toxic Environmental Business InterruptionFour standard release sizes are considered for each

    equipment item. Consequence models have been

    developed based on DNVs consequence software

    PHAST. This is used to determine the discharge rate,

    dispersion and consequence of each release. Consequenceis measured in terms of safety hazard zone, toxic impact,

    major environmental damage or business interruption.

    Consequence effect areas are calculated for each incident.

    Event trees are then used to determine the probability ofeach incident outcome. The methodology can also account

    for detection and mitigation measures (e.g. isolationvalves, fire monitors).

    RISK ANALYSIS

    Risk is the product of the likelihood of failure and the

    consequence.

    Risk = LoF x CoF

    Within the RBI methodology the risk can be expressed in

    terms of damage area or more frequently financial risk.

    The risk ranking identifies those equipment items with thehighest risk and whether the risk is dominated by

    likelihood of failure (a good candidate for inspection) or

    consequence (a good candidate for mitigation devices) or

    both. The figure below shows ranking in the form of a risk

    matrix.

    5

    4

    3

    2

    1

    High RiskMedium-High R isk Med. High Risk

    Medium Risk Low Risk

    Likelihood

    Category

    Consequence Category

    RISK BASED INSPECTION PLANNING

    Risk based inspection planning is a matter of acquiring

    enough information about each equipment item by

    inspection that the equipment replacement date can be

    predicted. The risk based approach is unique in that it

    allows a degree of flexibility as to the level of inspectionthat is appropriate to give the required knowledge and how

    this knowledge is accumulated, for example - by one or

    two major internal inspections or by more frequent, less

    intrusive inspections. The figure below shows the use of

    RBI tools to evaluate alternate inspection strategies.

    0

    1

    10

    100

    1000

    0 3 6 9 12 15 18 21 24 27 30

    Year

    RiskLevel

    No

    Inspections

    High Level

    Inspections

    Low LevelInspections

    "Average"

    "Below Average"

    "Above Average"

    TOOLS FOR RBI

    The fundamentals of Risk Based Inspection apply

    universally to all types of petrochemical processes, either

    onshore or offshore installations. There are however, some

    differences on the specifics of the process and the type of

    installation. DNV has developed proprietary software tools

    for RBI. ORBITTM

    Onshore is available for the onshorerefinery-, petrochemical- and chemical industries.ORBIT Offshore, Analysis of Topside Systems, has

    been developed specifically for the offshore industry.