480V Switchgear & MCC deficiencies found during inspections

22
480V Switchgear & MCC deficiencies found during inspections Loose PT connections Loose CT connection Dirty Panels and covers not affixed properly (bolts without nuts held in with tape Ground ball covers missing Stainless wire for tag securement and other foreign material left in sections (hard hats, gloves tools, metal bars, etc.) Deformed/damaged structure Modified structure Missing components Non Manufacturer hard ware Damaged cables Damaged breaker and breaker cubicle components Conduit entry into arc flash doors Wiring ferruls too small for the wire and strands that did not fit were “trimmed” off. Bus boots and covers not secured or covering bus bolts or splices Equipment numbers missing or on wrong devices Ferrous Gland Plate on MCC incoming sections. Incorrect cables on all Battery systems, flexible cable is required by spec LCS tags need to follow specific EMETL methods and include equipment tag number (not LCS P&ID number), Description, and Source (MCC and cubicle), if more than one substation in facility then building number shall be included as well. S7C- 0702-06, 07, &08 SEOLDs not created MCC cubicles not identified with cubicle numbers. Missing communication cable between SEL relays on MTM

Transcript of 480V Switchgear & MCC deficiencies found during inspections

Page 1: 480V Switchgear & MCC deficiencies found during inspections

480V Switchgear & MCC deficiencies found during inspections

• Loose PT connections• Loose CT connection• Dirty • Panels and covers not affixed properly (bolts without nuts held in with tape• Ground ball covers missing• Stainless wire for tag securement and other foreign material left in sections (hard hats, gloves tools, metal bars, etc.)• Deformed/damaged structure • Modified structure• Missing components• Non Manufacturer hard ware• Damaged cables• Damaged breaker and breaker cubicle components• Conduit entry into arc flash doors• Wiring ferruls too small for the wire and strands that did not fit were “trimmed” off.• Bus boots and covers not secured or covering bus bolts or splices• Equipment numbers missing or on wrong devices• Ferrous Gland Plate on MCC incoming sections.• Incorrect cables on all Battery systems, flexible cable is required by spec• LCS tags need to follow specific EMETL methods and include equipment tag number (not LCS P&ID number), Description,

and Source (MCC and cubicle), if more than one substation in facility then building number shall be included as well. S7C-0702-06, 07, &08

• SEOLDs not created• MCC cubicles not identified with cubicle numbers. • Missing communication cable between SEL relays on MTM

Page 2: 480V Switchgear & MCC deficiencies found during inspections

Loose 480V SWR PT Connections

Page 3: 480V Switchgear & MCC deficiencies found during inspections

Loose 480V SWR PT & CT Connections

Page 4: 480V Switchgear & MCC deficiencies found during inspections

Bolts without nuts on panels & covers

Page 5: 480V Switchgear & MCC deficiencies found during inspections

Before cleaning

Page 6: 480V Switchgear & MCC deficiencies found during inspections

Cleanliness/PT/CT connections & Ground ball covers

Page 7: 480V Switchgear & MCC deficiencies found during inspections

Deformed/damaged structural members

Page 8: 480V Switchgear & MCC deficiencies found during inspections

Structural Modifications (this bracket was moved form its original position)

Page 9: 480V Switchgear & MCC deficiencies found during inspections

Missing Components (a barrier between sections is missing in this photo)

Page 10: 480V Switchgear & MCC deficiencies found during inspections

Non manufacturer hardware

Page 11: 480V Switchgear & MCC deficiencies found during inspections

Inspect power cables for damage and tightness

Page 12: 480V Switchgear & MCC deficiencies found during inspections

Damaged hardware in breaker cubicles (this shutter mechanism is bent in a “U”

Page 13: 480V Switchgear & MCC deficiencies found during inspections

Damage to Structure

Page 14: 480V Switchgear & MCC deficiencies found during inspections

Conduit in arc flash blast openings

Page 15: 480V Switchgear & MCC deficiencies found during inspections

Conduit hole repair

Page 16: 480V Switchgear & MCC deficiencies found during inspections

Lug feral to small for wire (you can see where wire strands were given a “haircut”

Page 17: 480V Switchgear & MCC deficiencies found during inspections

Foreign objects found in gear (here is wire that held on information tags left on a ground ball that will be energized). Hard hats, gloves, metal rods, info

tags, tools etc. were found in the gear during our inspections.

Page 18: 480V Switchgear & MCC deficiencies found during inspections

Info tag left in gear

Page 19: 480V Switchgear & MCC deficiencies found during inspections

Another example of CT layout also be sure that the bus boots & covers are all in place and secured.

Page 20: 480V Switchgear & MCC deficiencies found during inspections

Equipment tagging – not there or wrong (below the Bus PTs are labeled Line PT and the Line PT is labeled Bus PT)

Page 21: 480V Switchgear & MCC deficiencies found during inspections

Gland plates made from ferrous material

Page 22: 480V Switchgear & MCC deficiencies found during inspections

Incorrect battery cable, flexible cable required to eliminate stress on connections