#42 - APWA Lets Talk Prioritization slidesmidatlantic.apwa.net/Content/Chapters/midatlantic.apwa...$...
Transcript of #42 - APWA Lets Talk Prioritization slidesmidatlantic.apwa.net/Content/Chapters/midatlantic.apwa...$...
A Fairfax County, VA, publication
Department of Public Works and Environmental ServicesWorking for You!
Let’s Talk PrioritizationAPWA Mid-Atlantic Chapter Conference May 3, 2018
December 14, 2017
Let’s Talk Prioritization
Stormwater/Maintenance and Stormwater Management Division
Agenda
• Background• Fairfax Stormwater Likelihood of Failure• Fairfax Stormwater Consequence of Failure• Things to Look out for• Scoring/Ranking• What Next?
2
Let’s Talk Prioritization
Who am I
• Engineer at Fairfax County Stormwater Maintenance• Working with Prioritization/Asset Management for three years• Primarily worked with Stormwater Pipe Prioritization but
dabbled in Sanitary Pipe Prioritization• Attended Prioritization Presentations for:
– Stormwater Pipe– Sanitary Sewer Pipe– Water Lines– Pump Stations – Ponds
3
Fairfax County Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Fairfax County – Prioritization Background
• Program was solely complaint driven• Started CCTV in 2009
– 950+ out of 1300 miles complete– Provides internal condition of pipes
• NASSCO PACP grading system allows capability to rank– Ranks pipe defects by structural score– Reviewed highest ranked pipes, added proactive projects to the Work
Plan
• Started to create a Prioritization system, using a consultant– Likelihood of Failure (LOF) parameters– Consequence of Failure (COF) parameters
• Currently Refining LOF and COF Parameters
4
- Engineers
- Project Managers
- Senior Management
Fairfax County Stormwater Pipe Prioritization Program
Fairfax County - Background - Staff Workshop
• May 2017• Staff from varied aspects participated
‒ Customer Service – call takers‒ Complaint Technicians‒ Maintenance Professionals
• Two Agencies Represented
• Surveyed participants prior to workshop– Typical problems– History of complaints they hear about or see
• Consultant developed initial parameters• Fairfax team vetted, expanded, refined and ranked the parameters
5
- Stormwater MSMD - CAP (Wastewater)
Stormwater/Maintenance and Stormwater Management Division
Fairfax County Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Likelihood of Failure
9 LoF Parameters:• PACP Structural QuickScore• Joint Defects• PACP Operation and Maintenance (O&M) QuickScore• Hydraulic Capacity• Pipe Material• Installation Date• Cover Depth/Surface Features• Groundwater Level• Soil Type
6
Fairfax County Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Likelihood of Failure
• PACP Structural QuickScoreThe Structural QS represents the severity and quantity of defects in a pipe. Severe defects are assigned higher grades.
Need to complete CCTV of entire storm conveyance network.
• Pipe Joint DefectsOffset/separated joints are a major problem in storm pipes, but the PACP grade is not adequate to depict their severity.
Need to complete CCTV of entire storm conveyance network and identify pipes with joint defects
• PACP Operation and Maintenance (O&M) QuickScoreO&M defects can also cause structural failure. O&M allows us to prioritize cleaning.
Need to complete CCTV of entire storm conveyance network and identify pipes with O&M defects
7
Fairfax County Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Likelihood of Failure
• Hydraulic CapacityIf a pipe is unable to contain a 10-year storm causing nuisance flooding or doesn’t have Overland Relief, it is considered a failed pipe.
Need to determine drainage area to each pipe. Need to confirm pipe dimensions.
• Pipe MaterialSome materials are more susceptible to damage or accelerated deterioration.
Need to update GIS with pipe material, including renewed pipe.
• Installation DateSome deterioration is expected to occur as a pipe ages.
Use easement dates to estimate the age.
8
Need to determine what you consider failure.
Under capacity may cause flooding but may not
cause damage to the pipe
Fairfax County Stormwater Pipe Prioritization Program
Age of Pipes
9Stormwater/Maintenance and Stormwater Management Division
Fairfax County Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Likelihood of Failure
The following parameters were identified as affecting LoF. However, they are more constant parameters that may not
change with repair or rehabilitation.
• Cover Depth/Surface FeaturesPipes are more susceptible to damage when in shallow circumstances.
Need to determine pipe depths.
• Groundwater LevelGroundwater fluctuations can displace surrounding soil, and affect load capacity.
Need to determine groundwater depths around pipes.
• Soil TypeSoil properties can affect pipe settlement and damage.
10
Fairfax County Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Consequence of Failure
5 CoF Parameters:• Potential Damage to Critical Facilities• Pipe Flow Rate• Population Density• Site Accessibility• Water Quality Impacts
11
Fairfax County Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Consequence of Failure
• Potential Damage to Critical FacilitiesPipe failure near critical facilities could create problems that impact loss of life or emergency response.
Need to determine where pipes are located relative to the critical facilities.
• Pipe Flow RateA pipe with greater flow will have more displaced water should it fail.
Need to update pipe dimensions and slope.
• Population DensityThe surrounding population density may indicate the number of people impacted or the magnitude of property loss caused by a potential pipe failure.
12
Let’s Talk Prioritization
Choosing Scoring Ranges
13
y = 261.14e-0.19x
0
50
100
150
200
250
300
350
400
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 26 28 29 33 37 47 54
Freq
uenc
y
Population Density(people/acre)
Frequencies of Population Densities
Notes: Densities rounded up to a whole numberAreas delineated by subwatershed boundaries
Fairfax County Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Consequence of Failure
• Site AccessibilityPipes that are more difficult to access could require more time and effort to repair when they fail.
Need to determine surrounding conditions, such as topography, buildings, foundations, pipe depth, to access each pipe.
• Water Quality ImpactsA failed pipe could transport surrounding contaminants into a protected area
Determining non-natural contaminant sources
14
Let’s Talk Prioritization
Parameters should be based on your own circumstances
What type of asset? Where is it located? What are the geographic circumstances
• Stormwater tends to be shallow– Less focus on crossing utilities since they tend to be below our system
• Less contaminants than sewer pipes– Typically less sever environmental impacts when failure occurs
• VDoT in Fairfax owns the stormwater pipe under the road.– Our focus is less road damage more residential damage
15
Let’s Talk Prioritization
Building up Data
• Baby Steps– What data do you have?– What can you get? How fast can you get it?– Are there interim steps that can be taken?
We have people walking grids to do above ground inspections. We can add a section of site accessibility to their forms.
16
Site Accessibility
Have Need
GIS layers• Buildings• Tree cover• Contours• Roads• Some invert depths
Where the pipe is relative to buildings?What is the density of nearby trees?What is the depth through the length of the pipe
Let’s Talk Prioritization
Things to look for
• Same Data but Opposing Parameters
If looking at the parameters on an individual basis, this could be helpful.
17
Depth
Cost – Accessibility Likelihood – Damage
The deeper the pipe is the more expensive it will be to fix
Deep pipes would have a more critical score
The more shallow a pipe is the more damage it will receive from live loads
Deep pipes would have a less condition score
Let’s Talk Prioritization
Things to look for
• “Double Dipping”
18
Holes
PACP Quick Score Cave-in – Joint and Hole
Holes have a Score of 5.If a hole is coded in a pipe it will automatically be within the highest score range.
If a Hole is coded in a pipe it will be given the highest score
Cave-ins can be caused by joints and holes. If there is a hole or a large joint offset it is within the highest score range.
If a Hole is coded in a pipe it will be given the highest score
Unconnected Joints do not have the capability of getting a PACP score of 5, but they cause
major problems in out Stormwater pipes
…But what about joints?
Fairfax County Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Scoring – Ex. Refining: Pipe Diameter/Capacity
19
Date GroupScore
1 2 3 3.1 4 5
10/16 Consultant
The pipe is measured or
determined to be less than 24-inches
in diameter
N/A
The Pipe is measured or determined to be grater than or equal to 24-
inches and less than or equal to 42-inches in diameter
X N/A
The pipe is measured or determine to be greater
than 42-inches in diameter
3/17 ConsultantThe pipe capacity is determine to be less than 22 cfs (14 mgd)
N/A
The pipe capacity is determine to be greater than or equal to 22 cfs (14
mgd) and less than or equal to 67 cfs(44 mgd)
X N/AThe pipe capacity is
determine to be greater than 67 cfs (44 mgd)
5/17 Consultant < 22 cfs N/A 67 cfs ≥ capacity ≥ 22 cfs X N/A >67 cfs
7/17 Consultant
< 22 cfs - basis is range of 15" to 24"
dia. Pipes with scouring velocity at
7 ft/sec
N/A67 cfs ≥ capacity ≥ 22 cfs - basis is
range of > 24" dia. To 42" dia, scouring velocity at 7 ft/sec
Unknown pipe diameter N/A
> 67 cfs; basis is range of > 42" dia. Pipe with scouring
velocity at 7 ft/sec
11/17 Fairfax* Qmax < 2.5 cfs N/A 2.5 cfs ≤ Qmax ≤ 25.1 cfsUnknown
pipe diameter or slope
N/A Qmax >25.1 cfs
* data based on PFM 2 ft/s
Fairfax County Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Scoring
• Scoring Range 1-5 (good – critical) used– Range 1-3 does not differentiate the conditions enough– Range 1-10 is an acceptable alternative and differentiates parameters
more successfully, complicates with more choices• 1-5 keeps it simple as we form and we can see if it doesn’t differentiate
adequately
Unknown Information :Any Parameter with no knowledge is scored as 3.1
20
Fairfax County Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Scoring - Calculating Final Score for Ranking
• Likelihood of Failure– Uses highest scored parameter
• Can dilute information for critical condition pipes• If it has failed in one category, it’s failing
– Should there be a count of the scores? Should those with multiple parameters with a score of 5 be elevated
• Consequence of Failure– Parameters are weighted based on perceived criticality – Balances all the different impacts
21
Fairfax County Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Ranking - Weighting for CoF
Workshop initial estimate:
• 46% Potential Damage to Critical Facilities• 25% Pipe Flow Rate• 15% Population Density• 12% Site Accessibility• 2% Water Quality Impacts
If something is only at 2% is it worth keeping?Fine-tuning will be needed once the final parameters are defined and refined.
22
What’s important to you? Stormwater doesn’t have as much
risk as sanitary.
Let’s Talk Prioritization
Weighting
• Watch when you Weight multiple times
23
Criticality Category
Category Weight Parameter Parameter
Weight Final Weighting
Level of Service 40%
Option #1 40% 16%
Option #2 60% 24%
Environment 40%Option #3 30% 12%
Option #4 70% 28%
Cost 20%
Option #5 20% 4%
Option #6 45% 9%
Option #7 35% 7%
Is 4% really worth keeping?
Let’s Talk Prioritization
Stormwater/Maintenance and Stormwater Management Division
Ranking - Problems with Calculated Risk
• ‘Risk’ = LoF x CoF• ‘Risk’ is a very linear way of looking at pipes.
– Which pipe is worked on first vs. How should we handle this pipe
• It can dilute information and decrease ability to find the correct pipes to rehab
24
A pipe in fair condition will be looked at for rehabilitation
before a pipe in critical condition
18.35
11.85
10.329.66
9.33
8.48
7.727.14
5.95.43
4.92
4.163.77
2.712.18
Like
lihoo
d of
Fai
lure
Consequence of Failure
Let’s Talk Prioritization
Stormwater/Maintenance and Stormwater Management Division
Ranking - Calculated Risk Graph
25
18.35
11.85
10.329.669.33
8.487.72
7.14
5.95.43
4.924.16
3.77
2.712.18
1
25
1 25
Like
lihoo
d of
Fai
lure
Consequence of Failure
Let’s Talk Prioritization
Stormwater/Maintenance and Stormwater Management Division
Ranking - Prioritization Table
26
Like
lihoo
d of
Fai
lure
Consequence of Failure
5
4
3
2
1
0 1 2 3 4 5
Let’s Talk Prioritization
Stormwater/Maintenance and Stormwater Management Division
What Next?
• Planning– What information are we deficient in?– Cost of obtaining that information– Weighting CoF Parameters once defined
• Implement– Test Parameters– Evaluate Results
• Differentiation• Matrix Definitions
– Adjustments• Parameters• Weighting• Matrix
27
Additional Information
For additional information, please contact
www.fairfaxcounty.gov/dpwes
Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division 28
Amy Linderman
703-877-2872
Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Condition Assessment Progress
29
0.8% 1.2% 1.5% 2.5%1.7% 2.4% 3.1% 4.1%
9.6%14.7%
19.2%22.8%
28.6%
37.9%
40.5%
42.0%
0.7%
0.8%
0.9%
1.0%58.6%
43.0%
34.9%27.5%
0.0
200.0
400.0
600.0
800.0
1000.0
1200.0
1400.0
7/1/14 7/1/15 7/1/16 7/1/2017
Structural
Additional Review Required Failed or Failing Minor Defects Good Rehabbed Not Assessed Yet
Stormwater Pipe Prioritization Program
Quick Score Delineation
30
Rehabbed1%
000037%
1000-1z005%
2000-2z1z7%
3000-3z2z12%
4000-4z3z1%
5000-5z4z4%
Additional Review Required 2%
Need to CCTV31%
Based on data from July 2017
Stormwater/Maintenance and Stormwater Management Division
Stormwater Pipe Prioritization Program
Diameter of Pipes in System
31Stormwater/Maintenance and Stormwater Management Division
Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Scoring - LoF
32
Likelihood of FailureScore
Parameter 1 2 3 3.1 4 5
1 PACP Structural QS
No defects or like new, Structural QS = 0000
Minor defects, Structural QS 100 to 3100 Structural QS 300 to 4100 No information on
pipe condition Structural QS 4100 to 5100 Abandoned survey or Structural QS =/> 5100
2 Joint and Hole Defects No visible joint defects
Joint infiltration stains verified to be without joint
seals
Any separated joint or hole with infiltration stains and >1 cave-in
complaint
Any separated joint or hole with active infiltration, >3
cave-in complaints
Any offset/misaligned joint or hole with active infiltration, > 6
cave-in complaints
3 PACP O&M QuickScore
Pipe is clear or O&M QS is 0000 to 2100
Sediment, debris or roots present, or O&M QS is 2100
to 3100
>10% of the cross-sectional area is blocked, flushing or root cutting is
required more than once/yr, or O&M QS is 3100 to 4100
O&M QS of 4100 to 5100Cross bores or intrusions (pipe break-ins) present or O&M QS
is 5100 or greater
4 Hydraulic Capacity
Pipe can adequately convey the 10-yr storm and sufficient OLR exists
Pipe cannot adequately convey the 10-yr storm and OLR is sufficient
Pipe capacity is unknown
Pipe can adequately convey the 10-yr storm and works
with OLR
Pipe cannot adequately convey the 10-yr storm and OLR does
not exist
5 Pipe Material
Reinforced Concrete (RCP) or rehabilitated
with structural integrity (ex. CIPPL)
Non-Reinforced Concrete or rehabilitated with non-
structural integrity (ex. Slip-line or coated)
Masonry block, brick or clay Unknown Corrugated Metal (CMP) or High Density Polyethylene
(HDPE)
6 Installation Date
Installed or renewed after 1995 1984 through 1995 1974 through 1983 Unknown 1961 through 1973 Before 1961
7Cover Depth/ Surface Features
Average cover is greater than 8 feet
Average cover is between 2 feet and 8 feet, and lies only under an unpaved
area or sidewalk
Average cover is between 2 feet and 8 feet, and lies partially under a roadway
or building
Pipe cover depth or type is unknown
Average cover is 2 feet or less and lies only under an
unpaved area or sidewalk
Average cover is 2 feet or less and at least partially lies under
a roadway, driveway or building
8 Groundwater level
Groundwater level stays below the pipe invert
Groundwater level remains above the pipe invert and below the pipe crown
Unknown groundwater level
Groundwater level fluctuates from above the pipe crown to
below the pipe invert
9 Soil Type Sand or Gravel Unknown or classified as Urban
Acidic/corrosive, Silt, Loam or Marine Clay
Stormwater Pipe Prioritization Program
Stormwater/Maintenance and Stormwater Management Division
Scoring - CoF
33
Consequence of FailureScore
Parameter 1 2 3 3.1 4 5
A
Potential Damage to Critical Facilities
Failure would cause minimal or no property
damage
Failure may cause erosion or temporary yard flooding
Non-Critical - Failure would cause damage to transit, park & ride, or
transportation facilities
Degree of failure damage is unknown
Essential - Failure would cause damage to dwellings, government buildings
Critical - Failure would cause damage to a fire or police
station, sanitary sewer pump station, electrical sub-station,
hospital or health center
B Pipe Flow Rate Qmax < 2.5 cfs Capacity 2.5 cfs through 25.1 cfs Pipe size or slope is unknown Q max > 25.1 cfs
C Population Density
Pipe lies in area of 0-25 persons per acre
Pipe lies in area of 26-50 persons per acre
Pipe lies in area of 51-75 persons per acre
Population density is unknown
Pipe lies in area of 76-100 persons per acre
Pipe lies in area of 101 or more persons per acre
D Site Accessibility
Equipment access is through an easily
accessible right-of-way or easement
Equipment access is through County property or
an easily accessible road right-of-way
Equipment access is through County property, without a cleared accessway.
Access may involve tree removal or installation of construction
entrances/roads
Equipment access may involve: removing fences,
sheds or other semi-permanent structure: cutting
trees or installation of temporary construction
entrances/ roads; obtaining permission over private or
non-Co property
Pipe is located behind/under permanent structures/buildings
with no equipment access. Building foundations are close
to easements. Accesswayscontain steep slopes or utility
obstructions.
E Water Quality Impacts
> 200 feet from a BMP, floodplain, wetland or Resource Protection
Area, and containment of contamination within
or nearby the asset exists
> 200 feet from a BMP, floodplain, wetland or
Resource Protection Area and containment of
contamination within or nearby the asset not
available
<200 feet from a BMP, floodplain, wetland or Resource Protection Area
If an incident that causes water-borne contaminants or
sedimentation cannot be contained by natural or
constructed features, would potentially contribute to water
quality impairment