4. Capturing lessons learned, 12th Oct 2015
-
Upload
association-for-project-management -
Category
Business
-
view
585 -
download
1
Transcript of 4. Capturing lessons learned, 12th Oct 2015
© Turner & Townsend plc December 11making the difference
Capturing Lessons Learned
Art and Design Building Project
..........
..........
..........
2
Speaker Profile
APM 2010 - Project Manager of
the Year
Associate Director at Turner and
Townsend
Matthew Pendergast
APM 2013 – Finalist Project of
the Year – Liverpool Library
3
Aims of Session
■ To understand why we should undertake lessons learned
■ To learn best practice lessons learned techniques
■ To learn how we captured lessons learned on MMU Art & Design project
■ To learn how we are applying lessons on future projects
� Original School of Art 1885
� Chatham Tower 1960 refurbishment
� New Build 7,000m²
� Vertical Gallery - Eye on the Arts
� Convergence of Digital and Craft
� Village Green – collaboration
� Shared resources
� Open spaces
� Natural light
� Creative
School of Art & Design
School of Art & Design
6
Definitions of Lessons Learned
■ The bringing together of any insights gained during a project that can be
usefully applied on future projects.
■ PMBoK defines lessons learned as the learning gained from the process of
performing the project to
■ Promote the reoccurrence of desirable outcomes and
■ Preclude the reoccurrence of undesirable outcomes”
7
Lessons Learned
8
Question
“What percentage of projects
undertake a formal lessons learned
exercise?”
9
Why don’t we do lessons learned
■ Lack of time.
■ Lack of management support.
■ Lack of resources.
■ Lack of clear guidelines around collecting the information.
■ Lack of processes to capture information.
■ Lack of knowledge base to store and search information captured for future us.
10
Art and Design Building
Programme
Estimated – 74 weeks
Actual – 107 weeks
Cost (Construction)
Estimated – £23m
Actual – £23.5m
Cost (Overall)
Budget – £36.7m
Actual – £33.8m
11
Industry Best Practice
12
Methodology
13
Best Practice Methods - Qualitative
14
Best Practice Methods - Quantative
15
Process
■ Project Objectives
■ Delivery against programme and
budget
■ Project Organisation and
Governance
■ Reporting and Controls
■ Project team performance and
behaviours
■ Project Execution Plan(s)
■ Risk Management
■ Procurement and Supply Chain
Management
■ Cost Control/ Finance
■ Design Management
■ Construction Phase performance
(including Quality Management)
■ Change Control/ RFI/ Contract
Administration
■ Health, Safety, Security and
Environmental
■ Commissioning and Handover
■ Defects Management
16
Functional and Technical Performance
■ Overall quality of the areas
■ Security of the building
■ Accessibility
■ Cleanliness
■ Air Quality
■ Temperature
■ Noise
■ Lighting
■ Serviceability
■ Whole Life Cycle Costs/ Space
Utilisation Benchmarking
■ Aesthetic and Image Space
■ Environmental Systems
■ ICT Systems
■ In Use
17
Summary of Key Findings
■ Went Well
■ User Leadership and Decision Making
■ Collaboration and integration
■ Streamlined decision making
■ Use of best practice tools, templates and processes
■ Favourable benchmarked life cycle costs, energy usage and space utilisation
figures
■ Financial Reporting
■ Appropriately resourced
■ Legal and Procurement
18
Areas of Development
Area for Development How have we addressed
M&E Defects Picked up in backlogmaintenance
Continuity of IT personnel Dedicated ICT resource
Elements of training were reactive
Soft Landings Strategy and Action Plan
Door Design Addressed through planned maintenance programme
Sub Contractor insolvency Market Driven
Test Business Case Objectives have been met
Use of KPI’s
19
Conclusion
■ To understand why we should undertake lessons learned
■ To learn best practice lessons learned techniques
■ To learn how we captured lessons learned on MMU Art & Design project
■ To learn how lessons are being applied on future projects