38kV Overhead Lines - CRU Ireland · 2019. 1. 24. · Siemens in late 1920s and early 1930s •...
Transcript of 38kV Overhead Lines - CRU Ireland · 2019. 1. 24. · Siemens in late 1920s and early 1930s •...
-
Gate 3 Liaison Group
38kV Overhead Lines
Eoin Waldron
Overhead Networks Engineer
Asset Management
ESB Networks
-
Original 38kV Network System Current 38kV Network System
-
Introduction
• First lines were built by Siemens in late 1920s and early 1930s
• Currently there is 5,700kMs of 38kV Overhead Line
• There are a large amount of original Siemens lines still in service
• Over 4,000km of network is more than 10 years old
• Almost 60% of the network is over 30 years old
KMs of 38kV Overhead Line by Conductor Type
KMs
35 & 50 Copper
1003
KMs
Other
170
KMs
150 AAAC
567
KMs
200 & 300 ACSR
435KMs
100 ACSR
3407
Other
35 & 50 Copper
200 & 300 ACSR
150 AAAC
100 ACSR
38kV Overhead Network - Age Profile
0
200
400
600
800
1000
1200
1400
1600
Pre 1940 1940-49 1950-59 1960-69 1970-79 1980-89 1990-99 2000-09
38kV Overhead Network - Age Profile
0
200
400
600
800
1000
1200
1400
1600
Pre 1940 1940-49 1950-59 1960-69 1970-79 1980-89 1990-99 2000-09
38kV Overhead Network - Age Profile
0
200
400
600
800
1000
1200
1400
1600
Pre 1940 1940-49 1950-59 1960-69 1970-79 1980-89 1990-99 2000-09
-
Design History
• ESB adapted the German design in the
1940’s based on their own experience
• From 1940’s to 1980’s ESB built 38kV
lines on portal structures
• Mainly built with 92mm2 ACSR conductor
• Conductor suspended from double wood-
pole structure on strings of disc insulators
• Mainly Steel Towers on angle Positions
• Designed with span lengths of between
150m to 200m.
-
Design History
• In the 1980’s the design was changed to a
single pole design
• Still used 92mm2 ACSR conductor
• Conductor supported on pin-insulators
• Lines look more like Medium Voltage Lines
• Used heavier wood poles than Portal lines
• Usually Wood Poles at Angle Structures
• Maximum span length of 190m
-
Design History
• In the 1940’s the maximum design operating temperature for 92mm2
ACSR was 40oC.
• At that time it was not envisaged that lines would be loaded above
40oC
• Over time the maximum operating temperature was increased
• In the 1980’s the maximum operating temperature for ACSR
conductor was 60oC
• Lines were designed to give a minimum of 6.0m ground clearance at
maximum operating temperature
• In older ACSR lines the grease in the conductor is the limiting factor
-
Current Design
• All lines are now designed to operate at 80oC
• All lines designed since 2003 are designed to have a minimum of 7.0m
of ground clearance at maximum design temperature
• 7.0m clearance required where a line is being restrung with new
conductor or thermally up-rated
• The reasons for these changes is:
• Higher operating temperature – increased thermal capacity
• Higher ground clearance – increased safety margin under 38kV lines
-
Case Study – No. 1
• Existing 92mm2 ACSR line built before 1980 - Of which there are 2,000km
• Designed to 50oC and 6.0m of ground clearance
• Average span length of 150m
• Increase in load requires it to be thermally up-rated to 80oC
• Increase in Load of 6MVA
Sag @ 50oC = 3.43m
Using 13m Poles
13.0m
- 2.3m Foundation
- 0.6m Insulators
- 3.43m Sag
= 6.67m GC
6.67m
Ground Clearance OK
-
Case Study – No. 1
• Existing 92mm2 ACSR line built before 1980 - Of which there are 2,000km
• Designed to 50oC and 6.0m of ground clearance
• Average span length of 150m
• Increase in load requires it to be thermally up-rated to 80oC
• Increase in Load of 6MVA
Sag @ 80oC = 3.95m Using 13m Poles
13.0m
- 2.3m Foundation
- 0.6m Insulators
- 3.95m Sag
= 6.15m GC
6.15m
Ground ClearanceMust Have 7.0m
Sag @ 50oC = 3.43m
-
Case Study – No. 2
• Existing 92mm2 ACSR line built after 1980 on single wood poles
• Designed to 60oC and 6.0m of ground clearance
• Average span length of 150m
• Increase in load requires conductor to be changed to 150mm2 AAAC
• Increase in Load of 14MVA ~ 50% increase in capacity
Sag @ 60oC = 3.61m
Using 12m Poles
12.0m
+ 0.4m Insulators
- 2.3m Foundation
- 3.61m Sag
= 6.49m GC
6.49m
Ground Clearance OK
-
Case Study – No. 2
Sag @ 60oC = 3.61m
Using 12m Poles
12.0m
+ 0.4m Insulators
- 2.3m Foundation
- 4.04m Sag
= 6.06m GC
Sag of Mulberry
@ 80oC = 4.04m
Must Have 7.0m6.06m
Ground Clearance
• Existing 92mm2 ACSR line built after 1980 on single wood poles
• Designed to 60oC and 6.0m of ground clearance
• Average span length of 150m
• Increase in load requires conductor to be changed to 150mm2 AAAC
• Increase in Load of 14MVA ~ 50% increase in capacity
-
Re-Using Existing Material
• In general when a line is rebuilt all wood poles / crossarms /
insulators etc. are replaced
• Changing from 50mm2 Copper to 150mm2 AAAC
– Wishbone crossarms are not suitable for 150mm2 AAAC
– Single poles used on 50mm2 Copper are too light for 150mm2 AAAC
– 50mm2 Copper hardware not suitable for 150mm2 AAAC
• Changing from 92mm2 ACSR to 150mm2 AAAC / 300mm2 ACSR
– Heavier crossarms required for 150mm2 AAAC & 300mm2 ACSR
– In general poles would be replaced due to pole strength and ground
clearance
-
Thank You
Questions??