ITP - TECHNIBUILD CONTRACTING (OMAN) LLC Revision R1 ,DATE:09.10.12 INSPECTION TESTING PLAN (ITP) Prepared By : Contractor Reviewed By : Main Contractor / Consultants Approved By : Owner Technibuild Contracting (Oman) LLC

description

detailed piling

Transcript of 38-r1

Page 1: 38-r1

Revision R1 , 09.10.12

INSPECTION TESTING PLAN (ITP)

ActivityContractor Client

1 Pile Point Verification 5 mm Survey Book R Surveyor W

2 Boring Visual every pile W R

every pile W R

3 Concreting one per lot R R R

4 Reinforcement Cage lowering Visual random R R

5 Pile Load Tests Visual Every test Engineer W W/R

Sr. No.

Controlling Document

Type of Inspection/ test method

Acceptance Criteria

Frequency of Check/ Test

Verification Documents

Verification personnel / agency ( Review, Hold, Witness points )

Main Contractor

Pile lay-out drawing

every pile point

Project Specification

75 mm in shift in any direction

Daily Piling Report

Rig Opt & Foreman

1% in verticality

Daily Piling Report

Rig OPT & Foreman

Project Specification

Concrete Cube strength test

As per BS 8110

Third Party Laboratory Test report

Project Specification

Daily Piling Report

Rig OPT & Foreman

Project Specification & SPERW

As per SPERW

Pile Test Record

Prepared By : Contractor Reviewed By : Main Contractor / Consultants Approved By : OwnerTechnibuild Contracting (Oman) LLC