38-r1
description
Transcript of 38-r1
Revision R1 , 09.10.12
INSPECTION TESTING PLAN (ITP)
ActivityContractor Client
1 Pile Point Verification 5 mm Survey Book R Surveyor W
2 Boring Visual every pile W R
every pile W R
3 Concreting one per lot R R R
4 Reinforcement Cage lowering Visual random R R
5 Pile Load Tests Visual Every test Engineer W W/R
Sr. No.
Controlling Document
Type of Inspection/ test method
Acceptance Criteria
Frequency of Check/ Test
Verification Documents
Verification personnel / agency ( Review, Hold, Witness points )
Main Contractor
Pile lay-out drawing
every pile point
Project Specification
75 mm in shift in any direction
Daily Piling Report
Rig Opt & Foreman
1% in verticality
Daily Piling Report
Rig OPT & Foreman
Project Specification
Concrete Cube strength test
As per BS 8110
Third Party Laboratory Test report
Project Specification
Daily Piling Report
Rig OPT & Foreman
Project Specification & SPERW
As per SPERW
Pile Test Record
Prepared By : Contractor Reviewed By : Main Contractor / Consultants Approved By : OwnerTechnibuild Contracting (Oman) LLC