3.3 Existing Intersection Performance
Transcript of 3.3 Existing Intersection Performance
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 20
3.3 Existing Intersection Performance
The assessment of impacts associated with the proposed development has been assessed against a
‘base case’ being the existing traffic conditions. Accordingly, Surveys were undertaken to assess the
performance of the surrounding road network at the following key intersections:
Winnie Street with Gerard Street;
Winnie Street with Military Road;
Winnie Street with Parraween Street.
Waters Road with Belgrave Street/Gerard Street.
Waters Road with Grosvenor Street;
Waters Road with Military Road; and
A summary of the weekday traffic count surveys for the respective AM and PM peak periods are
provided in Figure 10 and Figure 11 below. It is noted that the weekend intersection operations were
discussed and analysed in the concept proposal TIA but not considered necessary for the Stage 1 DA
as all works are associated with weekday operation only.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 21
Figure 10: Existing AM Peak Turning Counts
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 22
Figure 11: Existing PM Peak Turning Counts
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 23
These surveys were taken on a typical school day in November 2014 from 7:00-9:00am during the
morning period and 2:00-6:00pm during the afternoon/evening period The PM surveyed period of 2pm-
6pm was surveyed to encompass the school peak departure times (2-4pm) and the road network peak
periods (4-6pm). The results of these surveys were analysed using the SIDRA computer program to
determine their performance characteristics under existing traffic conditions. The SIDRA model
produces a range of outputs, the most useful of which are the Degree of Saturation (DOS) and
Average Vehicle Delay per vehicle (AVD). The AVD is in turn related to a level of service (LOS)
criteria. These performance measures can be interpreted using the following explanations:
Degree of Saturation (DOS) - a measure of the operational performance of individual intersections. As
both queue length and delay increase rapidly as DOS approaches 1, it is usual to attempt to keep DOS
to less than 0.9. When DOS exceeds 0.9 residual queues can be anticipated, as occurs at many
major intersections throughout the metropolitan area during peak periods. In this regard, a practical
limit at 1.1 can be assumed. For intersections controlled by roundabout or give way/stop control,
satisfactory intersection operation is generally indicated by a DOS of 0.8 or less.
Average Vehicle Delay (AVD) - the AVD for individual intersections provides a measure of the
operational performance of an intersection. In general, levels of acceptability of AVD for individual
intersections depend on the time of day (motorists generally accept higher delays during peak
commuter periods) and the road system being modelled (motorists are more likely to accept longer
delays on side streets than on the main road system).
Level of Service (LOS) - this is a comparative measure which provides an indication of the operating
performance of an intersection as shown in Table 1 below.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 24
Table 1: Intersection Performance Characteristics
Level of
Service
Average Delay per
Vehicle (secs/veh) Traffic Signals Give Way and Stop Signs
A less than 14 Good operation Good operation
B 15 to 28 Good with acceptable delays and spare
capacity Acceptable delays and spare
capacity
C 29 to 42 Satisfactory Satisfactory but accident study
required
D 43 to 56 Operating near capacity Near capacity and accident study
required
E 57 to 70 At capacity; at signals incidents will
cause excessive delays. Roundabouts require other control mode
At capacity and requires other control mode
F More than 70 Unsatisfactory and requires additional
capacity. Unsatisfactory and requires other control mode or major treatment.
A summary of the modelled results are provided in Table 2 below.
Table 2: Intersection Performance - Existing
Intersection Description Control Type Period Degree of
Saturation
Intersection
Delay
Level of
Service
Winnie Street / Gerard Street
Signals
AM 1.023 38.3 C
PM 0.938 40.3 C
Waters Road / Belgrave Street/Gerard Street
Signals
AM 0.764 9.5 A
PM 0.645 9.7 A
Waters Road / Grosvenor Street
Giveway
AM 0.104 4.6 A
PM 0.155 4.4 A
Winnie Street / Murdoch Street /
Military Road Signals
AM 1.038 40.5 C
PM 0.998 48.1 D
Waters Road / Military Road
Stop
AM 0.141 14.4 A
PM 0.212 15.1 B
Winnie Street / Parraween Street
Giveway
AM 0.251 6.9 A
PM 0.154 6.6 A
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 25
It can be seen from Table 1 that all intersections operate satisfactorily under existing conditions. It is
noted that the intersection of Winnie Street, Murdoch Street with Military Road operates at near
capacity during the PM peak period. Notwithstanding this, it is stressed that the purpose of the existing
analysis is to compare the relative change in the performance parameters as a result of the proposed
development. This is discussed further in Section 7.
3.4 Public Transport
A pedestrian overpass located on Military Road provides convenient and direct pedestrian access
route to/from north and south of Military Road. The public bus services on the local road network are
shown in Figure 12, and those which travel within approximately 400m of the subject site are as
follows:
Route M30: Metrobus Spit Junction to Sydenham
Route 225: Neutral Bay Wharf to Cremome Wharf
Route 243: Spit Junction to City via North Cremome
Route 257: Balmoral Beach to Chatswood
Route 263: Crows Nest to City via Neutral Bay and Kirribili
Route 169,173: Narraweena to city and Milsons Point
Route 227-230: Mosman Junction, Clifton Gardens, Beauty Point and Mosman Wharf to Milsons
Point
Route 244-249: Chowder Bay, Balmoral, Taronga Zoo and Spit to City
Route 140,143,145: Epping and Chatswood to Mainly
Route 160s,170s,180s: Northern Beaches Services as far as Palm Beach.
It is clear from the above that there are a multitude of public transport options for school patrons.
Section 4 discusses the travel mode characteristics of the site in particular the utilisation of public
transport by students and staff.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 26
Figure 12: Public Transport
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 27
3.5 Minibuses
The school has a fleet of 6 minibuses which are all loaded and unloaded from the existing internal area
accessed via Military Road (two access driveways). Three of these buses are stored on the main
campus with the additional three buses stored within the Adams Centre site (accessed via Hampden
Avenue). The movement of the buses are sporadic with the use of the buses generally in the AM peak
and PM peak (3-4pm) and infrequently throughout the day for school excursions. The buses are
generally used to transport students to external sporting venues.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 28
4. Description of Proposed Development
4.1 Overview
A detailed description of the proposed development is provided in the Statement of Environmental
Effects prepared separately by Urbis. In summary, Stage 1 of the development for which approval is
now sought comprises the sub-stages:
Stage 1A
Demolition of landscape & erect 7 modular classrooms for relocation of visual and performing
arts
Relocation of music to 7 & 8 Monford Place
Demolition of Gerard Street Cottages
Landscape forecourt expansion
Stage 1B
Construct of shell for car park / music / performing arts /infrastructure
Relocation of music / performing arts / b block in the new building upon completion.
Stage 1C
Install 7 additional modular classrooms + relocate 7 on top of music / car park to
accommodate faculties from Mowll
Demolition of buildings (Mowll, 7 & 8 Monford Place, garage)
Construction of forecourt & stormwater relocation - as separable portion + enabling works
Sewer relocation - as separable portion + enabling works
Construction of new learning hub
Provision of interim car park layout with a total of 45 parking spaces including 2 disabled
parking spaces.
Stage 1D
Relocation of faculties into the new learning hub + removal of modular classrooms
Completion of car park, driveway and landscape
Provision of interim car park layout with a total of 68 parking spaces including 2 disabled
parking spaces.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 29
Stage 1E
New learning hub complete
Demolition of redundant cottages
Construction of new access road and bus parking (entry from Waters Road and exit onto
Military Road)
The traffic and parking impacts arising from the development are discussed in Sections 5 and 6.
Reference should be made to the plans submitted separately to Council which are presented at
reduced scale in Attachment 1.
4.2 Vehicular Access
The concept proposal TIA provided an overview of the proposed access driveway and the discussions
undertaken by TRAFFIX in consultation with the RMS. The access driveway that is proposed during
Stage 1 works is consistent with the master plan for the site with the only variance being the reduced
traffic generation as the car park operation will be primarily utilised during weekdays and will
accommodate a maximum of 68 parking spaces. In order to provide clarity and background, the
below overview is provided which summarises the access driveway location and discussions with
RMS.
Vehicular access to the new car park is proposed onto Gerard Street, approximately 38m to the west
of the Winnie Street Intersection, and 70m to the east of the Waters Road intersection. This access
location on Gerard Street has been selected for the following reasons:
Access options have being investigated from Winnie Street (directly opposite Parraween Street).
Although, it had been identified as a prohibited location under AS 2890.1, TRAFFIX reviewed the
potential to construct a public intersection (roundabout controlled). For various safety reasons and
road geometry constraints, this option was not considered acceptable or supportable. In addition to
the extensive compliance reasoning, North Sydney had also previously raised concern regarding
access via this intersection.
Monford Place was considered unsuitable for use due to its narrow width which permits one-way
flow only (with parking on both sides) and the fact that this cul-de-sac road primarily only
accommodates residential traffic.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 30
Having considered the above primary options and noting that the school must maintain the day to
day operation of the school during the various stages, the only remaining viable option for access
to the car park is via Gerard Street.
Figure 13: Proposed Access Location
Discussions have been held with RMS regarding the proposed new access driveway onto Gerard
Street, and RMS has advised that it is generally supportive of the proposed driveway, subject to the
following correspondence received from RMS Senior Land Use Planner, Angela Malloch on the 2nd
February 2015 which is also provided in Attachment 2.
“Roads and Maritime Services (Roads and Maritime) provides the following advice and information for
your review prior to lodging a formal application with the Department of Planning and Environment:
1) Roads and Maritime provides in-principle agreement to a vehicle access from Gerard Street.
At the meeting the restriction of movements to left in left out at this new access point were
discussed, however, due to the road corridor width, a median of sufficient width may not be
feasible and may impact on adjacent properties existing access. Roads and Maritime
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 31
suggested the applicant investigate lengthening the 'No Stopping' signs on Gerard Street to
allow a vehicle to pass a vehicle turning right into the site.
2) Roads and Maritime requires the proposed gate to the car park be located within the site to
allow for vehicles to queue within the property to reduce impact on through traffic on Gerard
Street.
3) Roads and Maritime suggested the applicant investigate the current pick up and drop off zones
to determine if the current provision is adequate to cater for the additional students and
additional facilities on site.
4) It is understood the existing exit (most eastern driveway) on Military Road will be closed in
stage 2, as a vehicular connection will be provided from Waters Road to the existing entry on
Military Road.
5) Roads and Maritime requested a Construction Traffic Management Plan be completed and a
Demolition Traffic Management Plan for all construction and demolition works, these
requirements may form part of the conditions of consent.
6) Roads and Maritime requested consideration be given to the relocation of the bus stop on
Military Road on the western boundary of the site to the eastern side of the entry (existing)
driveway. This would avoid students crossing the proposed new road through the site. “
In response, TRAFFIX NOW advises as follows:
Item 1 has been addressed and is provided in Attachment 3. The “No Stopping” restrictions will need
to be extended approximately 18 metres on the northern side of Gerard Street to permit vehicles to
pass right turning vehicles into the site. In addition, “No Stopping” restrictions will need to increase by
approximately 44 metres on the southern side of Gerard Street to allow safe sightlines to be provided
in accordance with AS 2890.1 (2004).
In relation to Item 2, the roller shutter door is to be located 18 metres within the property boundary
which provides queuing area for approximately 3 vehicles. This is more than sufficient for weekday
operation when only staff will utilise the car park during peak periods. At this stage weekend operation
of the car would be limited until such time that Stage 2 works (Sports Facilities) are completed. The car
park may be utilised to accommodate infrequent school events at weekends which are currently
accommodated on street.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 32
Item 3 requests the utilisation of the pick-up & drop-off areas has been reviewed and is discussed in
Section 3.4.1 and Section 11 Recommendations.
The internal vehicular link (as discussed in RMS Item 4) will now be provided in Stage 1 and this link
will service bus related trips only and infrequent servicing of the site (deliveries and waste collection) as
discussed in the RMS meeting. There are currently two access driveways located on Military Road
facilitating access to the existing visitor and staff car park. The most western driveway will be closed
and an amended eastern driveway will be maintained between Stage 1A and Stage 1D
accommodating approximately 11 parking spaces (the layout is discussed in Section 9).
RMS requested a Construction Traffic Management Plan be completed and a Demolition Traffic
Management Plan for all construction and demolition works. This is addressed in Section 7 of this
report with a high level overview of the traffic principles that will be adopted primarily relating to truck
access locations and the ability for vehicles to enter and exit in a forward direction. In addition, a
Preliminary Construction Management Plan has been prepared and submitted separately by TBH.
Item 6 requested consideration for the relocation of the bus stop to accommodate the exit access
driveway onto Military Road. It is considered that the bus stop be relocated to the west resulting in the
loss of 1-2 parking spaces. This however is an item for discussion with STA and liaison would be
required as to the most appropriate location during the Detailed Design CC stage.
4.3 General Vehicular & Pedestrian Access
An overview of the general vehicular and pedestrian access throughout all stages (including demolition
and operational stages) is provided in Attachment 4 of this report.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 33
5. Parking Requirements
5.1 Council Controls
North Sydney Development Control Plan ‘Section 10 Car Parking & Transport’ provides controls for car
parking and associated MAXIMUM parking rates for all land uses. In this regard, it is noted that Table
B-10-10.3 of Council’s DCP requires parking to be provided at a rate of 1 space per 6 staff for
‘Educational Establishments. As discussed within the masterplan concept traffic report, adoption of
this ‘generic’ parking rate should not be a mandatory requirement because the LEP rate does not
contemplate a situation where the development is an existing school with existing parking demands
and travel characteristics, which reflect established practices. Indeed, assessment based on RMS
Guidelines recommends surveys of these existing demands as the preferred methodology. Similarly,
the LEP does not therefore consider the adverse amenity impacts on local residents caused by on-
street parking demands and the benefits that may be available to local residents if this parking overspill
is dealt with on-site, as now proposed. Reference should be made to Section 3.5 of the concept
proposal report which summarises the existing parking demand of Redlands’ Senior Campus. This is
also summarised below in the merit parking assessment that has been undertaken.
5.2 Parking Assessment - Completion of Stage 1
A total of 68 parking spaces are provided upon completion of all Stage 1 works. As discussed in the
concept proposal TIA, this level of provision is supported for the following reasons:
The travel mode questionnaire undertaken for the concept proposal identified that a maximum
demand of 82 staff spaces are presently accommodated on-street at any one time on a typical
weekday, which should ideally be accommodated on-site within the proposed car park, even in the
absence of any redevelopment proposal. The proposed relocation of the current parking demand
to the on-site car park (Monday-Friday) will thus improve on-street parking conditions and provide a
direct benefit to the local community. In addition, the existing parking demand of 17 spaces on site
demonstrates an overall staff parking demand of 99 parking spaces.
With the above in mind, the provision of 68 parking spaces will satisfy a high proportion of the
existing parking demand on-site. The opportunity does exist to provide a proportion of parking
dedicated for staff who car share with other employees thereby assisting in reducing the use of
private vehicles upon completion of Stage 1. It is therefore recommended that 10 parking spaces
would be allocated for car-pooling and this represents approximately 15% of the total parking
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 34
provisions. Furthermore, it is proposed that upon completion of all Stage 1 works, 14 parking
spaces are allocated to visitor parking which seeks to reallocate the parking that is currently
provided on site and accessed via Military Road.
This approach is consistent with North Sydney Council’s DCP Quantity Requirements Objective to
ensure that sufficient car parking is provided on site for the users of the development, taking into
account the travel mode characteristics of the site.
There are additional benefits associated with providing 68 parking spaces in Stage 1, this primary
consideration being forward planning and the ability for this car park to satisfy the Stage 2
proposed works (discussed in the concept proposal TIA). These works will result in the provision
of a sports hall will accommodate a total of four (4) courts (for netball and basketball) and two (2)
tennis courts. Application of the above recreational facility parking requirement (1 space per
100m2) to the sports facility GFA of 6,906m2 results in a maximum parking requirement of 69
parking spaces based on Council’s DCP. In response, it is proposed that the parking layout
provide 68 parking spaces (upon the completion of Stage 1) and in compliance with Council
controls.
In summary, the parking demands associated with the existing Redlands’ Senior Campus weekday
operation will be largely allocated on site in the proposed car park (68 parking spaces) resulting in
significant improvements to the on street parking capacities in the locality. The provision of the car
park upon completion of Stage 1 also directly benefits the Stage 2 future work and would comply with
Council’s DCP ensuring that no adverse impacts are created during the weekend periods.
5.3 Stage 1 – Sub-stages & car park construction
As discussed above, the delivery of the car park will ultimately result in the provision of 68 parking
spaces however due to the intricacies associated with the construction methodology, the parking layout
will be delivered in two stages. These are
Stage 1C
Provision of interim car park layout with a total of 45 parking spaces including 2 disabled
parking spaces.
Stage 1D
Provision of interim car park layout with a total of 68 parking spaces including 2 disabled
parking spaces.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 35
The staged car park layout does not however affect the ultimate benefits associated with providing car
parking on site and provides direct benefits to the on-street parking capacities in the community which
will gradually improve upon the completion of Stages 1D and 1C.
5.4 Disabled Parking
North Sydney Council’s Parking DCP specifies a requirement of 1-2% of all non-residential parking
spaces to be designated for use by the disabled. Contrary to the above, Council’s Access DCP also
states that disabled spaces must be provided in accordance with Table D3.5 of the BCA and results in
a requirement of 1 space per 100 for a school.
Application of the accessible parking rate included in Council’s DCP suggests a single accessible
parking requirement within the new car park.
As shown in the reduced plans included as Attachment 1, the two accessible parking spaces that are
provided are generally designed in accordance with the requirements of AS2890.6 with minimum 2.4m
wide parking spaces and 2.4m wide adjacent shared zones. An assessment of the architectural plans
indicates that the parking layout for the disabled spaces accommodates a 7.6m width and therefore is
fully capable of accommodating the necessary 7.2m width to comply with AS 2890.6 (2.4m space,
2.4m shared area and 2.4m space). This can be readily addressed in response to a suitable condition
of consent.
These spaces are located within close proximity to the car park lift core for ease of access. A
minimum of 2.5m headroom will be required over the parking spaces and adjacent clear zones. The
path of vehicular travel from the car park entrance to the accessible parking spaces and from those
spaces to the car park exit will be required to have a minimum headroom of 2.2m.
It is envisaged that any detailed design matters relating to the accessible parking spaces can be
addressed and finalised at construction certificate stage. Nonetheless, the provision of 2 parking
spaces complies with Council’s DCP.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 36
5.5 Bicycle Parking
Council’s DCP does not specify bicycle parking requirements for a secondary school. It does refer to
Tertiary Educational Institution which requires minimums of 1 per 10 staff and 1 space per 10 students.
The DCP specifically states for ‘Other’ types of development that “On merit”, Council will give
consideration to the rates contained within the Planning guidelines for walking and cycling 2004 which
requires:
Long Term Use: 3-5% Staff (5-8 spaces)
Short Term Use: 5-10% Staff (8-16 spaces)
With regard for the above, the school would require between 13-24 bicycle parking spaces. In
response, the development provides 15 bicycle parking spaces within the basement car park suitable
for use by staff.
5.6 Motorcycle Parking
Motorcycle parking is required to be provided at a “minimum” rate of 1 space per 10 cars or part
thereof. This requires 7 motorcycle parking spaces based on the Stage 1 provision of 68 spaces.
Council’s DCP also requires the motorcycle spaces to be designed with minimum dimension of 1.2m x
3m opposed to AS 2890.1 design requirement of 1.2m x 2.5m. These spatial requirements have been
provided within the car park for the ultimate scenario.
The development proposes a total of 7 motorcycle parking spaces which complies with Council’s
minimum DCP requirements.
5.7 Servicing
The existing service access points have been discussed in Section 2.2. It is reiterated all waste
collection currently occurs on site with access from Gerrard Street. This access and servicing
provision will be maintained until the delivery of the internal site through link (Stage 1E). Upon
completion of Stage 1E, the waste collection vehicle (and associated delivery vehicles) will access via
Waters Road and exit onto Military Road.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 37
Finally, it is highlighted that the existing car park currently accessed via Military Road will be modified
to provide a single access driveway and approximately 11 parking spaces. This area will continue to
be capable of accommodating small vans (B99 design vehicles) as per the current parking
arrangements and until such time that the through site link is constructed.
5.8 Minibuses
It is proposed (as documented in the masterplan concept report), that the school’s minibus fleet will
ultimately be stored and loaded within the site’s through link located on the western site boundary.
This through link will be delivered in Stage 1E. An interim management plan is proposed until such
time, with three buses to be maintained within the Adams Centre site and the remaining buses to be
stored within the junior school campus.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 38
6. Traffic Impacts
6.1 Trip Generation
6.1.1 Introduction
The Stage 1 works will not result in additional traffic generation during weekday operation, rather the
redistribution of traffic in the locality to the proposed car park. That is to say, the school is an existing
development which currently accommodates the traffic associated with 920 students and 150 staff on
the external road network.
The school has advised as part of the masterplan concept proposal (Stage 1 - Stage 5), there is
potential for the student numbers to increase by 30 students and staff numbers to increase by 10
people. This is unlikely to occur within Stage 1 works. Section 6.12 provides an overview of the
estimated traffic generation increase associated with the above and is a worst case assessment.
6.1.2 Weekday
As discussed in the masterplan concept traffic report, the development will generate an additional 12
vehicle arrivals in the AM peak with 6 vehicle arrivals associated with student drop off and 6 vehicle
trips associated with staff arrivals. Furthermore, 10 vehicle departures will be generated during the
peak afternoon period with 4 vehicle trips being student pick up and 6 trips associated with staff
departures.
The trips associated with students must however be factored to account for pick-up or drop-off
movements. In this case, the school is not the end destination of the driver (parent) and therefore the
impact upon the external road network would be doubled. This is referred to as a linked trip. It must
also be acknowledged that the proposed volumes occur over the school peaks which range from 6-
9am and 2-4pm. The impact of the above mentioned traffic volumes has been summarised below
based on the findings of the questionnaire travel mode surveys
Staff Peaks
AM peak (6-9am) with 73% of staff arriving between 7-8 am
PM Peak (3-6pm) with 53% of staff departing between 4-5 pm
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 39
Student Peaks
AM peak (7-9am) with 61% of students arriving between 8-9am
PM Peak (3-6pm) with 85% of students departing between 3-4pm
In this regard, the following volumes represent the additional vehicle movements taking into account
linked trips and the peak splits that will occur on the external road network. The results are
summarised in Table 3 and Table 4.
Table 3: Proposed Morning Hourly Volumes: Weekday
Period
In
Veh/hr
Out
Veh/hr
Total
Veh/hr
6-7am 1 0 1
7-8am 11 6 17
8-9am 11 11 22
Total 23 17 40
Table 4: Proposed Evening Hourly Volumes: Weekday
Period
In
Veh/hr
Out
Veh/hr
Total
Veh/hr
3-4pm 9 9 18
4-5pm 1 4 5
5-6pm 0 2 2
Total 10 15 25
Table 3 identifies that the peak AM period occurs between 8-9am and results in an additional traffic
generation of 22 veh/hr. Table 4 indicates that the peak PM period will occur from 3-4pm generating
an additional 18 veh/hr over and above the existing development traffic generation. It is highly
noteworthy also that the PM peak occurs outside of the external road network peak experienced
between 5-6pm.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 40
The above volumes are not significant and will have a negligible impact on the external road network.
In fact, if all 22 veh/hr during the AM peak or 18 veh/hr during the PM peak were distributed to a single
intersection, there would be a minimal impact noting that this would represent very minor increase over
and above existing traffic volumes. Indeed, taking into consideration the various arrival and departure
routes that are available, the additional impacts will be further minimised through the dispersion of
traffic surrounding the site. Finally, it is highly noteworthy that school has historically accommodated
over 1,000 students which has reduced over the past years. The increased student population that is
now proposed will not exceed the previous peaks which have been previously fully accommodated by
the surrounding road network.
In summary, the additional impacts of Redlands’ Senior Campus redevelopment are minor and will
have little measurable impact on the external road network.
6.1.3 Bus Related Trips
Access to the site’s through link will be appropriately managed for general use by the school’s mini bus
fleet per week. Anticipated volumes are as expected to reach a maximum of:
AM peak (8-9am): 6 veh/hr primarily associated with Redland’s Senior Campus mini-buses
departing for extracurricular activities.
PM Peak (3-4pm): 12 veh/hr (worst case associated with school mini fleet buses and Thursday use
of 65 seater buses (14.5m Buses).
The through link will be capable of accommodating larger buses (14.5m or 65 seater) and these are
generally only required on Thursdays for transportation of students to external sporting facilities. The
buses are generally used to transport students to external sporting venues however with the proposed
redevelopment of the entire site and provision of the Sports and Performing Arts Centre, the school’s
reliance upon the minibuses will reduce over time and be utilised for general excursions.
In addition to the above, the infrequent attendance of waste collection vehicles (5 times per week) and
general deliveries (1-2) times per day will ensure that the through site link will remain a low volume
thoroughfare utilised only by service vehicles and buses. This will be appropriately managed by the
school and it is anticipated that a Management Plan would be developed as part of a suitable condition
of consent to ensure efficient operation of the thoroughfare and that only authorised vehicles are
provided with access.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 41
7. Construction Traffic Management
A detailed Construction Traffic Management Plan (CTMP) for Stage 1 works will be prepared (and
submitted to Council) separate to this Development Application. At this stage, a Preliminary
Construction Management Plan has been prepared by TBH and has been submitted separately.
The below commentary addresses the overall management principles for the site during the
construction process. It is noted that the preparation of a detailed CTMP report would require
significant input from the appointed builder and would heavily rely upon the construction methodology
which at this point cannot be confirmed. The proposed development would however adhere to the
general CTMP principles that are provided below for information purposes:
Truck routes
The truck routes to and from the site are provided in Figure 14 below. These truck routes would be
utilised for the construction of the proposed development (Stage 1A – Stage 1D) and seek to utilise the
arterial road network where possible. A copy of these routes would be provided to all drivers prior to
attending the site and all trucks servicing the site will do so via the following routes. The proposed
truck routes are recommended so that all vehicles could access the site in a forward direction and
likewise the vehicle could also exit the site in a forward direction. These truck routes are therefore
recommended to ensure that no reverse manoeuvres occur on the public roadway and along Gerard
Street, a classified arterial road.
With regard for the access locations identified in the Preliminary Construction Management Plan
(prepared by TBH), a swept path analysis assessment has been undertaken demonstrating forward
entry and forward exit manoeuvres with all reverse manoeuvres to occur on site. This swept path
analysis is provided in Attachment 5. The access locations are summarised below in Figure 15-17.
At this stage, it is unclear if access to the site at Stage 1d (Figure 17) will be feasible and a temporary
works zone may be required outside the hours of clearway operation. This will be addressed during
the preparation of the detail CTMP report.
Finally, Stage 1E will result in the delivery of the site through link and the demolition of the cottages
which are located along the western site boundary. It is anticipated that the initial site establishment
and demolition works may necessitate a short term works zone on Waters Road and this would be
addressed during the preparation of the detailed CTMP report. Upon completion of the demolition, all
trucks will utilise the site through link, with all vehicles entering and exiting in a forward direction.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 42
Truck Size and Volumes
The maximum size of vehicles and frequency of construction delivery vehicles will be documented in
the detailed CTMP report however it is anticipated that a maximum vehicle size of 12.5m HRV is
generally feasible as demonstrated in the swept path analysis provided in Attachment 5. The
anticipated truck volumes are estimated and discussed in the Preliminary Construction Management
Plan.
Contractor parking
Contractors will be encouraged to either use public transport or ride share to / from the site noting that
the delivery of the car park interim layouts (Stage 1C & Stage 1D) would allow a small proportion of
construction employee vehicles to park on site. This parking would of course be restricted for
construction employees who car pool to reduce the impact and this can be further detailed subject to
the detailed CTMP which will be undertaken at CC stage.
Traffic Control Plans (If necessary)
Traffic Control Plans (TCP) will be designed in accordance with the RMS Traffic Control at Worksites
Manual and AS 1742.3. The TCP’s would primarily relate pedestrian control to ensure appropriate
safety measures are implemented.
Swept Path Analysis
Swept Path Analysis has been undertaken for each construction stage and is provided in Attachment 5
(as discussed above) demonstrating forward entry and exit during all construction stages. All entry and
exit movements will be monitored by certified traffic controllers.
Accordingly, it is anticipated that a standard condition of consent would be imposed requiring a site
specific CTMP be provided for this development application. The CTMP will be designed in
accordance with the above principles and the draft CTMP would be issued to Council at a later stage
for consideration and review.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 43
Figure 14: Truck Routes – To/From the Site
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 44
Figure 15: Stage 1A Construction Vehiuclar Access
Figure 16: Stage 1B – 1C General Construction Vehicluar Access
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 45
Figure 17: Stage 1D General Construction- Access or Work Zone
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 46
8. DGR Assessment and Compliance
Section 5 of the Director General’s Environmental Assessment provided a number of considerations in
relation to traffic and transport to be addressed within the concept proposal traffic report. The following
DGR Assessment & Compliance Table is provided confirming that all conditions have been addressed
in the report and providing a summary of the relevant responses in relation to specific traffic matters.
Table 5: Stage 1 DA - DGR Requirements
Item Section Compliance
(Y/N)
Comments
First Stage Construction
Detail construction access
arrangements and measures to
mitigate any associated pedestrian,
cycle, public transport or traffic
impacts.
Section 7 Y
A high level overview of the
construction principles are
provided in Section 7. In addition
the preliminary CTMP report has
been separately provided by TBH.
Details regarding car parking
arrangements during construction,
including the displacement of visitor
and staff car parking. Alternative
parking arrangements (on or off
site) should be made for staff and
construction workers.
Section 7 Y As noted above.
First Stage Operational
Detail proposed first stage
operational access arrangements
and measures to mitigate any
associated traffic impacts and
impacts on public transport,
pedestrian and cycle networks
Section 4.3 Y An overview is provided in
Attachment D as discussed in
Section 4.3.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 47
Demonstrate the provision of
appropriate on-site car parking and
pickup and drop-off facilities, having
regard to the availability of public
transport and compliance with
requirements of relevant car
parking codes and Australian
Standards (i.e. turn paths, sign
distance requirements, aisle widths,
etc).
Section 5 Y Refer to Section 5 for overview of
parking assessment.
Refer to Section 9 for compliance
with Australian Standards.
Details of delivery, servicing and
loading arrangements.
Section 5.5 Y All servicing will be
accommodated on site with all
waste vehicles access via the
existing access onto Gerard
Street. As noted in Section 5.5,
the delivery of the through site
link at Stage 1E will enable all
waste collection and delivery
vehicles to be continue to be
accommodated on site.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 48
9. Access & Internal Design
9.1 Access
The proposed development requires a Category 3 Access Driveway with consideration for the ultimate
master plan car park layout to accommodate between 101-300 parking spaces and User Class 2 type
parking (sports facilities/medium term parking). A Category 3 Access Driveway in turn requires the
following dimensions:
6.0 metre entry width
4.0 – 6.0 metre exit width and
Separation of driveways for 1.0-3.0 metres
In our view, a 4.0 metre entry and exit width separated by a 2 metre median is suitable for adoption
noting that a swept path analysis assessment has been undertaken demonstrating that entering
movements can occur from the nearside lane and therefore the intent of the standard is met. In
summary, the design complies with the requirements of AS 2890.1 (2004) and will ensure satisfactory
operation.
9.2 Internal Design Aspects
The car park layout as shown in the reduced plans included as Appendix B has been developed based
upon the requirements of the relevant standards and guidelines, as outlined in the following sections.
9.2.1 Parking Modules
Parking spaces are generally 2.5m wide and 5.4m long, in accordance with the dimensional
requirements for a medium turnover parking facility (User Class 2) under AS 2890.1.
Parking aisle widths of minimum 5.8m are provided which complies with the minimum
requirement under AS 2890.1.
Dead-end aisles are provided with the required 1.0m aisle extension in accordance with Figure 2.3
of AS2890.1.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 49
Disabled parking spaces are designed in accordance with AS2890.6. As discussed in Section
5.2, the necessary 2.4m parking space and located adjacent to a minimum shared area of 2.4m
can be provided.
The position of columns complies with the required design envelope as shown in Figure 5.2 of
AS2890.1 (generally 750mm – 1750mm from the open end of the parking bays).
9.2.2 Ramps
The ramp providing access to the car park level has a maximum gradient of 1:8 with transitions at
the top and bottom, to meet the requirements of AS2890.1.
A maximum grade of 1:20 is to be provided for a distance of 18m inside the property boundary.
9.2.3 Clear Head Heights
A minimum clear head height of 2.2m is to be provided for all areas within the basement car park,
as required under AS2890.1.
A clear head height of 2.5m is to be provided above the disabled parking spaces and adjacent
shared zones, as required under AS2890.6.
9.2.4 Other Considerations
Appropriate visual splays are provided in accordance with the requirements of Figure 3.3 of
AS2890.1 at the access driveway.
9.2.5 Through Site Link (Stage 1E)
A 6.6m driveway width (at the Waters Road boundary) is provided and is splayed externally to
provide a 7.4 m width. This width is necessary to facilitate the spatial requirements of a 14.5m
bus which will attend the site intermittently for excursions and visiting schools.
The curvature of the roadway requires extensive spatial requirements. Upon entry (from Waters
Road), the following cross section is generally required to accommodate a 14.5m bus and in
order for the vehicle to negotiate the road curvature:
300mm kerb
6.5 road width
300mm kerb and
1.2m footpath.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 50
The road cross section required to accommodate parking for four mini bus vehicles necessitates
the following:
300mm kerb
3.5m road width
3.0m parking aisle suitable for access by School Mini Bus
300mm Kerb &
1.2m footpath
Visual splays of 2.5mX2.0m are provided on both sides of the driveway to ensure safe sightlines
towards pedestrians.
A 4.8m driveway width (at the Military Road boundary) which is required to be splayed externally
to a 7.8 m width is provided to accommodate exiting manoeuvres for the largest vehicle that will
access the sites through link.
The exit driveway on Military Road will require the relocation of the existing bus stop for approx. 3-
4 metres. The existing bus stop is provided with an approximate 27m length and by relocating
and maintain this facility, it will result in the loss of one (1) on street parking space.
Swept Path Analysis has been undertaken for the largest vehicle required to access the site’s
through link and is provided in Attachment 6.
9.2.6 Temporary Visitor Car Park (Military Road)
It is highlighted that the existing car park currently accessed via Military Road will be modified with a
single access driveway and approximately 11 parking spaces (refer to Figure 18 below). This area will
continue to be capable of accommodating small vans (B99 design vehicles) as per the current parking
arrangements until such time that the parking can be relocated to the basement car park accessed via
Gerard Street (Stage 1C). The layout has been designed in accordance with AS 2890.1 (2004).
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 51
Figure 18: Ammend Visitor Car-park Layout -Military Road (Temporary)
9.2.7 Internal Design Summary
In summary, the internal configuration of the basement car park and site’s through link has been
designed generally in accordance with the requirements of AS 2890.1, AS 2890.2, and AS 2890.6. It is
however envisaged that any minor amendments considered necessary (if any) can be dealt with as a
condition of consent for the requisite Staged DA, or prior to the release of a construction certificate.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 52
10. Recommendations
The following recommendations have been identified and advised as part of the masterplan concept
report prepared by TRAFFIX. As previously highlighted, these are provided in order to improve the
efficiency of existing systems in place and reduce the ultimate parking demand of the existing
development which is currently accommodated on street. They are as follows:
It is clear from the parking surveys undertaken and on site observations that the Winnie street
(south) pick-up drop-off facility (5 spaces) is not adequately utilised. It is recommended that
parents are re-informed in relation to the dedicated areas for school use during these peak
periods. This is in line with the recommendation outlined in the Lyle Marshall & Associates report
which recommended a “Traffic Management Policy” document be prepared identifying signage
and time restrictions of each zone to inform parents.
Staff members to monitor zones and ensure time limits (2-5minute parking) are not exceeded.
The travel mode questionnaire survey undertaken identified a demonstrated demand for drop
off at Hampden Avenue. Although it is not relied upon, it is recommended that a formal pick up,
drop off area be provided on the western side of Hampden Avenue in order to provide a safe pick
up and drop off facility. This would ideally provide 5 parking spaces with a 2 minute time limit
during school peak periods. This is of course provided for information purposes and discussion
with Council and would enhance the dispersion of traffic surrounding the site rather than the
concentration of traffic on streets such as Winnie Street, Gerard Street and Waters Road.
The new car park will provide a direct benefit to the parking amenity in the locality removing the
existing demand of staff vehicles that are parked on-street. The car park will accommodate 68
parking spaces in Stage 1 and 115 parking spaces as part of the masterplan for the subject site.
This will suitably improve conditions during a typical weekday and maintain conditions on a typical
Saturday.
The provision of a site through link will ensure that the development can store the school mini-
bus vehicles internally. The through link will also accommodate waste collection vehicles and
ensure forward entry and forward exit manoeuvres. Finally, the delivery of this facility will
accommodate the storage of visiting 14.5m buses which are currently accommodated on-street.
It is recommended that in addition to the ‘Traffic Management Policy’ for parent information, a
Workplace Travel Plan (WTP) be developed for staff. The implementation of a car pooling
scheme could ultimately reduce the impact of private vehicle use.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 53
11. Conclusions
In summary:
11.1 Context
This application seeks consent for a detailed proposal for the first stage development referred to as
“Stage 1 New Learning Hub”. The associated works include Demolition of existing buildings and
structures, Fit-out of 7 and 8 Monford Pl for temporary use as an educational facility and the
construction of a new purpose built music and education building.
From a traffic perspective, the application will result in the creation of new vehicular access road off
Gerard Street for the new basement car park and a new internal vehicular access link facilitating
ingress from Waters Rd and egress onto Military Rd. As documented in this report, the internal site
link will accommodate buses and service vehicles only and is a low traffic volume thoroughfare that
will be appropriately managed to limit access.
The proposed modifications are generally intended to cater more safely and efficiently for the
requirements of the school, than the current facilities.
11.2 Parking Assessment
It is proposed that a total of 68 parking spaces are provided upon completion of all Stage 1 works.
The parking demands associated with the existing Redlands’ Senior Campus weekday operation
will be largely allocated on site in the proposed car park (68 parking spaces) resulting in significant
improvements to the on street parking capacities in the locality. Furthermore, the provision of the
car park upon completion of Stage 1 also directly benefits the Stage 2 future work and would
comply with Council’s DCP ensuring that no adverse impacts are created during the weekend
periods.
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 54
11.3 Access & Internal Design
The car park access has been discussed with RMS and is supported in principle by RMS, noting
that the analysis provided herein demonstrates a very satisfactory outcome.
All access locations and internal design or the proposed car parks have been reviewed and it is
confirmed that the layouts generally comply with both AS 2890.1 (2004), AS 2890.2 (2002) and AS
2890.6 (2009). It is however envisaged that any minor amendments considered necessary (if any)
can be dealt with as a condition of consent for the requisite Staged DA, or prior to the release of a
construction certificate.
11.4 Traffic Assessment Summary
To summarise, the following findings and outcomes have been derived from the traffic assessment for
weekday operation. The following proposed weekday development and hourly flows have been
estimated based on current travel behaviour of the existing Redlands’ Senior Campus. They are
associated with a maximum increase of 30 students and 10 staff members and assume a worst case
scenario with reference to Stage 1 works. That is to say, that the proposed works will generally relate
to the redistribution of the existing staff and student population and the delivery of the improved
learning facilities on site.
Table 6: Proposed Morning Hourly Volumes: Weekday
Period
In
Veh/hr
Out
Veh/hr
Total
Veh/hr
6-7am 1 0 1
7-8am 11 6 17
8-9am 11 11 22
Total 23 17 40
Table 7: Proposed Evening Hourly Volumes: Weekday
Period
In
Veh/hr
Out
Veh/hr
Total
Veh/hr
3-4pm 9 9 18
4-5pm 1 4 5
5-6pm 0 2 2
Total 10 15 25
14.397r01v3 TRAFFIX SCECGS Redlands, Cremorne, Stage 1 Development Application 55
A modelling assessment of the above mentioned flows is not warranted based on the low
nature of the volumes and the various arrival departure routes that exist surrounding the site.
In conclusion, it can be said that the proposed modifications are intended to largely cater more
efficiently and more safely for the existing requirements of the college. It is expected that the car park
will generally cater for traffic that is currently experienced by the school during the typical weekday
(with only very minor increases in staff and student numbers as part of the masterplan), and most
significantly the current parking demands of the school are accommodated in the local streets
surrounding the college due to a limited parking supply within the site itself.
In summary, the impacts of the proposal on the surrounding road network are generally expected to be
positive with a minor increase in traffic (worst case) that can be fully accommodated by the external
road network during weekend periods.
11.5 Construction Traffic Management
A Preliminary Construction Management Plan has been prepared by TBH and has been submitted
separately to this traffic report. An overview of the management principles to be adopted for the site
during the construction process have been provided in the subject report noting that all truck access
onto Gerard Street will be required to enter and exit in a forward direction. This has been
demonstrated in the swept path analysis assessment undertaken.
11.6 Conclusion
On the basis of the above, it is concluded that the development application for Stage 1 works is
supportable on traffic planning grounds, and should be approved from a traffic perspective.
.
Attachment 1
Reduced Plans
MIL
ITAR
YR
OAD
GER
ARD
STR
EET
WATE
RSROAD
WINNIE STREET
MURDOCHSTREET
HAMPDENAVENUE
NEW
LEAR
NIN
GH
UB
3001 1
3002
1
MONFORD PLACE
SUBJ
ECT
TO S
EPAR
ATE
APPL
ICAT
ION
SUBJ
ECT
TO S
EPAR
ATE
APPL
ICAT
ION
NEW
OPE
N S
PAC
E W
ITH
UN
DER
GR
OU
ND
CAR
PAR
KAN
D M
USI
C F
ACU
LTY
NEW
INTE
RN
ALD
RIV
EWAY
PO B
ox 6
60 D
arlin
ghur
st N
SW 1
300
Aust
ralia
Leve
l 1, 1
9 Fo
ster
Stre
et, S
urry
Hills
NSW
201
0 Au
stra
lia
Tann
er K
ibbl
e De
nton
Arc
hite
cts
Pty
Ltd
ww
w.tk
da.c
om.a
u
Rev
D
ate
Des
crip
tion
Che
cked
Au
th.
LEG
END
CLI
ENT
T +6
1 2
9968
980
2F
+61
2 99
09 3
228
Urbi
sTO
WN
PLA
NN
ING
T +6
1 2
8233
990
0
TTW
STR
UC
TUR
AL &
CIV
IL
T +6
1 2
9439
728
8F
+61
2 94
39 3
146
Stee
nsen
Var
min
gES
D, E
LEC
TRIC
AL &
MEC
HAN
ICAL
T +6
1 2
9967
220
0
Wilk
inso
n M
urra
yAC
OU
STIC
T +6
1 2
9437
461
1
Insy
nc S
ervi
ces
HYD
RAU
LIC
T +6
1 92
62 3
400
Dra
win
g N
o.
Rev
isio
n
Proj
ect
Dra
win
g Ti
tle
Proj
. Dir
Proj
. Arc
h
Dra
wn
Job
No.
Dat
e
Sca
le
RD
VC MAY
15
N
NSW
Nom
inat
ed A
rchi
tect
s:R
ober
t Den
ton
R
eg. N
o. 5
782
Alex
Kib
ble
R
eg. N
o. 6
015
Do
not s
cale
dra
win
gs. V
erify
all
dim
ensi
ons
on s
ite. N
otify
arc
hite
ct o
f all
disc
repa
ncie
s
T +
61 2
928
1 43
99F
+61
2 9
281
4337
Traf
fixTR
AFFI
C
T +6
1 83
24 8
700
Silk
Con
sulti
ng L
ands
cape
Arc
hite
cts
LAN
DSC
APE
T +6
1 2
9966
196
0
Ride
r Lev
ett B
uckn
all
QU
ANTI
TY S
UR
VEYO
R
T +6
1 2
9922
227
7
RED
LAN
DS
SEN
IOR
CAM
PUS
STAG
E 1
BUIL
DIN
GM
ON
FOR
D P
LAC
E LE
ARN
ING
HU
B
Redl
ands
Sand
rick
Proj
ect D
irect
ions
/Bl
oom
park
Con
sulti
ng
PRO
JEC
T M
ANAG
ER
T +6
1 2
8860
949
4 / +
61 2
995
7 14
73
A
1 :
500
@ A
1
AR-D
A-
1411
11
0000
VC
CO
VER
SH
EET
& SI
TE P
LAN
RED
LAN
DS
SEN
IOR
CAM
PUS
STAG
E 1
BUIL
DIN
GM
ON
FOR
D P
LAC
E LE
ARN
ING
HU
BR
EDLA
ND
S
272
MIL
ITAR
Y R
OAD
, CR
EMO
RN
E N
SW
AR.D
A.00
00C
OVE
R S
HEE
T &
SITE
PLA
N
AR.D
A.10
01LE
VEL
1 D
EMO
LITI
ON
PLA
N N
OR
THAR
.DA.
1002
LEVE
L 1
DEM
OLI
TIO
N P
LAN
SO
UTH
AR.D
A.10
03LE
VEL
2 D
EMO
LITI
ON
PLA
N N
OR
THAR
.DA.
1004
LEVE
L 2
DEM
OLI
TIO
N P
LAN
SO
UTH
AR.D
A.10
05R
OO
F D
EMO
LITI
ON
PLA
N
AR.D
A.11
01ST
AGE
1 SU
B ST
AGIN
G D
IAG
RAM
S 1
AR.D
A.11
02ST
AGE
1 SU
B ST
AGIN
G D
IAG
RAM
S 2
AR.D
A.20
01BA
SEM
ENT
LEVE
L PL
ANAR
.DA.
2002
LEVE
L 1
FLO
OR
PLA
N N
OR
THAR
.DA.
2003
LEVE
L 1
FLO
OR
PLA
N S
OU
THAR
.DA.
2004
LEVE
L 2
FLO
OR
PLA
NAR
.DA.
2005
LEVE
L 3
FLO
OR
PLA
NAR
.DA.
2006
LEVE
L 4
FLO
OR
PLA
NAR
.DA.
2007
ACC
ESSI
BLE
RO
OF
PLAN
AR.D
A.20
08R
OO
F LE
VEL
PLAN
AR.D
A.20
31EX
ISTI
NG
AN
D D
EMO
LITI
ON
IN 7
& 8
MO
NFO
RD
PLA
CE
AR.D
A.20
32IN
TER
IM W
OR
KS IN
7 &
8 M
ON
FOR
D P
LAC
EAR
.DA.
2041
DEM
OU
NTA
BLE
CLA
SSR
OO
MS
- STA
GE
1A T
O 1
BAR
.DA.
2042
DEM
OU
NTA
BLE
CLA
SSR
OO
MS
- STA
GE
1CAR
.DA.
2051
BASE
MEN
T LE
VEL
PLAN
- IN
TER
IM M
USI
C S
TAG
E 1B
AR.D
A.30
01EL
EVAT
ION
S SH
EET
01AR
.DA.
3002
ELEV
ATIO
NS
SHEE
T 02
AR.D
A.30
03EL
EVAT
ION
S SH
EET
03AR
.DA.
3004
ELEV
ATIO
NS
SHEE
T 04
AR.D
A.30
05EL
EVAT
ION
S SH
EET
05AR
.DA.
3031
ELEV
ATIO
NS
SHEE
T 06
- 7
& 8
MO
NFO
RD
PLA
CE
AR.D
A.31
01SE
CTI
ON
S SH
EET
01AR
.DA.
3102
SEC
TIO
NS
SHEE
T 02
AR.D
A.31
31SE
CTI
ON
S SH
EET
03 -
7 &
8 M
ON
FOR
D P
LAC
E
DR
AWIN
G L
IST
1 :
500
SITE
PLA
N1
A13
/05/
15Is
sued
for S
SDA
ToA
AKR
D
(E) D
ESIG
N &
TEC
HN
OLO
GY
CO
TTAG
E TO
BE
DEM
OLI
SHED
(E) D
ESIG
N &
TEC
HN
OLO
GY
CO
TTAG
E TO
BE
DEM
OLI
SHED
(E) T
REE
S TO
BE R
EMO
VED
(E) T
REE
S TO
BE
REM
OVE
D
(E) B
/BLO
CK
CO
TTAG
E TO
BE
DEM
OLI
SHED
(E) K
IOSK
SU
BSTA
TIO
NTO
BE
REL
OC
ATED
.SU
BJEC
T TO
AU
SGR
IDAP
PRO
VAL.
JOIN
S AR
-DD
-100
2
(E) M
OW
LLBU
ILD
ING
TO
BE
DEM
OLI
SHED
(E) O
FFIC
E, S
TAIR
SAN
D D
RAM
A ST
OR
AGE
TO B
E D
EMO
LISH
ED
(E) L
IFT
TO B
ER
ETAI
NED
DU
RIN
GST
AGE
1CC
ON
STR
UC
TIO
N; T
OBE
DEM
OLI
SHED
AT
CO
MPL
ETIO
N O
F N
EWLE
ARN
ING
HU
B
(E) B
UIL
DIN
G 7
MO
NFO
RD
PLAC
E TO
BE
DEM
OLI
SHED
(E) B
UIL
DIN
G 8
MO
NFO
RD
PLAC
E TO
BE
DEM
OLI
SHED
(E) G
ARAG
E TO
BE D
EMO
LISH
ED
(E) R
ETAI
NIN
GW
ALL
AND
STAI
RS
TO B
ED
EMO
LISH
ED
(E) R
OLL
ERSH
UTT
ERD
OO
RS
TOBE
REM
OVE
D
(E) W
ALLS
,TR
EES
AND
STR
UC
TUR
ES T
OBE
DEM
OLI
SHED (E
) DR
AMA
(E) T
OIL
ETS
(E) L
ANG
GYM
(E) C
ANTE
EN
(E) C
LASS
RO
OM
(E) C
LASS
RO
OM
(E) O
FFIC
E
(E) O
FFIC
E(E
)O
FFIC
E
(E) C
LASS
RO
OM
(E) U
ND
ERC
RO
FT
(E)
CLA
SSR
OO
M(E
)C
LASS
RO
OM
(E) C
LASS
RO
OM
(E)
CLA
SSR
OO
M (E) S
TAFF
(E) C
LASS
RO
OM
(E) C
LASS
RO
OM
(E) T
OIL
ETS
(E)
CLA
SSR
OO
M
(E)
CLA
SSR
OO
M
FAC
ILIT
IES
BUIL
DIN
GN
o. 6
WIN
NIE
STR
EET
WATE
RSROAD
GER
ARD
STR
EET
(E) H
OU
SEN
o. 1
3 G
ERAR
D S
TREE
T
(E) A
PAR
TMEN
TSN
o. 8
-12
WIN
NIE
STR
EET
(E) A
PAR
TMEN
TSN
o. 8
-12
WIN
NIE
STR
EET
(E) H
OU
SEN
o. 1
5 G
ERAR
DST
REE
T
(E) A
PAR
TMEN
TSN
o. 1
9 W
ATER
S R
OAD
(E) B
ASKE
TBAL
LC
OU
RT
(E) M
USI
CC
OTT
AGE
W/B
LOC
K TO
BE
DEM
OLI
SHED
(E) V
ISU
AL A
RT
CO
TTAG
EV/
BLO
CK
TO B
ED
EMO
LISH
ED
(E) C
OTT
AGE
X/BL
OC
K TO
BE
DEM
OLI
SHED
(E) M
USI
CC
OTT
AGE
Y/BL
OC
K TO
BE
DEM
OLI
SHED
(E) F
ACIL
ITIE
SC
OTT
AGE
Z/BL
OC
K TO
BE
DEM
OLI
SHED
(E) G
ARD
ENBE
DS
AND
OU
TDO
OR
PLA
YAR
EA T
O B
ED
EMO
LISH
ED
(E) L
IGH
T PO
LETO
BE
REL
OC
ATED
(E) T
REE
SW
ITH
IN T
HE
SITE
TO
BE
REM
OVE
D
SUBJ
ECT
TO S
EPAR
ATE
APPL
ICAT
ION
EXIS
TIN
G R
OO
MS
EXIS
TIN
G W
ALLS
DEM
OLI
TIO
N
PO B
ox 6
60 D
arlin
ghur
st N
SW 1
300
Aust
ralia
Leve
l 1, 1
9 Fo
ster
Stre
et, S
urry
Hills
NSW
201
0 Au
stra
lia
Tann
er K
ibbl
e De
nton
Arc
hite
cts
Pty
Ltd
ww
w.tk
da.c
om.a
u
Rev
D
ate
Des
crip
tion
Che
cked
Au
th.
LEG
END
CLI
ENT
T +6
1 2
9968
980
2F
+61
2 99
09 3
228
Urbi
sTO
WN
PLA
NN
ING
T +6
1 2
8233
990
0
TTW
STR
UC
TUR
AL &
CIV
IL
T +6
1 2
9439
728
8F
+61
2 94
39 3
146
Stee
nsen
Var
min
gES
D, E
LEC
TRIC
AL &
MEC
HAN
ICAL
T +6
1 2
9967
220
0
Wilk
inso
n M
urra
yAC
OU
STIC
T +6
1 2
9437
461
1
Insy
nc S
ervi
ces
HYD
RAU
LIC
T +6
1 92
62 3
400
Dra
win
g N
o.
Rev
isio
n
Proj
ect
Dra
win
g Ti
tle
Proj
. Dir
Proj
. Arc
h
Dra
wn
Job
No.
Dat
e
Sca
le
RD
VC MAY
15
N
NSW
Nom
inat
ed A
rchi
tect
s:R
ober
t Den
ton
R
eg. N
o. 5
782
Alex
Kib
ble
R
eg. N
o. 6
015
Do
not s
cale
dra
win
gs. V
erify
all
dim
ensi
ons
on s
ite. N
otify
arc
hite
ct o
f all
disc
repa
ncie
s
T +
61 2
928
1 43
99F
+61
2 9
281
4337
Traf
fixTR
AFFI
C
T +6
1 83
24 8
700
Silk
Con
sulti
ng L
ands
cape
Arc
hite
cts
LAN
DSC
APE
T +6
1 2
9966
196
0
Ride
r Lev
ett B
uckn
all
QU
ANTI
TY S
UR
VEYO
R
T +6
1 2
9922
227
7
RED
LAN
DS
SEN
IOR
CAM
PUS
STAG
E 1
BUIL
DIN
GM
ON
FOR
D P
LAC
E LE
ARN
ING
HU
B
Redl
ands
Sand
rick
Proj
ect D
irect
ions
/Bl
oom
park
Con
sulti
ng
PRO
JEC
T M
ANAG
ER
T +6
1 2
8860
949
4 / +
61 2
995
7 14
73
A
1 :
200
@ A
1
AR-D
A-
1411
11
1001
VC
LEVE
L 1
DEM
OLI
TIO
N P
LAN
NO
RTH
A13
/05/
15Is
sued
for S
SDA
ToA
AKR
D
(E) B
/BLO
CK
CO
TTAG
E TO
BE
DEM
OLI
SHED
(E) W
ALLS
AN
DST
RU
CTU
RES
TO
BE D
EMO
LISH
ED
(E) T
REE
S TO
BE
REM
OVE
D
(E) A
/BLO
CK
CO
TTAG
E TO
BE
DEM
OLI
SHED
(E) T
OIL
ETS
(E) O
FFIC
E
MIL
ITAR
YR
OAD
MONFORD PLACE
JOIN
S AR
-DD
-100
1
(E) E
XTER
NAL
PLA
YAR
EA
(E) B
ASKE
TBAL
LC
OU
RT
(E) L
ON
E O
AKBU
ILD
ING
(E)
REC
EPTI
ON
(E)
OFF
ICE
(E)
OFF
ICE
(E)
OFF
ICE
(E)
OFF
ICE
(E)
HAL
LWAY
(E) F
OU
ND
OFF
ICE
(E)
OFF
ICE
(E)
VER
AND
AH
(E) C
AR P
ARK
SUBJ
ECT
TO S
EPAR
ATE
APPL
ICAT
ION
(E) A
PAR
TMEN
TS6
MO
NFO
RD
PLAC
E
(E) A
PAR
TMEN
TS4
MO
NFO
RD
PLAC
E(E
) APA
RTM
ENTS
3 M
ON
FOR
DPL
ACE
(E) A
PAR
TMEN
TS5
MO
NFO
RD
PLAC
E
(E) A
PAR
TMEN
TS1
MO
NFO
RD
PLAC
E
(E) H
OU
SE 2
84B
MIL
ITAR
Y R
OAD
(E) H
OU
SE 2
86M
ILIT
ARY
RO
AD(E
) HO
USE
288
MIL
ITAR
YR
OAD
(E) H
OU
SE2A
WIN
NIE
STR
EET
(E) H
OU
SE2
WIN
NIE
STR
EET
(E) H
OU
SE4
WIN
NIE
STR
EET
(E) "
BOU
NG
ANVI
LLEA
APAR
TMEN
TS" 2
58M
ILIT
ARY
RO
AD
EXIS
TIN
G R
OO
MS
EXIS
TIN
G W
ALLS
DEM
OLI
TIO
N
PO B
ox 6
60 D
arlin
ghur
st N
SW 1
300
Aust
ralia
Leve
l 1, 1
9 Fo
ster
Stre
et, S
urry
Hills
NSW
201
0 Au
stra
lia
Tann
er K
ibbl
e De
nton
Arc
hite
cts
Pty
Ltd
ww
w.tk
da.c
om.a
u
Rev
D
ate
Des
crip
tion
Che
cked
Au
th.
LEG
END
CLI
ENT
T +6
1 2
9968
980
2F
+61
2 99
09 3
228
Urbi
sTO
WN
PLA
NN
ING
T +6
1 2
8233
990
0
TTW
STR
UC
TUR
AL &
CIV
IL
T +6
1 2
9439
728
8F
+61
2 94
39 3
146
Stee
nsen
Var
min
gES
D, E
LEC
TRIC
AL &
MEC
HAN
ICAL
T +6
1 2
9967
220
0
Wilk
inso
n M
urra
yAC
OU
STIC
T +6
1 2
9437
461
1
Insy
nc S
ervi
ces
HYD
RAU
LIC
T +6
1 92
62 3
400
Dra
win
g N
o.
Rev
isio
n
Proj
ect
Dra
win
g Ti
tle
Proj
. Dir
Proj
. Arc
h
Dra
wn
Job
No.
Dat
e
Sca
le
RD
VC MAY
15
N
NSW
Nom
inat
ed A
rchi
tect
s:R
ober
t Den
ton
R
eg. N
o. 5
782
Alex
Kib
ble
R
eg. N
o. 6
015
Do
not s
cale
dra
win
gs. V
erify
all
dim
ensi
ons
on s
ite. N
otify
arc
hite
ct o
f all
disc
repa
ncie
s
T +
61 2
928
1 43
99F
+61
2 9
281
4337
Traf
fixTR
AFFI
C
T +6
1 83
24 8
700
Silk
Con
sulti
ng L
ands
cape
Arc
hite
cts
LAN
DSC
APE
T +6
1 2
9966
196
0
Ride
r Lev
ett B
uckn
all
QU
ANTI
TY S
UR
VEYO
R
T +6
1 2
9922
227
7
RED
LAN
DS
SEN
IOR
CAM
PUS
STAG
E 1
BUIL
DIN
GM
ON
FOR
D P
LAC
E LE
ARN
ING
HU
B
Redl
ands
Sand
rick
Proj
ect D
irect
ions
/Bl
oom
park
Con
sulti
ng
PRO
JEC
T M
ANAG
ER
T +6
1 2
8860
949
4 / +
61 2
995
7 14
73
A
1 :
200
@ A
1
AR-D
A-
1411
11
1002
VC
LEVE
L 1
DEM
OLI
TIO
N P
LAN
SO
UTH
A13
/05/
15Is
sued
for S
SDA
ToA
AKR
D
WATE
RSROAD
GER
ARD
STR
EET
(E) H
OU
SEN
o. 1
3 G
ERAR
D S
TREE
T
(E) A
PAR
TMEN
TSN
o. 8
-12
WIN
NIE
STR
EET
(E) A
PAR
TMEN
TSN
o. 8
-12
WIN
NIE
STR
EET
(E) H
OU
SEN
o. 1
5 G
ERAR
DST
REE
T
(E) A
PAR
TMEN
TSN
o. 1
9 W
ATER
S R
OAD
(E) S
CIE
NC
E LA
B 1
(E)
SCIE
NC
ELA
B 2
(E) R
EDLA
ND
S H
ALL
(E) C
LASS
RO
OM
(E) C
LASS
RO
OM
(E) C
LASS
RO
OM
(E)
TOIL
ETS
(E) S
CIE
NC
E LA
B 3
(E) C
LASS
RO
OM
(E) C
LASS
RO
OM
(E) C
LASS
RO
OM
(E) C
LASS
RO
OM
(E) C
LASS
RO
OM
(E) C
LASS
RO
OM
(E) C
LASS
RO
OM
(E) E
SL
(E) C
LASS
RO
OM
VOID
(E) B
ASKE
TBAL
LC
OU
RT
(E) D
ESIG
N &
TEC
HN
OLO
GY
CO
TTAG
E TO
BE
DEM
OLI
SHED
(E) D
ESIG
N &
TEC
HN
OLO
GY
CO
TTAG
E TO
BE
DEM
OLI
SHED
(E) T
REE
S TO
BE R
EMO
VED
(E) T
REE
S TO
BE
REM
OVE
D
(E) B
/BLO
CK
CO
TTAG
E TO
BE
DEM
OLI
SHED
(E) M
OW
LLBU
ILD
ING
TO
BE
DEM
OLI
SHED
(E) S
TAFF
RO
OM
TO
BE R
ETAI
NED
(E) L
IFT
TO B
E R
ETAI
NED
DU
RIN
G S
TAG
E 1C
CO
NST
RU
CTI
ON
; TO
BE
DEM
OLI
SHED
AT
CO
MPL
ETIO
N O
F N
EWLE
ARN
ING
HU
B
(E) B
UIL
DIN
G 7
MO
NFO
RD
PLAC
E TO
BE
DEM
OLI
SHED
(E) B
UIL
DIN
G 8
MO
NFO
RD
PLAC
E TO
BE
DEM
OLI
SHED
(E) R
ETAI
NIN
GW
ALL
AND
STAI
RS
TO B
ED
EMO
LISH
ED
(E) W
ALLS
,TR
EES
AND
STR
UC
TUR
ES T
OBE
DEM
OLI
SHED
BRIC
K U
PO
PEN
ING
S
(E) M
USI
CC
OTT
AGE
W/B
LOC
K TO
BE
DEM
OLI
SHED
(E) V
ISU
AL A
RT
CO
TTAG
EV/
BLO
CK
TO B
ED
EMO
LISH
ED
(E) C
OTT
AGE
X/BL
OC
K TO
BE
DEM
OLI
SHED
(E) M
USI
CC
OTT
AGE
Y/BL
OC
K TO
BE
DEM
OLI
SHED
(E) F
ACIL
ITIE
SC
OTT
AGE
Z/BL
OC
K TO
BE
DEM
OLI
SHED
(E) G
ARD
ENBE
DS
AND
OU
TDO
OR
PLA
YAR
EA T
O B
ED
EMO
LISH
ED
(E) T
REE
SW
ITH
IN T
HE
SITE
TO
BE
REM
OVE
D
JOIN
S AR
-DD
-100
4SU
BJEC
T TO
SEP
ARAT
E AP
PLIC
ATIO
N
EXIS
TIN
G R
OO
MS
EXIS
TIN
G W
ALLS
DEM
OLI
TIO
N
PO B
ox 6
60 D
arlin
ghur
st N
SW 1
300
Aust
ralia
Leve
l 1, 1
9 Fo
ster
Stre
et, S
urry
Hills
NSW
201
0 Au
stra
lia
Tann
er K
ibbl
e De
nton
Arc
hite
cts
Pty
Ltd
ww
w.tk
da.c
om.a
u
Rev
D
ate
Des
crip
tion
Che
cked
Au
th.
LEG
END
CLI
ENT
T +6
1 2
9968
980
2F
+61
2 99
09 3
228
Urbi
sTO
WN
PLA
NN
ING
T +6
1 2
8233
990
0
TTW
STR
UC
TUR
AL &
CIV
IL
T +6
1 2
9439
728
8F
+61
2 94
39 3
146
Stee
nsen
Var
min
gES
D, E
LEC
TRIC
AL &
MEC
HAN
ICAL
T +6
1 2
9967
220
0
Wilk
inso
n M
urra
yAC
OU
STIC
T +6
1 2
9437
461
1
Insy
nc S
ervi
ces
HYD
RAU
LIC
T +6
1 92
62 3
400
Dra
win
g N
o.
Rev
isio
n
Proj
ect
Dra
win
g Ti
tle
Proj
. Dir
Proj
. Arc
h
Dra
wn
Job
No.
Dat
e
Sca
le
RD
VC MAY
15
N
NSW
Nom
inat
ed A
rchi
tect
s:R
ober
t Den
ton
R
eg. N
o. 5
782
Alex
Kib
ble
R
eg. N
o. 6
015
Do
not s
cale
dra
win
gs. V
erify
all
dim
ensi
ons
on s
ite. N
otify
arc
hite
ct o
f all
disc
repa
ncie
s
T +
61 2
928
1 43
99F
+61
2 9
281
4337
Traf
fixTR
AFFI
C
T +6
1 83
24 8
700
Silk
Con
sulti
ng L
ands
cape
Arc
hite
cts
LAN
DSC
APE
T +6
1 2
9966
196
0
Ride
r Lev
ett B
uckn
all
QU
ANTI
TY S
UR
VEYO
R
T +6
1 2
9922
227
7
RED
LAN
DS
SEN
IOR
CAM
PUS
STAG
E 1
BUIL
DIN
GM
ON
FOR
D P
LAC
E LE
ARN
ING
HU
B
Redl
ands
Sand
rick
Proj
ect D
irect
ions
/Bl
oom
park
Con
sulti
ng
PRO
JEC
T M
ANAG
ER
T +6
1 2
8860
949
4 / +
61 2
995
7 14
73
A
1 :
200
@ A
1
AR-D
A-
1411
11
1003
VC
LEVE
L 2
DEM
OLI
TIO
N P
LAN
NO
RTH
A13
/05/
15Is
sued
for S
SDA
ToA
AKR
D