2~Text Book~Project Risk Management Rev-3 (Final)

download 2~Text Book~Project Risk Management Rev-3 (Final)

of 14

Transcript of 2~Text Book~Project Risk Management Rev-3 (Final)

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    1/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 1 of 14

    Dated 22-Aug-2011 Project Risk Management

    Project

    RiskManagement

    Prepared by

    Ajay Kumar SinghalMobile # 98101 53530

    All rights reserved. No part of this document may be reproduced or transmitted in any form or by anymeans, electronic, mechanical, photocopying, recording, or otherwise, without prior written permission ofWriter.

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    2/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 2 of 14

    Dated 22-Aug-2011 Project Risk Management

    Construction projects, from inception to closure, encounter unlimited risks. The risks

    vary from project to project. Project risk management aims at planning and controlling of

    risks, which might affect the performance of the project.

    It involves identifying, analyzing, response planning, monitoring and controlling risks atproject site.

    Project Constraints :

    Time

    Quantity

    Cost

    Scope

    What Is A Risk

    The chance of an event occurring which would cause actual project circumstances to

    differ from those assumed when forecasting project benefit and costs.

    When it is good, we call it opportunity or Positive Risk.

    When it is bad, we call it threat or Negative Risk.

    Risk Management

    Risk is the degree of probability of an external event threatening the success of the

    Project.

    Risk Management is the process of identifying, analyzing and drawing up plans to

    minimize their effect on a Project.

    Project risks affect schedule or resources.

    Product risks affect the quality or performance.

    Business risks affect the organization.

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    3/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 3 of 14

    Dated 22-Aug-2011 Project Risk Management

    A systematic approach to control the level of risk to mitigate its effects

    Risk Identification

    It is the process of determining which risks may affect the project and documenting their

    characteristics. The success of a project depends upon the management of these risk

    prone changing environments within the framework of project objectives.

    1) Acts of God :

    Flood, Earthquake,

    Landslide,

    Wind damage,

    Epidemic etc.

    2) Financial & Economic :

    Investment risk,

    Inflation,

    Availability of funds,

    Fluctuations in currency exchange rates, Change in tax structures,

    Change in royalty structure of stone and sand,

    Effect of time & cost overruns.

    3) Political and Legal :

    Site area is politically motivated,

    Presence and participation of union labour,

    Local personnel are to be engaged,

    Shifts in political leadership,

    Change in laws and regulations, Import-export restrictions and procedures,

    Risk Identification

    Risk AnalysisRisk

    Analysis

    ControlledRisk

    Environment

    Risk Planning

    Risk Monitoring

    Risk Response

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    4/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 4 of 14

    Dated 22-Aug-2011 Project Risk Management

    Requirement for licenses and permits,

    Pollution & safety rules.

    4) Project Scope:

    Ill-defined project scope,

    Frequent change in work scope,

    No extra work control.

    5) Design :

    Design responsibility,

    No proper soil investigation,

    Frequent changes in design during construction,

    Unrealistic specifications / constructability of design,

    Poor design and shop drawings.

    6) Physical :

    Inadequate or low quality procurement of resources,

    Constraints on the availability of labour,

    Non-availability of the material quality as well as quantity,

    Long hauling distance material problem,

    Non-availability of special equipments, spare parts etc,

    Non-availability of construction water, power, accommodations for labour andstaff,

    Weather conditions; like high temperature / heavy rainfall,

    Low load carrying capacity of existing culverts / bridges on the route,

    Unsafe working conditions,

    Fire, wastage and theft.

    7) Contractual :

    Insufficient time to prepare bid tenders,

    Unrealistic time schedule,

    Project schedules anticipate weather that may occur during the execution period,

    Conflicting conditions of contract,

    Delay in possession of site,

    Differing site conditions,

    Payment problems,

    Extra works / variations,

    Claims and disputes, Inability to take timely corrective action.

    8) Leadership :

    No project vision, no team building,

    Poor motivation,

    Lack of senior management support,

    Limited authority / control for Project In-charge,

    Lack of co-ordination,

    Insufficient liaison with public services,

    Barriers in communication / poor communications.

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    5/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 5 of 14

    Dated 22-Aug-2011 Project Risk Management

    9) Organizational :

    Lack of competent / experience persons in the project team,

    Wrong selection of project team,

    No project manual / documented procedures / processes,

    Project being too complex for the available resources,

    Inadequate communications infrastructure,

    Poor quality control, Unsatisfactory conduct of status review meetings,

    Inability to take timely corrective action.

    Risk Analysis

    Perform Risk Analysis on all possible significant risks likely to be encountered in

    a Project.

    Asses the probability of each risk.

    Asses the impact if it happens.

    Risk Planning

    Consider each risk and develop a strategy to manage that risk.

    Avoidance strategies

    o The probability that the risk will arise is reduced.

    Minimization strategies

    o The impact of the risk on the project or product will be reduced.

    Contingency plans

    o If the risk arises, contingency plans are planned to deal with that risk.

    Risk Monitoring

    Identify new risks.

    Re-assess each identified risks regularly to decide whether or not it is becoming

    less or more probable.

    Also asses whether the effects of the risk have changed.

    Each key risk should be discussed at management progress review meetings.

    Risk Response Method

    Elimination

    o Tendering a very high bid.

    o Placing conditions on the bid.

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    6/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 6 of 14

    Dated 22-Aug-2011 Project Risk Management

    o Pre-contract negotiations as to which party takes certain risks.

    o Not biding on the high risk portion of the contract.

    Transfer

    o The activity responsible for the risk may be transferred- To a contractor or designer by the Client.

    - To a Sub-contractor by the Contractor.

    o The activity may be retained, but the financial risk transferred, i.e. methods

    such as insurance.

    Deferred

    o Activities can be moved to a later date in the Project when the adverse effects

    of events may be minimized or reduced.

    Retention

    o Handling risks by the company who is undertaking the project.

    o Two retention methods, active and passive.

    - Active retention is a deliberate management strategy after a conscious

    evaluation of the possible losses and costs of alternative ways of handling

    risks.

    - Passive retention occurs through negligence, ignorance or absence of

    decision.

    Reduction

    o Continuous effort.

    o Well-defined specifications.

    o Detailed site survey.

    o Detailed design.

    o Completing design before execution.

    o Early involvement of trained / expert project group.

    o Related with improvements of a companys physical, procedural, educational,

    and training devices.

    o Improving housekeeping, maintenance, first aid procedures and security.

    o Education and training within every department.

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    7/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 7 of 14

    Dated 22-Aug-2011 Project Risk Management

    Risk Assessment Matrix

    A matrix is a two-dimensional array; an array made of rows and columns. In risk

    management the risk matrix is a mean to visualize these two dimensions in order to

    display the ranking of a risk. It is made of the impact / consequence / severity of a

    risk when occurring and the likelihood / probability of a risk to occur.

    To build the risk matrix, you will divide likelihood and consequences into steps.

    Find it : Identify What you need to do ?

    - Consider what can go wrong.

    - Calculate the risk level.

    Asses it : Probability / Likelihood How likely is it to happen ?

    - Usually underestimated,

    - Consider existing controls,

    - Work conditions and procedures.

    Probability Meaning Value

    Rare A remote likelihood. 1

    Unlikely Very unlikely to occur. 2

    Possible Unlikely, but possible to occur at some time. 3

    Likely Will probably occur in most circumstances. 4

    Almost Certain Likely to occur in most circumstances. 5

    Asses it : Impact / Consequences / Severity How severely could it hurt

    someone / cause damage ?

    - Be realistic.

    Impact Meaning Value

    Negligible No injuries, low financial impact. 1

    Minor First-aid treatment required, some financial impact. 2

    Moderate Medical treatment required, high cost. 3

    Major Serious injury, major cost. 4

    Catastrophic Death or large number of serious injuries, huge cost. 5

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    8/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 8 of 14

    Dated 22-Aug-2011 Project Risk Management

    Asses it : Risk Matrix = Probability x Impact

    Risk

    Probability

    Risk Impact

    Negligible Minor Moderate Major Catastrophic

    1 2 3 4 5

    Rare 11

    Low

    2

    Low

    3

    Low

    4

    Low

    5

    Medium

    Unlikely 22

    Low

    4

    Low

    6

    Medium

    8

    Medium

    10

    Significant

    Possible 33

    Low

    6

    Medium

    9

    Significant

    12

    Significant

    15

    Major

    Likely 44

    Low

    8

    Medium

    12

    Significant

    16

    Major

    20

    Major

    Almost

    Certain 5

    5

    Medium

    10

    Significant

    15

    Major

    20

    Major

    25

    Major

    Risk Based Control Plan

    Risk Level Action and Time Scale

    1 - 4

    Low

    Acceptable with continued data collection and trending forcontinuous improvement. Monitoring required ensuring controls

    are maintained. Manage through routine procedures. Go foreconomic improvements where possible.

    5 - 8Medium

    Acceptable after review of the operation. Requires continuedtracking and recorded action plans. Undertake a risk assessmentof the situation / task and implement the appropriate actions.Actions should have a timescale and should be monitored.

    9 12Significant

    Where the risk involves work in progress, undertake a riskassessment as soon as possible to ensure the safety of thesituation or task. Work should not start until the risk isreduced to an acceptable level. Considerable resources mayhave to be allocated. Requires Management decision.

    15 25Major

    Unacceptable under existing circumstances requires immediateaction. Do not commence the activity until a risk assessmenthas been completed to ensure the safety of the situation or task.If it is not possible to reduce or eliminate the risk even withunlimited resources, work must remain prohibited. RequiresSenior Management decision.

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    9/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 9 of 14

    Dated 22-Aug-2011 Project Risk Management

    Use Risk Matrix Data for Risk Management Strategy

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    10/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 10 of 14

    Dated 22-Aug-2011 Project Risk Management

    A decision tree is a tree in which each branch node represents a choice between a

    number of alternatives, and each leaf node represents a classification or decision.

    A decision tree is a method you can use to help make good choices, especially

    decisions that involve high costs and risks. Decision trees use a graphic approach to

    compare competing alternatives and assign values to those alternatives by combining

    uncertainties, costs, and payoffs into specific numerical values.

    Decision Trees are excellent tools for helping you to choose between several courses of

    action. They provide a highly effective structure within which you can lay out options

    and investigate the possible outcomes of choosing those options. They also help you to

    form a balanced picture of the risks and rewards associated with each possible course

    of action.

    Example

    A company has asked his two Project Managers to look for the opportunity to develop a

    new product. Company only has the resources and time to develop one of two projects,

    or to develop none.

    Project Managers A and B arrived. After brief introductions, A says that a smoke

    and fire detector is the best project to make. The detector goes beyond ordinary smoke

    detectors. It can detect flames as well as smoke. It will cost Rs 1,00,000 to develop, and

    if it succeeds it will generate revenue of Rs 10,00,000. Not to be outdone, B

    announces that a motion detector device is the best project to develop. The motion

    detector, which uses conventional household lighting, will only cost Rs 10,000 to

    develop. He adds that if it succeeds it will generate revenue of Rs 4,00,000. About the

    chances for success, the Director of the Business Analysis Department, informs themeeting that the smoke and fire detector has a 50% chance of success, and that the

    motion detector has an 80% chance of success.

    Draw the Tree

    Start by drawing a small square on the left side on a piece of paper. This is called the

    root node, or root. The root node represents the first set of decision alternatives. For

    each decision alternative draw a line, or branch, extending to the right from the root

    node.

    Decision Tree Analysis

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    11/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 11 of 14

    Dated 22-Aug-2011 Project Risk Management

    The first decision (root node) : Label each branch with the decision and its associated

    investment cost. Write that the smoke and fire detector will cost (- Rs 1,00,000) to

    develop. Similarly, write that the motion detector will cost (- Rs 10,000) to develop. Write

    Rs 0 at the third branch corresponding to the alternative to develop neither product.

    Show the costs as negative values since they represent a preliminary loss.

    Chance outcomes : Each product development effort can have one of two outcomes :

    each project can either succeed or fail. Draw a small circle, or chance node, at the end

    of the branch for the smoke & fire detector and as well for the motion detector. From

    each chance node draw two branches towards the right; one branch represents success

    and the other represents failure.

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    12/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 12 of 14

    Dated 22-Aug-2011 Project Risk Management

    Endpoints and payoffs : You can now complete all the branches with endpoints, since

    there is no further branch information to represent. Draw a small triangle at the end of

    each branch to represent the endpoint. Write the payoff value at the endpoint. In

    business applications the payoff is usually a monetary value equal to the anticipated net

    profit, or return on investment.

    Incorporate uncertainty (outcome probability) : We can now incorporate the

    likelihood of success and failure and use that to analyze the decision alternatives. In

    above example, the smoke and fire detector has a 50% chance of success, andtherefore a 50% chance of failure. The motion detector has an 80% chance of success,

    and therefore a 20% chance of failure. Write these values on their respective branch

    lines.

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    13/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 13 of 14

    Dated 22-Aug-2011 Project Risk Management

    Find the expected value (EV) : You are now ready to evaluate the relative merits of

    each decision alternative. Expected value (EV) is the way to combine payoffs and

    probabilities for each node. The higher the EV, the better a particular decision

    alternative on average when compared to the other alternatives in the decision tree.

    Expected value (EV) is the sum of all the combined payoffs and probabilities for each

    chance node.

    Summary : The smoke and fire detector project has a higher EV than the motion

    detector. You can report the analysis with these summarized presentation points:

    The smoke and fire detector is the better project to develop, despite the greater

    risk. The significantly larger anticipated profits make the risk more acceptable

    than the competing project.

    The motion detector is less risky, but also significantly less profitable. With the

    given profit expectations the project does not overcome the expected value of its

    rival project.

    Advantages of using decision trees

  • 7/28/2019 2~Text Book~Project Risk Management Rev-3 (Final)

    14/14

    ______________________________________________________________________AKS/TRG-NR/PRM/Rev-3 By : Ajay Kumar Singhal Page 14 of 14

    Dated 22-Aug-2011 Project Risk Management

    Decision trees offer advantages over other methods of analyzing alternatives. They are:

    Graphic. You can represent decision alternatives, possible outcomes, and

    chance events schematically.

    Efficient. You can quickly express complex alternatives clearly. You can easily

    modify a decision tree as new information becomes available.

    Revealing. You can compare competing alternativeseven without complete

    informationin terms of risk and probable value. The Expected Value (EV) term

    combines relative investment costs, anticipated payoffs, and uncertainties into a

    single numerical value.

    Complementary. You can use decision trees in conjunction with other project

    management tools. For example, the decision tree method can help evaluate

    project schedules.

    To contact, e-mail at : [email protected]