ZXSDR BS8906 U040UMTS Micro Node B
Hardware Installation Guide
Version HV2.0
ZTE CORPORATIONNO. 55, Hi-tech Road South, ShenZhen, P.R.ChinaPostcode: 518057Tel: (86) 755 26771900Fax: (86) 755 26770801URL: http://ensupport.zte.com.cnE-mail: [email protected]
-
LEGAL INFORMATION
Copyright 2010 ZTE CORPORATION.
The contents of this document are protected by copyright laws and international treaties. Any reproduction or distribution ofthis document or any portion of this document, in any form by any means, without the prior written consent of ZTE CORPO-RATION is prohibited. Additionally, the contents of this document are protected by contractual confidentiality obligations.
All company, brand and product names are trade or service marks, or registered trade or service marks, of ZTE CORPORATIONor of their respective owners.
This document is provided as is, and all express, implied, or statutory warranties, representations or conditions are dis-claimed, including without limitation any implied warranty of merchantability, fitness for a particular purpose, title or non-in-fringement. ZTE CORPORATION and its licensors shall not be liable for damages resulting from the use of or reliance on theinformation contained herein.
ZTE CORPORATION or its licensors may have current or pending intellectual property rights or applications covering the subjectmatter of this document. Except as expressly provided in any written license between ZTE CORPORATION and its licensee,the user of this document shall not acquire any license to the subject matter herein.
ZTE CORPORATION reserves the right to upgrade or make technical change to this product without further notice.
Users may visit ZTE technical support website http://ensupport.zte.com.cn to inquire related information.
The ultimate right to interpret this product resides in ZTE CORPORATION.
Revision History
Revision No. Revision Date Revision Reason
R1.0 20100619 The First edition
Serial Number: SJ-20100510160815-031
-
Content
About This Manual............................................. I
Safty Instructions .............................................1Safety Instructions Overview ........................................... 1
Safety Symbols .............................................................. 1
Safety Instructions Guideline ........................................... 2
Installation Overview........................................7Appearance ................................................................... 7
Construction specification ................................................ 8
Physical Specification .................................................. 8
Power Supply Specifications ......................................... 8
Grounding Specification............................................... 8
Temperature and Humidity Specification ........................ 9
Installation Flow............................................................. 9
Installation Precautions ..................................................11
Installation Preparations ................................13Personnel Requirements .................................................13
Tools and Instruments....................................................13
Technical Documents......................................................19
Unpacking and Inspection...............................................20
Counting Goods.........................................................20
Unpacking Crate........................................................20
Unpacking Carton ......................................................21
Goods Acceptance and Handover .................................22
Cabinet Installation.........................................25Installing Cabinet on Pole ...............................................25
Back-to-Pole Installation Mode ....................................25
Side-to-Pole Installation Mode .....................................33
Installing Cabinet on Wall ...............................................42
Back-to-Wall Installation Mode ....................................42
Side-to-Wall Installation Mode.....................................52
Installing Cabinet on Ground...........................................63
Confidential and Proprietary Information of ZTE CORPORATION I
-
ZXSDR BS8906 U040 Hardware Installation Guide
Module Installation .........................................71Module Positions............................................................71
Installing RF Module.......................................................72
Installing Baseband Module.............................................72
Installing Baseband Horizontally-Inserted Module ..............73
Installing Baseband Vertically-Inserted Module ..................73
Installing FCE................................................................73
Cable Installation............................................75List of Cables to Be Installed ...........................................75
Cable Installation Flow ...................................................75
Waterproof Cable-Through Module ...................................76
Installing BBU DC Input Power Cable................................79
Installing Equipment AC Input Power Cable .......................82
Installing Grounding Cable..............................................83
Installing Data Cable......................................................85
Installing 75 E1 Cable .................................................87
Installing 120 E1 Cable ...............................................89
Installing Dry Contact I/O Cable ......................................91
Installing RSU DC Input Power Cable................................93
Installing Cable Connecting BBU and RSU .........................96
Installing GPS Jumper ....................................................97
Installing RF Jumper ......................................................99
GPS Antenna Feeder System Installation .......103GPS Antenna Feeder System Installation Flow ................. 103
GPS Antenna Feeder System Installation Preparation ......... 104
Installing GPS Antenna................................................. 104
GPS Antenna Appearance ......................................... 104
GPS Antenna Installation Position .............................. 104
Installing GPS Antenna in Vertical Placement............... 105
Installing GPS Antenna in Horizontal Placement ........... 107
Installing GPS Antenna in Wall-Mount Mode ................ 109
Installing GPS Feeder................................................... 111
GPS Feeder Selection Principle .................................. 111
Wiring GPS Feeder................................................... 111
Installing GPS 1/4'' Feeder Grounding Kit.................... 113
Leading GPS Feeder Indoors ..................................... 115
Installing Arrester........................................................ 117
Main Antenna Feeder System Installa-
tion ...............................................................121
II Confidential and Proprietary Information of ZTE CORPORATION
-
Antenna Feeder System Installation Preparation .............. 121
Foundational Facility Requirements ............................ 121
Checking Incoming Material ...................................... 122
Making Feeder Connector ......................................... 122
Assembling Omnidirectional Antenna.......................... 125
Assembling Directional Antenna................................. 127
Hoisting Antenna and Feeder .................................... 129
Installing Outdoor Grounding Bar................................... 130
Installing Antenna ....................................................... 130
Installing Directional Antenna on Top-tower ................ 130
Installing Directional Antenna on Roof ........................ 137
Installing Omnidirectional Antenna on Top-tower.......... 147
Installing Omnidirectional Antenna on Roof ................. 152
Installing Antenna Jumper ........................................ 159
Installing and Grounding Feeder and Jumper................... 161
Feeder Cutting Principle............................................ 161
Feeder Layout Principle ............................................ 161
Installing Feeder on Tower ........................................ 162
Installing Feeder on Roof .......................................... 164
Feeder Grounding Principle ....................................... 165
Installing Feeder Grounding Kit ................................. 167
Performing Antenna Feeder System Test ......................... 168
Performing Outdoor-Connector Waterproof
Processing .......................................................... 169
Installation Check .........................................173Checking Equipment Installation.................................... 173
Cabinet Inspection Items.......................................... 173
Cable Check Items................................................... 173
Socket, Plug and Locking Piece Inspection Items.......... 174
Label Inspection Items ............................................. 174
On-site Environment Inspection Items........................ 175
Checking Antenna Feeder System Installation.................. 175
Checking Feeder...................................................... 175
VSWR Test.............................................................. 176
Checking Waterproof Processing ................................ 176
BS8906U040Checking Before Power on .......................... 177
Figures ..........................................................179
Tables ...........................................................185
Glossary ........................................................187
Confidential and Proprietary Information of ZTE CORPORATION III
-
ZXSDR BS8906 U040 Hardware Installation Guide
This page is intentionally blank.
IV Confidential and Proprietary Information of ZTE CORPORATION
-
About This Manual
Purpose This manual provides procedures and guidelines for installingZXSDR BS8906 U040.
IntendedAudience
Installation Engineer
What Is in ThisManual
This manual contains the following chapters.
Chapter Description
Chapter 1, Safety Instructions Explains safety symbols andsafety measures to follow duringthe hardware installation ofZXSDR BS8906 U040.
Chapter 2, Installation Overview Describes ZXSDR BS8906 U040installation flow and installationprecautions.
Chapter 3, InstallationPreparations
Describes installation preparationsin personnel, tools and meters,and technical documents.
Chapter 4, Cabinet Installation Introduces how to install ZXSDRBS8906 U040 cabinet.
Chapter 5, Module Installation Introduces how to install ZXSDRBS8906 U040 modules.
Chapter 6, Cable Installation Describes types and installation ofcables of ZXSDR BS8906 U040.
Chapter 7, GPS Antenna FeederSystem Installation
Explains the installation methodsand procedure for ZXSDR BS8906U040 GPS antenna feeder system.
Chapter 8, Main Antenna FeederSystem Installation
Explains the installation methodsand procedure for ZXSDR BS8906U040 main antenna feedersystem.
Chapter 9, Installation Check Introduces items to be checkedafter ZXSDR BS8906 U040installation is completed.
Confidential and Proprietary Information of ZTE CORPORATION I
-
ZXSDR BS8906 U040 Hardware Installation Guide
This page is intentionally blank.
II Confidential and Proprietary Information of ZTE CORPORATION
-
C h a p t e r 1
Safty Instructions
Table of ContentsSafety Instructions Overview ............................................... 1Safety Symbols .................................................................. 1Safety Instructions Guideline ............................................... 2
Safety Instructions OverviewTo avoid accidents, read this manual carefully before performinginstallation or maintenance for ZXSDR BS8906 U040 equipments.These instructions are supplementary to local safety regulations inplace. In case of any conflict, local safety regulations shall prevail.
ZXSDR BS8906 U040 installation personnel should have prelimi-nary knowledge about safety operations and must have receivedtraining on installing ZTE equipment.
Follow related equipment precautions and special safety instruc-tions during ZXSDR BS8906 U040 maintenance.
Some important safety instructions are discussed in this manual.ZTE shall not bear any liabilities incurred by violation of universalsafety operation requirements, or violation of safety standards fordesigning, manufacturing, and equipment usage.
Safety SymbolsTable 1 lists safety symbols.
TABLE 1 SAFETY SYMBOL TYPES AND MEANINGS
Safety Symbol Meaning
No smoking: Smoking is forbidden
No combustible material:Combustible material can not bestored.
No touching: Do not touch
Confidential and Proprietary Information of ZTE CORPORATION 1
-
ZXSDR BS8906 U040 Hardware Installation Guide
Safety Symbol Meaning
Universal alerting symbol:General safety attentions
Electric shock: Risk of electricshock
Electrostatic: The device may besensitive to static electricity
Microwave: Beware of strongelectromagnetic field
Laser: Beware of strong laserbeam
Scald: Beware of scald
The universal alerting symbol has three levels: danger, warn-ing, and caution. The formats and meanings of the three levelsare described as below:
Danger:
Indicates an imminently hazardous situation, which, if not avoided,could result in death or serious injury. Limit its use to only extremesituations.
Warning:
Indicates a hazardous situation, which, if not avoided, could resultin serious injuries, equipment damages or interruption of majorservices.
Caution:
Indicates a potentially hazardous situation, which, if not avoided,could result in moderate injuries, equipment damages or partialservice interruption.
Safety Instructions GuidelineElectrical Safety 1. Tools
Use special tools rather than common tools for high-voltageand AC operations.
2. High Voltage
2 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 1 Safty Instructions
Strictly follow local safety rules to install AC power equip-ments.
Installation staff must be qualified for performing high-volt-age and AC operations.
Do not wear any watch, hand chain, bracelet, ring or anyother conductive object during such operations.
Prevent moisture from accumulating on the equipment dur-ing operations in a damp environment.
Danger:
High voltage is hazardous. Direct or indirect contact with highvoltage or main supply using a wet object may result in death.
3. Power Cable
Make sure to shut off power supply before installing or dis-connecting a power cable.
Before connecting cables, make sure that the cables andcable labels match the practical installation conditions.
Danger:
Never install or uninstall power cables while they are live.
Otherwise, the power cable, when contacting a conductor,may result in sparks or electric arc, causing a fire or evendamage to eyes.
4. Drilling Holes
Unqualified drilling could damage wiring and cables insidethe cabinet. Additionally, metal pieces inside the cabinetgenerated by the drilling may result in a short circuit.
When it is necessary to perform drilling on a cabinet, wearinsulating gloves and first move away cables inside the cab-inet. Protect eyes during drilling as dust or flying debrismay damage eyes. Clean debris in time after drilling.
Warning:
It is strictly prohibited to drill holes on the cabinet without per-mission.
5. Lightning
Thunderstorms might generate a strong electromagneticfield in the atmosphere. Therefore, the equipment must begrounded and protected in time against lightning strikes.
Confidential and Proprietary Information of ZTE CORPORATION 3
-
ZXSDR BS8906 U040 Hardware Installation Guide
Danger:
Do not perform high-voltage or AC operations or operations atiron tower or mast in a thunderstorm.
Antistatic Friction caused by human body is the root cause of electro-static charge accumulation. In dry environment, the electro-static voltage carried by human body can be as high as 30 kVand can remain in human body for a long time. When an oper-ator carrying static electricity touches a component, the staticelectricity will be discharged and damage the component.
Before touching any equipment or holding the board, circuitboard, and IC chip, wear the antistatic wrist strap and make theother end of it be well grounded. This helps avoid damagingelectrostatic-sensitive components by the static electricity ofhuman body.
A resistor over 1 M must be connected in series on the cablebetween the antistatic wrist strap and the grounding point, toprotect the operator against accidental electric shock. Resis-tance over 1 M is low enough to discharge static voltage.
The antistatic wrist strap must be checked periodically. Do notreplace the cable of an antistatic wrist strap by any other cable.
Do not contact static-sensitive modules with any object thattends to generate static electricity. For example, frictioncaused by package bag, transfer box and transfer belt, whichis made from insulation plastic, may cause static electricity oncomponents.
Static-sensitive boards/modules should only contact materi-als of good discharging performance, such as the antistaticbag. Keep boards/modules in antistatic bags during storageand transportation.
Discharge static electricity of the testing device before use,that is, make the testing device be grounded first.
Do not place a board/module near a strong DC magneticfield, such as the cathode-ray tube of a monitor. Keep theboard/module at least 10 cm away.
Electrostatic:
Static electricity produced by human body can damage electro-static-sensitive components on the circuit board, such as LargeIntegrated Circuits (LIC).
Hoisting Weights To disassemble, move, or replace a heavy equipment, makesure that facilities with proper hoisting capability are available.
Personnel performing the hoisting task must have receivedproper training. Before the hoisting operation is performed, thehoisting tools must be checked and be complete. Make surethat the hoisting tools are firmly fixed on the support frame orthe wall. Use short command to avoid misoperation.
4 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 1 Safty Instructions
Warning:
Make sure that no one stays or walks under the hoisted weight.
Unplugging/Plug-ging a Board/Mod-
ule
Do not plug in a board with great force as it might bend thepins at the backplane.
Insert the board/module along the slot to avoid the circuit sur-face of board/module touching each other lest there is anyshort circuit.
While holding a module, do not touch its circuits, components,connectors, and wiring trough.
Others Replacing the parts or modifying the equipment may give riseto extra danger.
Therefore, do not replace any part or alter the equipment un-less being authorized.
To ensure your safety, please contact ZTE Corporation if youhave any problem.
Due to that RRU is in high temperature during running, the RRUshould be installed in some regions out of operators reach orstrictly restricted.
Caution:
Do not perform maintenance or debugging independently, unlessa qualified person is present.
Confidential and Proprietary Information of ZTE CORPORATION 5
-
ZXSDR BS8906 U040 Hardware Installation Guide
This page is intentionally blank.
6 Confidential and Proprietary Information of ZTE CORPORATION
-
C h a p t e r 2
Installation Overview
Table of ContentsAppearance ....................................................................... 7Construction specification .................................................... 8Installation Flow................................................................. 9Installation Precautions ......................................................11
AppearanceFigure 1 shows the appearance of ZXSDR BS8906 U040.
FIGURE 1 ZXSDR BS8906 U040 APPEARANCE
Confidential and Proprietary Information of ZTE CORPORATION 7
-
ZXSDR BS8906 U040 Hardware Installation Guide
Construction specification
Physical Specification
The physical specification of the cabinet is as follows:Table 2.
TABLE 2 PHYSICAL SPECIFICATION
Parameter Value
Dimensions 600mm 320 mm 480mm(Height Width Depth)
Weight Not more than 33 KG atfull configuration (RSU notincluded)
Not more than 52 KG at fullconfiguration (RSU included)
Color Gray
Power Supply Specifications
The power supply specifications are shown in Table 3.
TABLE 3 POWER SUPPLY SPECIFICATIONS
Parameter Value
-48 V DC: voltage fluctuation range -40 V ~ -57 VPower supply andvoltage range
100V~240 V AC: voltage fluctuation range90V~290 V
Grounding Specification
The grounding should follow the requirements below:
The grounding resistance at the installation site is not to higherthan 5. For the areas with less than 20 thunderstorm daysa year, the grounding resistance may be not higher than 10Omega.
Guarantee that all equipments are connected to the outdoorgrounding system, and the outdoor grounding system is ingood status.
8 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 2 Installation Overview
Temperature and HumiditySpecification
The temperature and humidity specifications are shown in Table 4.
TABLE 4 TEMPERATURE AND HUMIDITY SPECIFICATION
Parameter Requirement
Operating Temperature-40 deg - +50 deg, 55 deg of shortperiod is supported.
Operating Humidity 5%RH ~ 95%RH
Installation FlowThe installation flow of ZXSDR BS8906 U040 is shown in Figure 2.
Confidential and Proprietary Information of ZTE CORPORATION 9
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 2 ZXSDR BS8906 U040 INSTALLATION FLOW
10 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 2 Installation Overview
Installation Precautions
Caution:
Non-professionals shall not install or debug the equipment individ-ually, unless instructed by professionals on site.
Read this manual and relevant manuals carefully before instal-lation. Strictly follow the installation flow and specifications inthis manual to perform installation.
ZXSDR BS8906 U040Hardware installation personnel mustparticipate in some training related to communication equip-ment installation and acquire proficient installation skills.
During installation, ensure personal safety and avoid accidentssuch as electric shock or bruise.
During installation in the equipment room, installation per-sonnel should wear insulation shoes and take off necklaces,bracelets and watches.
During inserting/extracting modules, installation personnelshould wear antistatic wrist strap and make sure that theother end of the strap is grounded reliably.
During installation and maintenance of optical fiber, do not di-rectly stare at the cross-section of optical fiber or a socket ofoptical terminal in case that laser beams damage eyes. Seriouseye injury may occur if laser bundle irradiates your eyeball.
Do not plug in a board with too much force lest that the pinson the backplane be bent. Insert the board along the slot toavoid contact between parallel boards, which might cause shortcircuit.
Hold the board at the edge to avoid directly contacting theboard's circuits, components, and connectors. Hold and movecarefully to avoid hand injury.
Replacing any part or altering the equipment might result inunexpected dangers. Therefore, do not replace any part oralter the equipment unless being authorized.
ZXSDR BS8906 U040 is an expensive electronic equipment, bevery careful during the installation.
Confidential and Proprietary Information of ZTE CORPORATION 11
-
ZXSDR BS8906 U040 Hardware Installation Guide
This page is intentionally blank.
12 Confidential and Proprietary Information of ZTE CORPORATION
-
C h a p t e r 3
Installation Preparations
Table of ContentsPersonnel Requirements .....................................................13Tools and Instruments........................................................13Technical Documents .........................................................19Unpacking and Inspection...................................................20
Personnel RequirementsArrange ZXSDR BS8906 U040 installation personnel and deter-mine the construction time. Installation personnel should partici-pate in ZTEs training and examination, and acquire the knowledgeof installation and debugging. After obtaining job certificate, in-stallation personnel are qualified for installation and debugging.
Tools and InstrumentsTools and instruments that may be used for installation are listedin Table 5.
TABLE 5 REQUIRED TOOLS AND INSTRUMENTS
Cate-gory Name Example
A knife for feeder cable
A cable stripper for 75 ohmscoaxial cable
Spe-cial-pur-posetools
Confidential and Proprietary Information of ZTE CORPORATION 13
-
ZXSDR BS8906 U040 Hardware Installation Guide
Cate-gory Name Example
A multifunctional press plier
A multimeter
A SWR tester
Grounding resistance tester
An electric drill
Several bits provided
A dust collector
Pun-chingtools
A power board (at least 3 2P &3P sockets, current above 15A)
14 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 3 Installation Preparations
Cate-gory Name Example
Philips screwdriver (one for 4",6", and 8")
Straight screwdriver (one for4", 6", and 8")
Adjustable wrench (one 6",one 8", one 10", and one 12")
Bifunctional wrench (one 17"and one 19")
A set of socket wrench
A paper knife
A 5 kg claw-hammer
A 300 W iron and a 40 W iron
A set of hex wrench
Nor-maltools
Confidential and Proprietary Information of ZTE CORPORATION 15
-
ZXSDR BS8906 U040 Hardware Installation Guide
Cate-gory Name Example
A coil of soldering tin bar
A 50 m skin ruler
A 5 m steel tape
A angle instrument
A compass
a horizontal ruler
Mea-sure-menttools
16 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 3 Installation Preparations
Cate-gory Name Example
plumb line
Anti-static wrist strap
Slip-proof gloves
Pro-tec-tionTools
Safety helmet
A hacksaw (several sawblades)
A sharp nose plier (8")
A diagonal plier (8")
A round plier (8")
A plier (8")
Lock-smithtools
Confidential and Proprietary Information of ZTE CORPORATION 17
-
ZXSDR BS8906 U040 Hardware Installation Guide
Cate-gory Name Example
A set of broach file (middle)
Nipper
A paint brush
A pair of scissors
A fan
A tin extractor
A hydraulic plier
Level
A set of chain wheels
Rope
Aux-iliarytools
18 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 3 Installation Preparations
Cate-gory Name Example
Ladder
Spectrum analyzer (if neces-sary)
Site tester
Me-ters
Field strength tester (if neces-sary)
Technical DocumentsBefore installing ZXSDR BS8906 U040 make sure that the follow-ing technical documents are available:
ZXSDR BS8906 U040 (HV2.0) UMTS Micro Node B HardwareInstallation Guide
ZXSDR BS8906 U040 (HV2.0) UMTS Micro Node B HardwareDescription
ZXSDR BS8906 U040 (V4.09.21) UMTS Micro Node B SystemDescription
ZXSDR BS8906 U040 (V4.09.21) UMTS Micro Node B Mainte-nance Guide
Confidential and Proprietary Information of ZTE CORPORATION 19
-
ZXSDR BS8906 U040 Hardware Installation Guide
Unpacking and Inspection
Counting Goods
Prerequisites Goods have arrived at the installation place.
Context Goods counting must be performed by technical personnel of ZTEand the operator together.
Steps 1. Check the total number of goods, intactness of packing boxes,and check whether arrival place is the actual installation placeagainst packing list number attached to packing boxes. If theabove check is passed, start to unpack and inspect the goods.
2. The Equipment Inspection List and the Unpacking AcceptanceReport are put in the packing box marked 1#. Firstly, openthe 1# packing box and take out the Unpacking AcceptanceReport to check whether the goods received are in accordancewith the inspection list.
3. If there is any goods short or damaged, fill in the UnpackingAcceptance Feedback Table, and contact ZTE in time for appro-priate handling.
END OF STEPS
Unpacking Crate
Context Use a claw hammer, a pair of pliers, a flathead screwdriver, and acrowbar to unpack the crate.
Steps 1. Insert a flathead screwdriver or claw hammer into the mentallatch of the cover plate of the crate, and rotate the flatheadscrewdriver or claw hammer to loosen the iron sheet.
2. Use the tools to loosen all the mental latches on the cover plateof the crate, and then remove the cover plate.
3. Take the carton out of the crate.
END OF STEPS
Example Figure 3 shows the components in the crate.
20 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 3 Installation Preparations
FIGURE 3 COMPONENTS IN CRATE
1. Accessory2. Cover plate3. Carton
4. Foam pad5. Crate
Unpacking Carton
Context Usually, electronic components, terminal equipments, and aux-iliary material are put in the carton. Electronic components arestored in the antistatic bag. Therefore, installation personnelshould take antistatic measure during the unpacking process toavoid any damage.
Unpacking tools: diagonal plier, paper knife.
Be careful about the following two items during the unpackingprocess:
Do not damage the antistatic bag, which can be used in thefuture for storage of spare parts).
Properly dispose of the desiccants, and keep them away fromchildren.
Steps 1. Use the diagonal pliers to cut packing straps.
2. Use the paper knife to cut adhesive tape along slits on thecarton cover, and avoid damaging the goods inside.
3. Open the carton and take out the foam pad.
Confidential and Proprietary Information of ZTE CORPORATION 21
-
ZXSDR BS8906 U040 Hardware Installation Guide
4. Check the goods in the carton according to the goods list upondelivery.
5. Take out the antistatic packing bag.
6. Open the antistatic packing bag and take out the electroniccomponents, as shown in Figure 4.
FIGURE 4 WEARING ANTISTATIC WRIST STRAP
END OF STEPS
Goods Acceptance and Handover
Steps 1. Goods acceptance
According to the goods name, category and amount in thegoods list, check the goods one by one. Make sure that thegoods satisfy the following conditions:
There are no protruding, concave, bubble, peeling, nick andsmear on the surface of the cabinet.
The cabinet's surface is in good condition, without problemssuch as the lacquer flaking off or damage.
All clamping screws are tight and intact.
All the components are properly installed at the correct po-sitions.
Arrange the inspected goods according to categories.
2. Goods handover
After the goods are inspected, the representative of customerand the project supervisor should approve and sign on the Un-packing Acceptance Report. If the contract specifies that thegoods are kept by the customer after the acceptance is passed,
22 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 3 Installation Preparations
then hand over the goods to the customer after the UnpackingAcceptance Report is signed.
END OF STEPS
Confidential and Proprietary Information of ZTE CORPORATION 23
-
ZXSDR BS8906 U040 Hardware Installation Guide
This page is intentionally blank.
24 Confidential and Proprietary Information of ZTE CORPORATION
-
C h a p t e r 4
Cabinet Installation
Table of ContentsInstalling Cabinet on Pole ...................................................25Installing Cabinet on Wall ...................................................42Installing Cabinet on Ground...............................................63
Installing Cabinet on Pole
Back-to-Pole Installation Mode
Prerequisites ZXSDR BS8906 U040The equipment unpacking and acceptanceare completed.
Note:
All modules inside ZXSDR BS8906 U040 cabinet have been in-stalled upon delivery.
Context The following lists components required for installing ZXSDRBS8906 U040 on the pole.
1. ZXSDR BS8906 U040 cabinet
2. Pole-mounted installation components
The pole-mounted installation mode has two types: side-to-poleinstallation (i.e. the cabinet's side is mounted on the pole) andback-to-pole installation (i.e. the cabinet's back is mounted onthe pole)
Steps 1. Form the main bracket.
i. Use two reinforcing girders to connect the left bracket andthe right bracket, and fix them with eight M6 screws, asshown in Figure 5.
Confidential and Proprietary Information of ZTE CORPORATION 25
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 5 MAIN BRACKET SCHEMATIC DIAGRAM (1)
1. M6 screws2. Reinforcing girder
3. Right bracket4. Left bracket
ii. Fix the two beams at the two pairs of holes on the mainbracket with four M6 screws, as shown in Figure 6.
26 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 6 MAIN BRACKET SCHEMATIC DIAGRAM (2) -BACK-TO-POLE INSTALLATION
1. Beam 2. M6 screws
2. Use long bolts to fix the main bracket on the pole via two fixingplates, as shown in Figure 7.
Confidential and Proprietary Information of ZTE CORPORATION 27
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 7 FIXING MAIN BRACKET
1. Hexagon nut2. Spring washer3. Flat washer4. Pole fixing plate5. Pole
6. Insulating washer7. Insulating gasket8. Flat washer9. Long bolt
3. Remove the protective batten from the cabinet, as shown inFigure 8. The removed six screws are used for connecting thecabinet and the main bracket. Keep them for use in future.
28 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 8 REMOVING PROTECTIVE BATTEN OF CABINET
1. Batten 2. Screw
4. Fix the cabinet on the main bracket.
i. Fix the corner component on the two nuts on the cabinet'sback, and tighten it with two screws, as shown in Figure 9.
Confidential and Proprietary Information of ZTE CORPORATION 29
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 9 FIXING CORNER COMPONENT
1. Screws 2. Corner component
ii. Lift the cabinet and mount the corner component's hook onthe reinforcing girder, as shown in Figure 10.
30 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 10 MOUNTING CABINET
iii. At the cabinet's bottom, use the six screws, which are re-moved from the protective batten, to fix the cabinet onthe six holes on the main bracket, as shown in Figure 11.Installation personnel can also use four screws to fix thecabinet, that is, the two screws in the middle can be omit-ted.
Confidential and Proprietary Information of ZTE CORPORATION 31
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 11 FIXING CABINET
END OF STEPS
Result Figure 12 shows a back-to-pole installed ZXSDR BS8906 U040 cab-inet.
32 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 12 BACK-TO-POLE INSTALLED ZXSDR BS8906 U040
Side-to-Pole Installation Mode
Prerequisites ZXSDR BS8906 U040The equipment unpacking and acceptanceare completed.
Note:
All modules inside ZXSDR BS8906 U040 cabinet have been in-stalled upon delivery.
Context ZXSDR BS8906 U040The following lists components required forinstalling the cabinet on the pole.
1. ZXSDR BS8906 U040 cabinet
2. Pole installation components
The pole installation mode has two types: side-to-pole installation(i.e. the cabinet's side is mounted on the pole) and back-to-poleinstallation (i.e. the cabinet's back is mounted on the pole)
Steps 1. Form the main bracket.
i. Use two reinforcing girders to connect the left bracket andthe right bracket, and fix them with eight M6 screws, asshown in Figure 13.
Confidential and Proprietary Information of ZTE CORPORATION 33
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 13 MAIN BRACKET SCHEMATIC DIAGRAM (1)
1. M6 screws2. Reinforcing girder
3. Right bracket4. Left bracket
ii. For side-to-pole installation, fix one beam at a pair of holeson the main bracket with two screws, as shown in Figure14.
34 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 14 MAIN BRACKET SCHEMATIC DIAGRAM (2) -SIDE-TO-POLE INSTALLATION
1. Beam 2. M6 screws
2. Use long bolts to fix the main bracket on the pole via two fixingplates, as shown in Figure 15.
Confidential and Proprietary Information of ZTE CORPORATION 35
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 15 FIXING MAIN BRACKET
1. Hexagon nut2. Spring washer3. Flat washer4. Pole fixing plate5. Pole
6. Insulating washer7. Insulating gasket8. Flat washer9. Long bolt
3. Remove the protective batten from the cabinet, as shown inFigure 16. The removed six screws are used for connectingthe cabinet and the main bracket. Keep them for use in future.
36 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 16 REMOVING PROTECTIVE BATTEN OF CABINET
1. Batten 2. Screws
4. Fix the cabinet on the main bracket.
i. Fix the beam on the two nuts on the cabinet's side with thebeam's rabbet facing downwards, and tighten it with twoscrews, as shown in Figure 17.
Confidential and Proprietary Information of ZTE CORPORATION 37
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 17 FIXING BEAM
ii. Fix the corner component on the two nuts on the beam,and tighten it with two screws, as shown in Figure 18.
38 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 18 FIXING CORNER COMPONENT
1. Screws 2. Corner component
iii. Lift the cabinet and mount the corner component's hook onthe reinforcing girder, as shown in Figure 19.
Confidential and Proprietary Information of ZTE CORPORATION 39
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 19 MOUNTING CABINET
iv. At the cabinet's bottom, use the six screws, which are re-moved from the protective batten, to fix the cabinet on thesix holes on the main bracket, as shown in Figure 20.
40 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 20 FIXING CABINET
END OF STEPS
Result Figure 21 shows a side-to-pole installed ZXSDR BS8906 U040 cab-inet.
Confidential and Proprietary Information of ZTE CORPORATION 41
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 21 SIDE-TO-POLE INSTALLED ZXSDR BS8906 U040
Installing Cabinet on Wall
Back-to-Wall Installation Mode
Prerequisites ZXSDR BS8906 U040The equipment unpacking and acceptanceare completed.
Note:
All modules inside ZXSDR BS8906 U040 cabinet have been in-stalled upon delivery.
Context The following lists components required for installing ZXSDRBS8906 U040 on the pole.
1. ZXSDR BS8906 U040 cabinet
2. Wall-mounted installation components
42 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
The wall-mounted installation mode has two types: side-to-wallinstallation (i.e. the cabinet's side is mounted on the wall) andback-to-wall installation (i.e. the cabinet's back is mounted onthe wall)
Steps 1. Install the expansion bolt M10100.
i. Decide the installation position of ZXSDR BS8906 U040cabinet on the wall according to the engineering design.Mark the holes on the wall. The hole positions of the cab-inet's installation plate are shown in Figure 22. The lowerholes are 1 m away from the ground.
FIGURE 22 HOLE POSITIONS FOR INSTALLING CABINET (UNIT: MM)
ii. Use the electric percussive drill to drill holes (12) onmarked positions. Use the dust collector to clean dust intime while drilling.
Caution:
Hold the drill firmly and keep the drill bit vertical to the wall.
iii. Place the expansion tube on the expansion bolt, slightly ro-tate them into the nut, and strike them into the drilled holewith a rubber hammer, and fasten the nut until the expan-sion tube is completely expanded. Roate the nut outwards,as shown in Figure 23.
Confidential and Proprietary Information of ZTE CORPORATION 43
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 23 INSTALLING EXPANSION BOLT M10100
2. Form the main bracket.
i. Use two reinforcing girders to connect the left bracket andthe right bracket, and fix them with eight M6 screws, asshown in Figure 24.
44 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 24 MAIN BRACKET SCHEMATIC DIAGRAM (1)
1. M6 screws2. Reinforcing girder
3. Right bracket4. Left bracket
ii. Fix the two beams at the two pairs of holes on the mainbracket with four M6 screws, as shown in Figure 25.
Confidential and Proprietary Information of ZTE CORPORATION 45
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 25 MAIN BRACKET SCHEMATIC DIAGRAM (2) -BACK-TO-WALL INSTALLATION
1. Beam 2. M6 screws
3. Put spring washer, flat washer, and insulating washer on fourexpansion bolts, and fix the main bracket on the wall throughtwo insulating gaskets, as shown in Figure 26.
46 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 26 FIXING MAIN BRACKET
1. Expansion tube2. Insulating washer3. Main bracket4. Insulating gasket
5. Flat washer6. Spring washer7. Expansion bolt
4. Remove the protective batten from the cabinet, as shown inFigure 27. The removed six screws are used for connectingthe cabinet and the main bracket. Keep them for use in future.
Confidential and Proprietary Information of ZTE CORPORATION 47
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 27 REMOVING PROTECTIVE BATTEN OF CABINET
5. Fix the cabinet on the main bracket.
i. Fix the corner component on the two nuts on the cabinet'sback, and tighten it with two screws, as shown in Figure28.
48 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 28 FIXING CORNER COMPONENT
1. Screws 2. Corner component
ii. Lift the cabinet and mount the corner component's hook onthe reinforcing girder, as shown in Figure 29.
Confidential and Proprietary Information of ZTE CORPORATION 49
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 29 MOUNTING CABINET
iii. At the cabinet's bottom, use the six screws, which are re-moved from the protective batten, to fix the cabinet onthe six holes on the main bracket, as shown in Figure 30.Installation personnel can also use four screws to fix thecabinet, that is, the two screws in the middle can be omit-ted.
50 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 30 FIXING CABINET
END OF STEPS
Result Figure 31 shows a back-to-wall installed ZXSDR BS8906 U040 cab-inet.
Confidential and Proprietary Information of ZTE CORPORATION 51
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 31 BACK-TO-WALL INSTALLED ZXSDR BS8906 U040
Side-to-Wall Installation Mode
Prerequisites ZXSDR BS8906 U040The equipment unpacking and acceptanceare completed.
Note:
All modules inside ZXSDR BS8906 U040 cabinet have been in-stalled upon delivery.
Context ZXSDR BS8906 U040The following lists components required forinstalling the cabinet on the wall.
1. ZXSDR BS8906 U040 cabinet
2. Wall-mounted installation components
The wall-mounted installation mode has two types: side-to-wallinstallation (i.e. the cabinet's side is mounted on the wall) and
52 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
back-to-wall installation (i.e. the cabinet's back is mounted onthe wall)
Steps 1. Install the expansion bolt M10100.
i. Decide the installation position of ZXSDR BS8906 U040cabinet on the wall according to the engineering design.Mark the holes on the wall. The hole positions of the cab-inet's installation plate are shown in Figure 32. The lowerholes are 1 m away from the ground.
FIGURE 32 HOLE POSITIONS FOR INSTALLING CABINET (UNIT: MM)
ii. Use the electric percussive drill to drill holes (12) onmarked positions. Use the dust collector to clean dust intime while drilling.
Caution:
Hold the drill firmly and keep the drill bit vertical to the wall.
iii. Place the expansion tube on the expansion bolt, slightlyrotate them into the nut, and strike them into the drilledhole with a rubber hammer, and fasten the nut until theexpansion tube is completely expanded. Rotate the nutoutwards, as shown in Figure 33.
Confidential and Proprietary Information of ZTE CORPORATION 53
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 33 INSTALLING EXPANSION BOLT M10100
2. Form the main bracket.
i. Use two reinforcing girders to connect the left bracket andthe right bracket, and fix them with eight M6 screws, asshown in Figure 34.
54 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 34 MAIN BRACKET SCHEMATIC DIAGRAM (1)
1. M6 screws2. Reinforcing girder
3. Right bracket4. Left bracket
ii. Fix one beam at a pair of holes on the main bracket withtwo screws, as shown in Figure 35.
Confidential and Proprietary Information of ZTE CORPORATION 55
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 35 MAIN BRACKET SCHEMATIC DIAGRAM (2) -SIDE-TO-WALL INSTALLATION
1. Beam 2. M6 screws
3. Put spring washer, flat washer, and insulating washer on fourexpansion bolts, and fix the main bracket on the wall throughtwo insulating gaskets, as shown in Figure 36.
56 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 36 FIXING MAIN BRACKET
1. Expansion tube2. Insulating washer3. Main bracket4. Insulating gasket
5. Flat washer6. Spring washer7. Expansion bolt
4. Remove the protective batten from the cabinet, as shown inFigure 37. The removed six screws are used for connectingthe cabinet and the main bracket. Keep them for use in future.
Confidential and Proprietary Information of ZTE CORPORATION 57
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 37 REMOVING PROTECTIVE BATTEN OF CABINET
1. Batten 2. Screws
5. Fix the cabinet on the main bracket.
i. Fix the beam on the two nuts on the cabinet's side with thebeam's rabbet facing downwards, and tighten it with twoscrews, as shown in Figure 38.
58 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 38 FIXING BEAM
ii. Fix the corner component on the two nuts on the beam,and tighten it with two screws, as shown in Figure 39.
Confidential and Proprietary Information of ZTE CORPORATION 59
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 39 FIXING CORNER COMPONENT
1. Screws 2. Corner component
iii. Lift the cabinet and mount the corner component's hook onthe reinforcing girder, as shown in Figure 40.
60 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 40 MOUNTING CABINET
iv. At the cabinet's bottom, use the six screws, which are re-moved from the protective batten, to fix the cabinet on thesix holes on the main bracket, as shown in Figure 41.
Confidential and Proprietary Information of ZTE CORPORATION 61
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 41 FIXING CABINET
END OF STEPS
Result Figure 42 shows a side-to-wall installed ZXSDR BS8906 U040 cab-inet.
62 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 42 SIDE-TO-WALL INSTALLED ZXSDR BS8906 U040
Installing Cabinet on GroundPrerequisites ZXSDR BS8906 U040The equipment unpacking and acceptance
are completed.
Note:
All modules inside ZXSDR BS8906 U040 cabinet have been in-stalled upon delivery.
Context The following lists components required for installing ZXSDRBS8906 U040 on the ground.
1. ZXSDR BS8906 U040 cabinet
2. Ground installation components
Steps 1. Install the expansion bolt M10100.
Confidential and Proprietary Information of ZTE CORPORATION 63
-
ZXSDR BS8906 U040 Hardware Installation Guide
i. Decide the installation position of the ground installationbracket on the ground according to the engineering design.Mark the holes on the ground. Figure 43 shows dimensionsof the holes.
FIGURE 43 DRILLING DIMENSION
ii. Use the electric percussive drill to drill holes (12) onmarked positions. Use the dust collector to clean dust intime while drilling.
Caution:
Hold the drill firmly and keep the drill bit vertical to theground.
iii. Place the expansion tube on the expansion bolt, slightly ro-tate them into the nut, strike them into the drilled hole witha rubber hammer, and fasten the nut until the expansiontube is completely expanded. Rotate the nut outwards, asshown in Figure 44.
FIGURE 44 INSTALLING EXPANSION BOLT
2. Install the ground installation components.
64 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
Put insulating plate, ground installation bracket, insulatingtube, flat washer, and spring washer on the expansion boltM10100, and fasten the nut M10, as shown in Figure 45.
FIGURE 45 FIXING GROUND INSTALLATION COMPONENTS
1. Ground installation bracket2. Hexagon head nut3. Spring washer4. Flat washer
5. Insulating tube6. Insulating plate7. Expansion bolt
The ground installation components are fixed, as shown inFigure 46.
Confidential and Proprietary Information of ZTE CORPORATION 65
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 46 FIXED GROUND INSTALLATION COMPONENTS
3. Remove the screws and the supporting battens at the cabinetbottom, as shown in Figure 47.
66 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 47 REMOVING SUPPORTING BATTEN AT CABINET BOTTOM
1. Batten 2. Screws
4. Hoist the cabinet to the correct position on the ground instal-lation bracket. Use the screws removed from the supportingbattens to connect the cabinet to the holes on the ground in-stallation bracket, as shown in Figure 48.
Confidential and Proprietary Information of ZTE CORPORATION 67
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 48 FIXING CABINET ON GROUND INSTALLATION BRACKET
1. Installation hole 2. Screws
END OF STEPS
Result Figure 49 shows a ZXSDR BS8906 U040 cabinet installed on theground.
68 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 4 Cabinet Installation
FIGURE 49 ZXSDR BS8906 U040 GROUND INSTALLATION SCHEMATICDIAGRAM
Confidential and Proprietary Information of ZTE CORPORATION 69
-
ZXSDR BS8906 U040 Hardware Installation Guide
This page is intentionally blank.
70 Confidential and Proprietary Information of ZTE CORPORATION
-
C h a p t e r 5
Module Installation
Table of ContentsModule Positions................................................................71Installing RF Module ..........................................................72Installing Baseband Module.................................................72Installing Baseband Horizontally-Inserted Module ..................73Installing Baseband Vertically-Inserted Module ......................73Installing FCE....................................................................73
Module PositionsFigure 50 shows the positions of modules of ZXSDR BS8906 U040.
Confidential and Proprietary Information of ZTE CORPORATION 71
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 50 MODULE POSITIONS
1. RSU cabinet2. LPU subrack/Transmission sub-
rack/Microwave subrack
3. APM+PSU subrack/DPM subrack4. BBU cabinet5. FCE
Installing RF ModuleContext The RF module has been installed upon delivery.
Installing Baseband ModuleContext The baseband module has been installed upon delivery.
72 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 5 Module Installation
Installing BasebandHorizontally-Inserted Module
Context The baseband horizontally-inserted module has been installedupon delivery.
Installing BasebandVertically-Inserted Module
Context The baseband vertically-inserted module has been installed upondelivery.
Installing FCEContext FCE has been installed upon delivery.
Confidential and Proprietary Information of ZTE CORPORATION 73
-
ZXSDR BS8906 U040 Hardware Installation Guide
This page is intentionally blank.
74 Confidential and Proprietary Information of ZTE CORPORATION
-
C h a p t e r 6
Cable Installation
Table of ContentsList of Cables to Be Installed ...............................................75Cable Installation Flow .......................................................75Waterproof Cable-Through Module .......................................76Installing BBU DC Input Power Cable....................................79Installing Equipment AC Input Power Cable ...........................82Installing Grounding Cable..................................................83Installing Data Cable..........................................................85Installing 75 E1 Cable .....................................................87Installing 120 E1 Cable ...................................................89Installing Dry Contact I/O Cable ..........................................91Installing RSU DC Input Power Cable....................................93Installing Cable Connecting BBU and RSU .............................96Installing GPS Jumper ........................................................97Installing RF Jumper ..........................................................99
List of Cables to Be InstalledThe following lists cables that should be installed on the site:
BBU DC/AC input power cable
Grounding cable
Data cable
E1/T1 cable
RSU DC input power cable
Cable between BBU and RSU
GPS jumper
RF jumper
Dry contact I/O cable
Cable Installation FlowThe cable installation flow is shown in Figure 51.
Confidential and Proprietary Information of ZTE CORPORATION 75
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 51 CABLE INSTALLATION FLOW
Some cables might have been installed upon delivery.
Waterproof Cable-ThroughModuleThe waterproof cable-through module (cable-through hole) is lo-cated on the cabinet bottom. Figure 52 shows the cable lead-ing-out mode.
76 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
FIGURE 52 CABLE LEADING-OUT SCHEMATIC DIAGRAM
1. High-speed data cable2. RF cable or fiber connecting CC
and GPS (when GPS is external)3. Fibre4. AC power cable or fiber5. RS232 cable6. Dry contact cable7. E1/T12 or microwave8. E1/T1-1 or microwave9. High-speed data cable10. Cascading fiber
11. Dry contact, 485 cable12. ASIG13. Fibre14. DC power cable or fiber15. RSU power cable16. Fibre17. Fibre18. Fibre19. RSU power cable20. Antenna feeder21. Antenna feeder
InstallationProcedure ofWaterproof
Cable-ThroughModule
1. Settle cables to be led into the cabinet, and make marks onthe silica gel block, which is at the cabinet bottom.
2. Loosen the three captive screws on the silica gel block fromthe cabinet inside, as shown in Figure 53.
Confidential and Proprietary Information of ZTE CORPORATION 77
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 53 CAPTIVE SCREW POSITIONS
1. Captive screw
3. Loosen the two fixing screws of the waterproof cable-throughmodule from the cabinet outside, and the outer frame is sep-arated into two parts. Take out the silica gel block, as shownin Figure 54.
FIGURE 54 FIXING SCREW POSITIONS
1. Fixing screw 2. Silica gel block
4. Lead in cables, and extract the waterproof plug from corre-sponding holes. Cut a gap on the hole through which the cablewill pass, and insert the cable into the gap. Figure 52 showsthe cable-through holes. If the cable's diameter is too small,then wrap it with waterproof tape.
78 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
Caution:
If a cable-through hole has no cable to pass, make sure thatthe waterproof plug is in it.
5. Insert cables into the silica gel block, and make sure that thecable part which is wrapped by waterproof tape is in the block.
6. Insert the silica gel block into the cabinet and fix it at the cabi-net bottom. Use the other part of outer frame to clamp theblock, and fix the two parts of outer frame with two fixingscrews.
7. Use the three captive screws to fix the other part of outer frameat the cabinet bottom.
Cable LayoutSequence
It is recommended to lay cables according to the following se-quence.
1. Power cable.
2. Digital signal cable (E1/T1 cable, dry contact cable, 485/232cable, and ASIG cable.
3. RF cable.
4. Fibre.
Installing BBU DC InputPower Cable
Prerequisites Wear the antistatic wrist strap.
Cut a certain length of power cable according to actual require-ment.
Make sure that the power supply branch output is discon-nected.
Caution:
Check the cabinet's power supply status. Do not install thepower cable when it is live, which, if not avoided, could resultin death or serious injury.
Context The BBU DC input power cable is a 2-core 6 mm2 outdoor powercable.
Steps 1. Connect one end of power cable to a power distribution cabinet.
2. Lead the other end of power cable through the bottom of BBUcabinet.
3. Install the -48 V DC power cable at the power input interfaceof DPM module, as shown in Figure 55.
Confidential and Proprietary Information of ZTE CORPORATION 79
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 55 DPM SCHEMATIC DIAGRAM
Caution:
Connect positive and negative electrodes according to marks.Make sure they are connected correctly.
i. Install the -48V RTN cable at the grounding terminal at thecabinet bottom.
ii. Lead one power cable from the grounding terminal at thecabinet bottom, and connect it to the -48 V RTN terminalat the power input interface of DPM.
END OF STEPS
Result Figure 56 shows the installed BBU DC input power cable.
80 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
FIGURE 56 INSTALLATION POSITION OF BBU DC INPUT POWER CABLE
Confidential and Proprietary Information of ZTE CORPORATION 81
-
ZXSDR BS8906 U040 Hardware Installation Guide
Installing Equipment ACInput Power Cable
Prerequisites Wear the antistatic wrist strap.
Cut a certain length of power cable according to actual require-ment.
Make sure that the power supply branch output is discon-nected.
Caution:
Check the cabinet's power supply status. Do not install thepower cable when it is live, which, if not avoided, could resultin death or serious injury.
Context The equipment AC input power cable is an outdoor power cable,as shown in Figure 57.
FIGURE 57 EQUIPMENT AC INPUT POWER CABLE APPEARANCE
Steps 1. Connect end A of power cable to a power distribution cabinet.
2. Insert end B of power cable into the AC input terminal on APMin the cabinet, as shown in Figure 58.
FIGURE 58 APM SCHEMATIC DIAGRAM
1. AC power input interface
END OF STEPS
82 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
Installing Grounding CablePrerequisites Wear the antistatic wrist strap.
The baseband module and the RF module have been installed.
The grounding system and connection points of indoor and out-door copper grounding bars have been constructed completely.
Context The PE cable of ZXSDR BS8906 U040 cabinet must be installed.
ZXSDR BS8906 U040Figure 59 shows the grounding cable.
FIGURE 59 GROUNDING CABLE
Steps 1. Cut a certain length of grounding cable according to the dis-tance between the cabinet and the protective ground.
Note:
When cutting the cable, remain a certain margin.
2. Install one end of the grounding cable at the PE binding post atthe cabinet bottom. The installation position is shown in Figure60.
Confidential and Proprietary Information of ZTE CORPORATION 83
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 60 INSTALLING GROUNDING CABLE
3. Fasten the other end of the grounding cable at the connectionpoint of the protective ground.
4. Bind and fix the cable.
END OF STEPS
84 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
Installing Data CablePrerequisites Wear the antistatic wrist strap.
The SA module and the LPU module have been installed.
Context The data cable connecting BBU and LPU is used for monitoringinternal/external environment of the cabinet, and monitoring drycontacts. When Abis interface adopts E1/T1, the data cable is usedfor transferring signal from Abis interface.
End A and end B of the data cable connecting BBU and LPU are ofSCSI interfaces. The cable structure is shown in Figure 61.
FIGURE 61 DATA CABLE
Table 6 describes the data cable connecting BBU and LPU.
TABLE 6 DATA CABLE CONNECTING BBU AND LPU
End A End B
Connect the "Monitoring/Abis"interface on the SA board of BBUsubrack.
End B1: Connect the "BBU"interface of LPU subrackEnd B2: Connect the "COM"interface of FCE module
Steps 1. Insert end A of the data cable, which connects BBU and LPU,at the "Monitoring/Abis" interface of SA board of BBU subrack.
2. Insert end B1 of the data cable, which connects BBU and LPU,at the "BBU" interface of LPU subrack.
3. Lay the data cable along the top inside the cabinet. Bend bothends of the cable with a certain radian.
4. Fasten screws at the two ends of the cable.
5. Insert end B2 at the COM interface of FCE module, as shownin Figure 62.
Confidential and Proprietary Information of ZTE CORPORATION 85
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 62 EXTERNAL INTERFACES OF FCE MODULE
1. COM Interface of FCE Module
END OF STEPS
Result Figure 63 shows an installed data cable.
86 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
FIGURE 63 DATA CABLE INSTALLATION POSITIONS
Installing 75 E1 CablePrerequisites Wear the antistatic wrist strap.
The LPU module and the data cable have been installed.
Context Iub interface 75 E1 cable is the transmission cable betweenZXSDR BS8906 U040 and RNC. It transmits interface messagesbetween ZXSDR BS8906 U040 and RNC.
Confidential and Proprietary Information of ZTE CORPORATION 87
-
ZXSDR BS8906 U040 Hardware Installation Guide
End A of Iub interface 75 E1 cable is of DB44 straight connector.This cable has two types: Figure 64 supports 4 E1s, Figure 65supports 8 E1s.
Note:
For 8-core E1 cable, 1st E1 ~ 4th E1 are labeled, while 5th E1 ~8th E1 are not labeled.
FIGURE 64 IUB INTERFACE 75 E1 CABLE (4-CORE)
FIGURE 65 IUB INTERFACE 75 E1 CABLE (8-CORE)
Steps 1. Lead the 75 E1 cable into the BBU cabinet from the cabinetbottom.
2. Lay the 75 E1 cable vertically along the right side of thecabinet to the E1/T1 interface of LPU module.
3. Insert the DB44 connector of 75 E1 cable at the E1/T1 in-terface of LPU module.
END OF STEPS
Result Figure 66 shows an installed 75 E1 cable.
88 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
FIGURE 66 75 E1 CABLE INTALLATION POSITION
Installing 120 E1 CablePrerequisites Wear the antistatic wrist strap.
The LPU module and the data cable have been installed.
Context Iub interface 120 E1 cable is the transmission cable betweenZXSDR BS8906 U040 and RNC. It transmits interface messagesbetween ZXSDR BS8906 U040 and RNC.
Confidential and Proprietary Information of ZTE CORPORATION 89
-
ZXSDR BS8906 U040 Hardware Installation Guide
Figure 67 shows the appearance of Iub interface 120 E1 cable,and end A is of DB44 straight connector.
FIGURE 67 IUB INTERFACE 120 E1 CABLE
The 120 E1 cable has two types, which supports 4 E1s and 8 E1srespectively. The two types of cables have the same appearance,and differ from each other in the number of cores in the cable.
Steps 1. Lead the 120 E1 cable into the BBU cabinet from the cabinetbottom.
2. Lay the 120 E1 cable vertically along the right side of thecabinet to the E1/T1 interface of LPU module.
3. Insert the DB44 connector of 120 E1 cable at the E1/T1interface of LPU module.
END OF STEPS
Result Figure 68 shows an installed 120 E1 cable.
90 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
FIGURE 68 120 E1 CABLE INSTALLATION POSITION
Installing Dry Contact I/OCable
Prerequisites Wear the antistatic wrist strap.
The LPU module and the data cable have been installed.
Confidential and Proprietary Information of ZTE CORPORATION 91
-
ZXSDR BS8906 U040 Hardware Installation Guide
Context The dry contact I/O cable, which is called dry contact cable forshort, is between ZXSDR BS8906 U040 system and external envi-ronment monitoring system. It transfers the dry contact signal.
Figure 69 shows the dry contact I/O cable. End A is D-type 25-corestraight-cable welded connector (DB25).
FIGURE 69 DRY CONTACT CABLE
Steps 1. Lead the dry contact I/O cable into the BBU cabinet from thecabinet bottom.
2. Lay the dry contact I/O cable vertically along the right side ofthe cabinet to the MON IN/OUT interface of LPU module.
3. Insert the DB25 connector of dry contact I/O cable at the MONIN/OUT interface of LPU module.
END OF STEPS
Result Figure 70 shows an installed dry contact I/O cable.
92 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
FIGURE 70 DRY CONTACT CABLE INSTALLATION POSITION
Installing RSU DC InputPower Cable
Prerequisites Wear the antistatic wrist strap.
Confidential and Proprietary Information of ZTE CORPORATION 93
-
ZXSDR BS8906 U040 Hardware Installation Guide
Make sure that the power supply branch output is discon-nected.
The RF subrack has been installed.
The baseband power subrack has been installed.
Context The RSU DC input power cable is a 32.5 mm2 outdoor powercable, as shown in Figure 71.
FIGURE 71 RSU DC INPUT POWER CABLE
Steps 1. Lead end B of the power cable into the RSU cabinet from thecabinet bottom, and lay the cable vertically along the right sideof the cabinet to the RSU's power input interface.
2. Insert end B of the power cable at the RSU's power input in-terface.
3. Lead end A of the power cable into the BBU cabinet from thecabinet bottom, and lay the cable upwards to the external in-terface -48 V OUTPUT1 of the power subrack.
4. Insert end A of the power cable at the -48 V OUTPUT1 interfaceof the power subrack.
END OF STEPS
Result Figure 72 shows the installed RSU DC input power cable.
94 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
FIGURE 72 INSTALLATION POSITION OF RSU DC INPUT POWER CABLE
Confidential and Proprietary Information of ZTE CORPORATION 95
-
ZXSDR BS8906 U040 Hardware Installation Guide
Installing Cable ConnectingBBU and RSU
Prerequisites Wear the antistatic wrist strap.
ZXSDR BS8906 U040The cabinet and all modules have beeninstalled.
Context The cable connecting BBU and RSU performs signal transmissionbetween the baseband subrack and the RF module. Figure 73shows the cable connecting ZXSDR BS8906 U040 BBU and RSU.
FIGURE 73 CABLE SCHEMATIC DIAGRAM
Steps 1. Lead one end of the cable into the BBU cabinet from the cabinetbottom, and lay the cable upwards to the TX1/RX1 interface ofFS module or CVI module.
2. Insert one end of the cable at the TX1/RX1 interface of FSmodule or CVI module.
3. Lead the other end of the cable into the RSU cabinet from thecabinet bottom, and lay the cable vertically along the right sideof the cabinet to the RSU's TX1/RX1 interface.
4. Insert the other end of the cable at the TX1/RX1 interface ofRSU.
END OF STEPS
Result Figure 74 shows an installed cable connecting BBU and RSU.
96 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
FIGURE 74 INSTALLATION POSITION OF CABLE CONNECTING BBU AND RSU
Installing GPS JumperPrerequisites Wear the antistatic wrist strap.
The cabinet and all modules have been installed.
Confidential and Proprietary Information of ZTE CORPORATION 97
-
ZXSDR BS8906 U040 Hardware Installation Guide
The GPS lightning protector has been installed.
Context The GPS jumper connects GPS lightning protector and CC board.It provides GPS clock input signal for CC board, and CC boardconverts it into the clock signal required by ZXSDR BS8906 U040.
The GPS jumper's structure is shown in Figure 75.
FIGURE 75 GPS JUMPER STRUCTURE
Steps 1. Connect one end of the jumper to the REF antenna interfaceof CC.
2. Lay the jumper along the cabinet side.
3. Connect the other end of the jumper to the GPS lightning pro-tector.
4. Bind and fix the jumper.
END OF STEPS
Result Figure 76 shows an installed GPS jumper.
98 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
FIGURE 76 INSTALLED GPS JUMPER
Installing RF JumperPrerequisites Wear the antistatic wrist strap.
The cabinet and all modules have been installed.
Context The RF jumper connects the main feeder and the antenna feederinterface of ZXSDR BS8906 U040 cabinet.
The RF jumper is made of two 1/2" super flexible bellows cableswith a length of 3 m.
Confidential and Proprietary Information of ZTE CORPORATION 99
-
ZXSDR BS8906 U040 Hardware Installation Guide
ZXSDR BS8906 U040Figure 77 shows the RF jumper.
FIGURE 77 RF JUMPER
Steps 1. Lead end B of RF jumper into the RSU cabinet from the cabi-net bottom, and lay the jumper upwards to the ANT1(TX/RX)interface.
2. Connect end B of RF jumper to the ANT1(TX/RX) interface.
3. Connect end A of RF jumper to the female DIN connector ofthe main feeder.
4. Lead end B of the other RF jumper into the RSU cabinetfrom the cabinet bottom, and lay the jumper upwards to theANT2(RX) interface.
5. Connect end B of RF jumper to the ANT2(TX/RX) interface.
6. Connect end A of RF jumper to the female DIN connector ofthe other main feeder.
7. Perform waterproof handling for the connectors.
END OF STEPS
Result Figure 78 shows an installed RF jumper.
100 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 6 Cable Installation
FIGURE 78 RF JUMPER INSTALLATION POSITION
Confidential and Proprietary Information of ZTE CORPORATION 101
-
ZXSDR BS8906 U040 Hardware Installation Guide
This page is intentionally blank.
102 Confidential and Proprietary Information of ZTE CORPORATION
-
C h a p t e r 7
GPS Antenna FeederSystem Installation
Table of ContentsGPS Antenna Feeder System Installation Flow ..................... 103GPS Antenna Feeder System Installation Preparation............ 104Installing GPS Antenna..................................................... 104Installing GPS Feeder....................................................... 111Installing Arrester............................................................ 117
GPS Antenna FeederSystem Installation FlowThe installation flow of GPS antenna feeder system is listed inFigure 79.
FIGURE 79 GPS ANTENNA FEEDER SYSTEM INSTALLATION FLOW
Confidential and Proprietary Information of ZTE CORPORATION 103
-
ZXSDR BS8906 U040 Hardware Installation Guide
GPS Antenna FeederSystem InstallationPreparationThe installation preparation of the GPS antenna feeder system isas follows:
Prepare the GPS antenna.
Assign installation personnel.
Prepare technical documents, tools and measure instrument.
Make connectors of GPS feeder and jumper.
Installing GPS Antenna
GPS Antenna Appearance
The appearance of GPS antenna is as shown in Figure 80.
FIGURE 80 GPS ANTENNA APPEARANCE
GPS Antenna Installation Position
GPS AntennaInstallationPositioning
The GPS antenna installation position should meet the followingrequirements:
The installation position should be far away from high and largebuildings as well as some buildings on the top of which smallaffiliated constructions locate. The upwardvertically visualangle of antenna is more than 90. The installation position ofantenna is as shown in Figure 81.
104 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 7 GPS Antenna Feeder System Installation
FIGURE 81 GPS ANTENNA INSTALLATION POSITION
1. Ambient construction or otherobstructions
2. GPS antenna
The installation position can not be radiated in a near distanceby a face of main lobe of mobile communication antenna. Donot locate the antenna under microwave signal frommicrowaveantenna, high-voltage cables and strong radiation from a TVemission tower.
Considering from lightning, select the center of roof for an in-stallation position. Do not install the antenna on the sunk fencearound the roof as well as at a corner of the roof, in order toprevent from lightning.
There should be other special and similar equipment near tothe installation position, such as other operation's tower. Makesure the antenna within a protective area of arrester. If thereis no iron tower or arrester, install a special arrester to meetthe requirement of lightning design. The level distance be-tween arrester and GPS antenna should keep 23 m and be0.5m higher than the receiving connector of GPS antenna atleast.
Installing GPS Antenna in VerticalPlacement
Prerequisites Following tools must be ready.
Adjustable spanner
Normal Spanner
It is recommended to have a pole with a diameter between 30 mm~ 60 mm (48 mm is recommended). The antenna should not beinstalled during rain and heavy wind.
Steps 1. Open the package and take out the GPS antenna and GPS rack.
2. Use the U-shape clamp to install the GPS rack to the mountingpole. Insert a spring washer and washer between the U-shapedclamp and mounting pole.
3. Use a M6 nut to fix the U-shape clamp and the pole togetherfirmly.
Figure 82 shows the fixing process.
Confidential and Proprietary Information of ZTE CORPORATION 105
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 82 U-SHAPED CLAMP INSTALLATION
1. GPS settled clamp2. Cable strip
3. Mounting pole4. U-shape clamp
4. Fix the GPS antenna to the GPS settled clamp. Screw the bolt(M4x14) to firmly fix the antenna.
END OF STEPS
Result Figure 83 shows the antenna fixed in the vertical position.
106 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 7 GPS Antenna Feeder System Installation
FIGURE 83 GPS ANTENNA VERTICAL INSTALLATION
1. GPS settled clamp2. Feeder3. Feeder strip
4. GPS antenna5. Mounting pole6. U-shape clamp
Installing GPS Antenna in HorizontalPlacement
Prerequisites Confirm the installation mode and installation position of GPS an-tenna.
Following tools must be ready:
Adjustable spanner
Normal Spanner
Context It is recommended to have a pole with a diameter between 30mm ~ 60 mm (48 mm is optimal).
The pole used to fix the GPS antenna must be grounded well.
The antenna cannot be installed during rain and heavy wind.
Steps 1. Open the package and take out the GPS antenna and GPS rack.
2. Use the U-shape clamp to install the GPS rack to the mountingpole.
3. The installation support of GPS antenna is as shown in Figure84. Align holes on the U-shape clamp with Hole 1 and Hole 3,or Hole 4 and Hole 6 on the installation support. Then covera spring wash and flat washer respectively on these holes andfasten them with M6 screws, as shown in Figure 85.
Confidential and Proprietary Information of ZTE CORPORATION 107
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 84 GPS ANTENNA RACK INSTALLATION SUPPORT
1~6 hole position
FIGURE 85 GPS RACK INSTALLATION (HORIZONTAL PLACEMENT)
4. Fix the GPS antenna to the GPS settled clamp. Screw downthe bolt (M4x14) to firmly fix the antenna.
END OF STEPS
Result Figure 86 shows the GPS antenna fixed horizontally.
108 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 7 GPS Antenna Feeder System Installation
FIGURE 86 GPS ANTENNA FIXED HORIZONTALLY
1. GPS settled clamp2. Feeder3. Feeder strip
4. GPS antenna5. Mounting pole6. U-shape clamp
Installing GPS Antenna in Wall-MountMode
Prerequisites Following tools must be ready.
Adjustable spanner
Normal Spanner
Hammer
Expansion Anchor Bolts (M5x30 or M5x40)
Context For installing the GPS Antenna on the wall, the U-shape clamp isunnecessary.
Steps 1. Open the package and take out the GPS antenna and GPS rack.
2. Use the design template for marking holes on the wall. Thendrill holes on the wall according to the size of the expansionanchor bolts that are to be used.
Figure 87 shows the design template.
Confidential and Proprietary Information of ZTE CORPORATION 109
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 87 DESIGN TEMPLATE FOR MARKING HOLES
3. Insert the expansion bolts, and hammer them to fix properly.
4. Install the GPS antenna rack to the corresponding bolt position.
5. Insert a spring washer and flat washer onto expansion boltsand use the M6 nut to fix the rack on the wall firmly.
Note:
The torque used to fix the clamp is 45 Nm.
6. Fix the GPS antenna to the GPS settled clamp and screw theM4x14 bolt tightly.
END OF STEPS
Result Figure 88 shows the GPS antenna fixed on the wall.
110 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 7 GPS Antenna Feeder System Installation
FIGURE 88 GPS ANTENNA FIXED ON WALL
Installing GPS Feeder
GPS Feeder Selection Principle
GPS feeder selection complies with the following principles:
When the length of GPS feeder is less than 100 m, select 1/4"feeder.
When the length of GPS feeder is more than 100 m, pleasecontact with ZTE local office.
Wiring GPS Feeder
Prerequisites Before feeder layout, check layout environment such as the irontower and roof; according to the requirements of engineering de-sign drawing, make sure the planning and procedures of layout.
Context Take notice of the following items while performing layout of theGPS feeder:
The feeder passage from the installation position to the equip-ment room should be unhindered and accords with the wiringrequirements; take some measurements for rain protectionand anticorrosion.
Make a water avoidance crook while the feeder is importedfrom outdoors to indoors; the lowest point of water avoidancecrook keeps a vertical distance of 200 mm at least from theinlet for waterproof.
Unused feeder connectors should be protected with solid ma-terial, such as packing bags, from damaging there connectorsduring cable layout.
Unfold the feeder and lay out it; avoid twisting as possible asyou can; if it is necessary for bending, make sure the radius of
Confidential and Proprietary Information of ZTE CORPORATION 111
-
ZXSDR BS8906 U040 Hardware Installation Guide
bending not less than the minimum radius of bending permittedby cables.
If the GPS antenna is installed on the roof, fix the feeder alongthe wall foot on the roof with plastic clips which steel nailsare attached to; keep an distance of 1m between plastic clips;the directions of plastic clip head are staggered mutually andregularly; two feeders after junction should be bound togetherin case of twisting mutually and bending.
Steps 1. Attach a mark respectively at the both ends of feeder.
2. Protect the feeder connector with linen (also adopt a antistaticpaging bag with protective foam) and fasten the bag with abanding tape.
3. Move the GPS feeder near to the GPS antenna.
4. Make an GPS feeder connector at one end through the bidingtape, connect with the GPS antenna and screw down the con-nector clockwise, as shown in Figure 89.
FIGURE 89 CONNECTION BETWEEN FEEDER TO GPS ANTENNA
1. GPS Antenna2. Pole3. Hoop Iron
4. GPS Mounting Panel5. GPS Feeder6. Feeder Binding Tape
Note:
While fixing the feeder, it is required to screw down the feederclockwise. So considering the situation, after completing theabove step, lay out the feeder, or else it is inconvenient forinstallation.
5. Accomplish the performance measure of antenna and feeder,make sure that the system operation is normal, and then makea waterproof protection at the back of GPS mounting panel aswell as at the junction of GPS feeder and GPS antenna.
112 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 7 GPS Antenna Feeder System Installation
6. Fix the GPS feeder with the binding tape and cut a redundantpart flatly after binding.
END OF STEPS
Installing GPS 1/4'' Feeder GroundingKit
Prerequisites 1. Complete the installation and routing of GPS feeder.
2. Prepare installation materials and tools.
The installation materials include:
Grounding kit (tinning copper braid attached)
Two M625 hexagon head screw spring washer andplain washer attached
One M825 hexagon head screw (spring washer andplain washer attached), used to connect the ground ca-ble and ground bar.
Assembled 1/4" feeder ground cable
A package of tung oil (10 ml).
The installation tools include:
Electrical knife
M6 screwdriver
M8 screwdriver.
Context The structure of GPS 1/4" feeder grounding kit is as shown inFigure 90.
Confidential and Proprietary Information of ZTE CORPORATION 113
-
ZXSDR BS8906 U040 Hardware Installation Guide
FIGURE 90 GPS 1/4" FEEDER GROUNDING KIT STRUCTURE
1. Grounding kit2. M6 hexagon head screw (plain
washer and spring washer at-tached)
3. Ground cable
The structure of ground cable is as shown in Figure 91.
FIGURE 91 1/4" FEEDER GROUND CABLE STRUCTURE
1. Ground terminal (on the side ofgrounding kit)
2. 12 heat shrinkable sleeve
3. Ground cable4. Ground terminal (on the side of
cooper ground bar)
114 Confidential and Proprietary Information of ZTE CORPORATION
-
Chapter 7 GPS Antenna Feeder System Installation
Steps 1. Make sure the grounding position of 1/4" GPS feeder; strip asection of the sheath of GPS feeder (about 25mm) according tothe size of grounding kit, and place the grounding kit throughthe stripped position of GPS feeder.
2. Fasten the ground terminal (on the side of grounding kit, withtwo grounding holes) onto the grounding kit with M6 hexagonhead screws; place the attached spring washer and plainwasher between screw and ground terminal, and screw downthe screw with an M6 screwdriver.
3. Fasten the other ground terminal (on the side of cooper groundbar) onto the cooper ground bar with the M825 hexagon headscrew, and place the plain washer and spring washer betweenscrew and copper ground bar.
4. Cover a layer of tung oil on the exposed metal surface.
END OF STEPS
Leading GPS Feeder Indoors
Context The operation of leading feeder indoors is only performed for in-door base stations.
Note:
The procedure of leading GPS feeder indoors is same as that ofthe main antenna feeder system.
The following principles should be obeyed when leading the feederindoors:
A 12-hole feeder cable hermetic window has four big holes.Each big hole contains three small holes, and each small holehas one feeder cable passing through.
Feeder cables in the three small holes in one big hole are ar-ranged sequentially according to engineering label ID, and arelaid out either clockwise or anti-clockwise.
The feeder cable layout in the hermetic window should be easilyexpanded. Capacity expansion should not change the originalfeeder cable layout, it is only allowed to add feeder cables in thehermetic window or change jumper connections in the cabinet.
The feeder cable layout in hermetic window should facilitatelaying feeder cables on the cable rack and feeder connectionswith th