25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

13
25 October 2005 A.Ciocio - SCTSG 1 Type IV Cables and PP3 • Status & Plan

Transcript of 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

Page 1: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 1

Type IV Cables and PP3

• Status & Plan

Page 2: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 2

PP3 Racks in UX15 (US15 side)

Y.52-4.X7, Y.53-4.X7Y.52-1.X6, Y.46-1.X6Y.43-1.X6, Y.34-1.X6Y.51-2.X2, Y.52-2.X2Y.53-2.X2

Page 3: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 3

PP3 Racks in UX15 (USA15 side)

Y.51-23.X8 Y.52-23.X8 Y.53-23.X8Y.51-26.X5, Y.53-26.X5Y.52-25.X2, Y.53-25.X2Y.51-25.X1

Page 4: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 4

PP3 RacksDummy PP3

Racks on Level 6US side

Page 5: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 5

Status of Type IV cables• Type IV cables are delivered in double lengths with connectors installed at the PP3

end and pulled between the UX15 cavern and the US(A) halls

• US side completed• USA side installation started this week• Delivery of harness has been very slow

– Vacation and QA problems in the summer– Connectors quality– Delay of components delivery from CERN to company – Bobbins damage– Production stopped for 3 weeks

• Delivery restored this week with expected rate of 150 double harness/week

• Expected complete delivery of harnesses by the end of the year• Installation of type IV might be interrupted by installation of type ii/iii

UX side US(A) sidePP3 Power Supply

Page 6: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 6

Mapping• Mapping/layout subject to frequent adjustements to accommodate

changes in routing or discrepancies with original expected routing• Endcap mapping issue

– In the present mapping, six PS crates from each cavern are shared between the two endcaps

– The endcap interlock scheme requires four matrix cards per cavern– The full set of interlock signals from one quadrant will be connected to

one matrix card – the present mapping may be accommodated by the interlock hardware

by routing signals between matrix cards– PS channel skipping to better match the interlock modularity of 4 to the

modularity of the cooling system– Revision of the DCS system to accommodate modules from multiple

partitions within one PS crate

Page 7: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 7

US(A) racks

Page 8: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 8

In US15• Cut cables and connectors on the power supply side installed in situ• First rack (200 cables/connectors) completed early in July

– Work performed by SEDELEC (subcontract of KontaktSysteme that provides the double length cables - Many mistakes

– ~15 connectors have been repaired (mechanical)– Several label mismatch still to be fixed – ~10 need serious repair (electrical)– They raised the cost significantly for future connector work

• New Plan– TC help with connector attachment– Nicolas Massol joined TC in September. One of his tasks is to organize

connector activity – Work with Petr Kubik (Prague) to discuss technical aspects and qualify

samples made by other companies being contacted– Meanwhile all cables are being cut to some extra length and ~ all tooling

has been purchased to make prototypes– Qualification of one company (CPE/Italy) in progress– Work might start soon

• Plan for testing with cables plugged in PS crate• Prague is going to design feedtrough board

Page 9: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 9

Rack Scheme for PP3

Page 10: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 10

Status of PP3• Cables are plugged in a few dummy Patch Panels during installation to be placed in

the right (final) position and are tightened to horizontal bars• Cables will have to be all removed from the current position and plugged in by

groups/rows when the installation of the real PP3 will occur• Big shipment of rack railing, PP3 housing crates, horizontal bars has been received

(827 Kg)• Ashley French currently at CERN has been dressing all the USA racks• First 100 PP3 units are under preparation • 60 units will arrive at CERN next week for burn-in and 40 will be burnt in at Melbourne

• The hold up so far has been the HV inserts • Following a successful test, the company will be given the go-ahead for the remaining

4000 units. Expected production time is 2-3 weeks • We’ll work on a scheme for shipment that agrees with the schedule • Shaun Roe and Igor Ilyashenko with the help from Pamela Ferrari and Ewa Stanecka

will set up testing and burn-in – Duration of tests to be decided• Ashley F. and Scott Moncrieff should arrive at CERN on 14 November and will stay

for four weeks • Estimated installation of 200 units per day but more people will be needed to help on

US side racks

Page 11: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 11

Testing• Tester designed and provided by Ljubljana (Gregor, Erik)

– 2 Test box + 2 Laptops + test cables– Need upgrade of test cables which are decaying after so much use– Lots of problems lately

• Test steps:– Cables are tested at reception (acceptance test)– After being pulled from UX15 to US(A)15 (uncut-double length)– After they are cut in the US side at connectors are installed

• Shift planner (developed by D. Robinson) works very well for planning the activities and have people to sign up

• http://www.hep.phy.cam.ac.uk/si-bin/sctworkplanner.cgi– (and contact me because of unexpected changing in rate delivery/testing

problems)• What is needed to be able to take a shift:

1) take the safety training course (at the pompiers station)2) make the access request on EDH3) get your safety boots & helmet (or borrow them)

Page 12: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 12

Current Shift Counts per Institute

• Institute Total Completed Pending• Prague 40 37 3• Geneva 36 35 1• Bergen 19 19 0• Valencia 11 11 0• UC Santa Cruz 10 9 1• Wisconsin 9 9 0• MPI 8 8 0• CERN 7 7 0• Ioffe 5 5 0• Okayama 4 4 0• Ljubljana 4 4 0• LBL 3 3 0• Kyoto 3 3 0• UCL 2 2 0• KEK 2 2 0• Cracow 2 2 0• Lancaster1 1 0

Page 13: 25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.

25 October 2005 A.Ciocio - SCTSG 13

Summary• Installation on US side completed

– Cables delivered and tested– Cables routed and tested– Cables cut to extra length

• Installation on USA side started– Delivery of double length harnesses restored– If rate of 150/w expected installation completion at the end of year unless

interrupted by type ii/iii installation• Connector work

– Qualification of company in progress• PP3

– First 100 unit will be at CERN soon (60 next week)– Remaining 4000 hopefully early in December– Installation of PP3 units

• 100 in November – then gradually in December

• Testing– Good presence of SCT collaborators – need to continue