2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS...

16
2018 Campus Master Plan Preliminary Draft Concepts Theresa Doherty Senior Project Director Rebecca Barnes University Architect

Transcript of 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS...

Page 1: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

2018 Campus Master PlanPreliminary Draft Concepts

Theresa DohertySenior Project Director

Rebecca BarnesUniversity Architect

Page 2: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

CURRENT SCHEDULE for2018 CAMPUS MASTER PLAN

• Kick off of Campus Master Plan and EIS Scoping October 14 & 15, 2015

• Preliminary Plan Concepts Developed –Winter and Spring 2016

• Draft Plan and Draft EIS published – Fall 2016• Final Plan and Final EIS published – Winter 2017• Hearing Examiner and City Council – Summer 2017• City Council and Board of Regents approval –

Late 2017 or early 2018

Page 3: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing
Presenter
Presentation Notes
12 elements of the CUA Went over these with you at the last meeting Talk about each one
Page 4: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

Major Institution Boundary and Campus Sectors

WEST CAMPUS

CENTRALCAMPUS

SOUTH CAMPUS

EAST CAMPUS

Presenter
Presentation Notes
Original Image path: C:\Users\lge\Desktop\district-01.jpg Last Updated: 12/6/2015 1:17:48 AM by lge via Sasaki PPT Image Manager
Page 5: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

2018 Campus Master Plan Development Capacity

This plan identifies almost 12.7 million gross square feet of development. During the life of this plan, only 6 million will be developed within the four sectors of campus based on the square footage in the fourth column.

Campus AreaNet New

Development Introduced (GSF)

Maximum Development Limit

(%)

Maximum Development Limit

(GSF)

Central 2,010,551 15% 900,000

West 3,198,685 50% 3,000,000

South 2,892,735 25% 1,500,000

East 4,633,571 10% 600,000

Total 12,735,542 100% 6,000,000

Presenter
Presentation Notes
Original Image path: T:\for staff\Romil\SCUP Images\UW\01.jpg Original Size: 25.6MB W:16,175px H:9,600px Compressed Size: 1.7MB W:3,400px H:2,017px (93.5% using JPEG compression of 95) Last Updated: 4/21/2016 11:52:04 AM by cclauson via Sasaki PPT Image Manager
Page 6: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

NE 45th Street

15thAve N

E

2018 Potential Development Sites• 85 sites spread throughout the four sectors of campus• Not all sites will be developed• Only 6 million of the 12.7 identified will be developed• Identifying more space than needed gives the University

flexibility

Presenter
Presentation Notes
Original Image path: T:\for staff\Romil\SCUP Images\UW\01.jpg Original Size: 25.6MB W:16,175px H:9,600px Compressed Size: 1.7MB W:3,400px H:2,017px (93.5% using JPEG compression of 95) Last Updated: 4/21/2016 11:52:04 AM by cclauson via Sasaki PPT Image Manager
Page 7: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

2018 Campus Master Plan Potential* Development Site Heights

Potential Development SitesExisting Buildings

*not all potential development sites will be developed

240ft240ft

200ft

200ft200ft 130ft

240ft

240ft

240ft

160ft

80ft80ft

80ft

130ft 65ft

65ft

65ft

65ft

30ft

65ft

65ft

160ft

105ft

105ft

105ft

65ft

105ft

30ft

105ft240ft

105ft105ft

130ft

Presenter
Presentation Notes
Original Image path: T:\for staff\Romil\SCUP Images\UW\01.jpg Original Size: 25.6MB W:16,175px H:9,600px Compressed Size: 1.7MB W:3,400px H:2,017px (93.5% using JPEG compression of 95) Last Updated: 4/21/2016 11:52:04 AM by cclauson via Sasaki PPT Image Manager
Page 8: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

West Campus

Presenter
Presentation Notes
Original Image path: M:\56125.96\Interview\PPT\Process Diagram\Phases_1-02.jpg Last Updated: 6/10/2015 11:42:24 AM by cclauson via Sasaki PPT Image Manager
Page 9: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

West Campus – Big Moves

Campus AreaNet New

Development Introduced (GSF)

Maximum Development

Limit (%)

Maximum Development Limit

(GSF)

Central 2,010,551 15% 900,000

West 3,198,685 50% 3,000,000

South 2,892,735 25% 1,500,000

East 4,633,571 10% 600,000

Total 12,735,542 100% 6,000,000

3 million net new gsf

Illustrative rendering of sites that could be developed with 3 million cap

Park would be phased in as new development occurs

Presenter
Presentation Notes
Original Image path: G:\56125.00\3.0_Working\3.6_Graphics\3.6.1 Illustrator\8_District 3D diagrams\EXPORT 20151204\WEST2-01.jpg Last Updated: 12/6/2015 5:42:58 PM by lge via Sasaki PPT Image Manager
Page 10: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

South Campus

Presenter
Presentation Notes
Original Image path: G:\56125.00\3.0_Working\3.6_Graphics\3.6.1 Illustrator\3_MASTER PLAN AND PLAN DIAGRAMS\P-MAP-01.jpg Original Size: 16.5MB No compression. WARNING: this is a large image, please consider optimizing. Cropping: Left:1% Right:61% Top:42% Bottom:24% Last Updated: 11/6/2015 1:15:14 PM by lge via Sasaki PPT Image Manager
Page 11: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

South Campus – Big MovesCampus Area

Net New Development

Introduced (GSF)

Maximum Development

Limit (%)

Maximum Development Limit

(GSF)

Central 2,010,551 15% 900,000

West 3,198,685 50% 3,000,000

South 2,892,735 25% 1,500,000

East 4,633,571 10% 600,000

Total 12,735,542 100% 6,000,000

1.5 million net new gsfIllustrative rendering of sites that could be developed with 1.5 million limit

Park would be phased in as new development occurs

Presenter
Presentation Notes
Original Image path: G:\56125.00\3.0_Working\3.6_Graphics\3.6.1 Illustrator\8_District 3D diagrams\EXPORT 20151204\SOUTH-01.jpg Last Updated: 12/6/2015 6:40:19 PM by lge via Sasaki PPT Image Manager
Page 12: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

East Campus

Page 13: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

East Campus – Big MovesCampus Area

Net New Development

Introduced (GSF)

Maximum Development

Limit (%)

Maximum Development Limit

(GSF)

Central 2,010,551 15% 900,000

West 3,198,685 50% 3,000,000

South 2,892,735 25% 1,500,000

East 4,633,571 10% 600,000

Total 12,735,542 100% 6,000,000

600,000 net new gsfIllustrative rendering of sites that could be developed with 600,000 limit

Presenter
Presentation Notes
Original Image path: G:\56125.00\3.0_Working\3.6_Graphics\3.6.1 Illustrator\8_District 3D diagrams\EXPORT 20151204\EAST-01.jpg Last Updated: 12/6/2015 7:05:07 PM by lge via Sasaki PPT Image Manager
Page 14: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

Central Campus

Presenter
Presentation Notes
Original Image path: G:\56125.00\3.0_Working\3.6_Graphics\3.6.1 Illustrator\3_MASTER PLAN AND PLAN DIAGRAMS\P-MAP-01.jpg Original Size: 16.5MB No compression. WARNING: this is a large image, please consider optimizing. Cropping: Left:1% Right:61% Top:42% Bottom:24% Last Updated: 11/6/2015 1:15:14 PM by lge via Sasaki PPT Image Manager
Page 15: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

Central Campus – Big Moves Campus AreaNet New

Development Introduced (GSF)

Maximum Development

Limit (%)

Maximum Development Limit

(GSF)

Central 2,010,551 15% 900,000

West 3,198,685 50% 3,000,000

South 2,892,735 25% 1,500,000

East 4,633,571 10% 600,000

Total 12,735,542 100% 6,000,000

900,000 net new gsfIllustrative rendering of sites that could be developed with 900,000 limit

Presenter
Presentation Notes
Original Image path: G:\56125.00\3.0_Working\3.6_Graphics\3.6.1 Illustrator\8_District 3D diagrams\EXPORT 20151204\CENTRAL3-01.jpg Last Updated: 12/7/2015 5:03:01 PM by lge via Sasaki PPT Image Manager
Page 16: 2018 Campus Master Plan - UW Facilities · Winter and Spring 2016 • Draft Plan and Draft EIS published – Fall 2016 •Final Plan and Final EIS published – Winter 2017 •Hearing

CURRENT SCHEDULE for2018 CAMPUS MASTER PLAN

• Kick off of Campus Master Plan and EIS Scoping October 14 & 15, 2015

• Preliminary Plan Concepts Developed –Winter and Spring 2016

• Draft Plan and Draft EIS published – Fall 2016•Final Plan and Final EIS published – Winter 2017•Hearing Examiner and City Council – Summer 2017•City Council and Board of Regents approval –

Late 2017 or early 2018