Transcript of 2014 Ministerial Press Briefing Presentation by FERMA
MINISTERIAL PRESS
BRIEFING
FMW – SUMMARY OF FERMA
ACTIVITIES
Ministerial Briefing, September 2014
1
Outline
• Introduction(Background)
• Current Administration (Transformation)
– Strategies and Actions
– Results and achievements
– Work Photographs
– Video
• Conclusion
2Ministerial Briefing, September 2014
FERMA is committed to a consistent preventive road maintenance culture
through intensive surveillance, monitoring and repairs.
3Ministerial Briefing, September 2014
Introduction
FERMA Establishment and Mandate
The Federal Roads Maintenance Agency (FERMA) was established on
November 30th 2002 by an Act of the National Assembly cited as the
Federal Roads Maintenance Agency (Establishment, etc.) Act 2002 and
an Amendment Act 2007.
The Agency’s mandate is to ensure the efficient and effective
maintenance of all existing Federal trunk roads or such other roads as
may be declared, from time to time, as Federal trunk roads by the
National Assembly.
Since establishment in 2003, the Federal Roads Maintenance Agency
(FERMA) have made significant efforts towards effective and efficient
maintenance of the nations over 35,000km of Federal Highways.
Today, the Agency operates from 12 zonal and 38 state field operation
office.
4Ministerial Briefing, September 2014
Background
• The challenges from inception includes;
inherited huge maintenance backlogs.
funding challenges.
Resultant calls for the declaration of a state of emergency in the
road sector.
CURRENT ADMINISTRATION`S EFFORTS
Consequently, Mr. President directed that an aggressive and
strategic measure be put in place to make our Federal roads once
more motorable.
Thank God for the drive, commitment and support of the Hon.
Minister of Works.
Based on this instruction, considering that close to 80% of these
highways were in a state of total disrepair. 5Ministerial Briefing, September 2014
Background
They have exceeded design life span and generally weak
and old distressed pavements.
Still exposed to excess axle loading.
6Ministerial Briefing, September 2014
Current Administration
Thus the current FERMA management in
September 2011, developed a blueprint (Rapid
Road Recovery Blueprint-RRRB) that sets out the
Agency’s Road Maintenance Plan for 2011 to 2015:
Appropriate institutional framework was put in place
to cope with this challenge.
7Ministerial Briefing, September 2014
Current Administration
Aggressive Response by the Current Administration
The following aggressive response was adopted.
Flagged off the Preventive Road Maintenance Programme
at various zones nationwide,.
Established a Surveillance and Effective Monitoring Unit.
Acquired additional state of the art road Maintenance
equipment (patchers, back hoes etc).
Reorganized the Research and Development Unit to
develop all year round work materials for distribution and
use – cold Asphalt.
8Ministerial Briefing, September 2014
Current Administration
Developed and established the Public Works Unit to
mobilize unemployed Nigerian youths along Federal
roads alignments for routine Maintenance works.
Flagged off the Zero pothole initiative.
Commenced and sustained the reorientation of our
Engineers at various Zones to improve on productivity
and embrace good work ethics.
Commenced the quarterly Roads and projects
monitoring programme.
Commenced the Stakeholders interactive meeting
(NARTO, PTD) etc.
9Ministerial Briefing, September 2014
Current Administration
Established Federal Roads Committee on Surveillance and
Action Against Road Abuse (FERCSARA).
Installed and commissioned 3 Nos. 80TPH Asphalt Plants
for quick access to Asphaltic Concrete in Lagos, Abuja and
Oshogbo.
Prioritizing of maintenance programmes – Taking economic
roads first.
(Photographic representation of the above strategies will be
shown in subsequent slides)
10Ministerial Briefing, September 2014
Current Administration
Other strategies explored for sustainable road
maintenance programme include:
i. Comprehensive pavement management system (PMS)
Deploying Falling Weight Deflectometer(FWD), Road Roughness,
and Dynamic Cone Penetrometer equipment for data gathering to
inform decision making and cost effective road management.
ii. Area Management Contracts
Contracting out maintenance works on a specified km of road to
competent and equipped contractors for a fixed term period.
iii. Alternative funding.
IVTC, RoW billboards(as will be approved by relevant authorities),
and MOT options etc.
11Ministerial Briefing, September 2014
SUMMARY OF CURRENT ROAD MAINTENANCE TRANSFORMATION PROGRAMME:
• Proactive Recovery of Federal roads in bad conditions.
• Acquisition of all in one state of the art Bergkamp Mobile pothole patchers – 38 Nos.
• Operational use of 2No 80TPH Asphalt plant – Kuje & Lagos.
• Regular use of over 40No. Mini Asphalt plants.
• Production of Cold Asphalt for all year round maintenance work.
• Blending of Emulsion for regular use at sites.
• Inauguration of the Public Works Programme/SURE P.
• Road Surveillance Unit for proactive maintenance.
• General reorientation and workforce motivation.
• Selective Emergency Intervention Works nationwide.
• Selective Pavement Strengthening (overlay) programme.
• Progressive repairs and replacement of damaged/vandalized hydraulic structures, bridge handrails and road signs. 12
S/N DESCRIPTION BEFORE DURING AFTER
NORTH CENTRAL ZONE
1SPECIAL REPAIRS & PAVEMENT STRENGTHENING OF SECTIONS OF MOKWA -TEGINA ROAD
2GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG AKWANGA - KEFFI ROAD IN NASARAWA STATE
3GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG KATSINA – ALA –TAKUM – KONA BAISSA ROAD
PHOTOGRAPHS OF SOME EXECUTED ROAD MAINTENANCE PROJECTS
13
S/N DESCRIPTION BEFORE DURING AFTER
NORTH EAST ZONE
1
GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG MAYOBELWA – JADA –GANYE ROAD
2
GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG GOMBE - BILLIRI – FILLIYA ROAD IN GOMBE STATE
3 GENERAL MAINTENANCE REPAIRS & PAVEMENT STRENGTHENING OF
SECTIONS ALONG GOMBE -POTISKUM ROAD, SECTION
II(KM.80+000 - KM.124+000) IN YOBE STATE 14
PHOTOGRAPHS OF SOME EXECUTED ROAD MAINTENANCE PROJECTS
S/N DESCRIPTION BEFORE DURING AFTER
NORTH WEST ZONE
1
KANO - ZARIA ROAD (KM.0+000 - KM.86+000) SECTION I KANO STATE
2EMERGENCY REPAIRS OF WASHOUT AT KM.22+000 ALONG BAGUDO - TUGA -KAOJE ROAD IN KEBBI STATE
3
SECTIONS OF KADUNA -BIRNIN GWARI ROAD IN KADUNA STATE
15
PHOTOGRAPHS OF SOME EXECUTED ROAD MAINTENANCE PROJECTS
S/N DESCRIPTION BEFORE DURING AFTER
SOUTH EAST ZONE
1GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG 9TH MILE –AWKA (OLD ROAD) IN ANAMBRA STATE
2
GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG UMUAHIA –BENDE ROAD
3 GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG YAHE – ABAKALIKI –NKALAGU – ENUGU ROAD 16
PHOTOGRAPHS OF SOME EXECUTED ROAD MAINTENANCE PROJECTS
S/N DESCRIPTION BEFORE DURING AFTER
SOUTH SOUTH ZONE
1 GENERAL REPAIRS AND PAVEMENT STRENGTHENING (OVERLAY) OF SECTIONS ALONG OGOJA – OBUDU ROAD
2 GENERAL REPAIRS AND PAVEMENT STRENGTHENING (OVERLAY) OF SECTIONS ALONG AHOADA – ABUA - DEGEMA ROAD
3 GENERAL REPAIRS AND PAVEMENT STRENGHTENING (OVERLAY) OF SECTIONS ALONG AMUKPE-ABRAKA-UMUTU-AGBOR-UROMI ROAD
17
PHOTOGRAPHS OF SOME EXECUTED ROAD MAINTENANCE PROJECTS
S/N DESCRIPTION BEFORE DURING AFTER
SOUTH WEST ZONE
1 GENERAL REPAIRS OF SECTIONS ALONG ITAWURE - ESA OKE JUNCTION OSUN STATE BORDER ROAD IN EKITI STATE
2 OLD ABEOKUTA ROAD IN LAGOS STATE
3 REPAIRS OF IJORA COURSE WAY, LAGOS STATE (FAILED SECTIONS)
18
PHOTOGRAPHS OF SOME EXECUTED ROAD MAINTENANCE PROJECTS
NORTH CENTRAL ZONE1. POTHOLE PATCHING ALONG MAKURDI – GBOKO –YANDEV ROAD (CH.0+000 – CH.82+000) IN
BENUE STATE
19
NORTH CENTRAL ZONE
2. GENERAL REPAIRS OF SECTIONS ALONG KABBA – ISANLU – EGBE ROAD (INCLUDING ABU
BRIDGE) IN KOGI STATE
20
NORTH EAST ZONE
1. SPECIAL MAINTENANCE REPAIRS ALONG NGURORE - MAYOBELWA ROAD CH. 18+000 – CH.
44+000 IN ADAMAWA STATE.
21
NORTH EAST ZONE
2. EMERGENCY REPAIRS OF GOMBE – NUMAN ROAD (KM. 136 + 400 – KM. 145 + 200) IN GOMBE
STATE.
22
NORTH WEST ZONE1. SPECIAL GENERAL MAINTENANCE OF SECTIONS OF KAFFIN MAIYAKI – TUDUN WADA –
SAMINAKA ROAD IN KANO STATE
23
NORTH WEST ZONE
2. EMERGENCY REPAIRS OF EMBANKMENT WASHOUT AT KM.16+200-KM.19+500 AND
KM.35+100 ALONG RIJAU-RIBAH-WASAGU ROAD IN KEBBI STATE
24
SOUTH EAST ZONE1. GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG OWERRI – OKIGWE ROAD IN
IMO STATE
25
SOUTH EAST ZONE 2. REPAIRS OF FAILED SECTIONS ALONG OWUTU – AMASIRI – OKPOSI – UBURU ROAD IN
EBONYI STATE
26
SOUTH SOUTH ZONE 1. EXPANSION OF MBIAMA – YENAGOA ROAD, BAYELSA STATE.
27
SOUTH SOUTH ZONE 2. GENERAL MAINTENANCE REPAIRS OF SECTIONS ALONG EWU – UROMI – AGBOR
ROAD IN EDO STATE
28
SOUTH WEST ZONE 1. MAINTENANCE REPAIRS OF FAILED SECTIONS ALONG ILESHA – IJEBU JESA ROAD IN OSUN
STATE
29
SOUTH WEST ZONE SPECIAL REPAIRS OF CRITICAL SECTIONS ALONG ADO-IKERE-ONDO STATE BORDER ROAD (CH
14+000 - CH 25 + 000) IN EKITI STATE
30
(1) Reinstatement of Collapsed 7-Cell Box Culvert at
CH.11+850 & CH.12+850 along Katsina – Kano highway &
provision of 2 bridges & approach roads.
(2) Reinstatement of Embankment washout & collapsed 3-
cell culvert at KM.34+200 along Gombe – Bauchi road,
Gombe state – In progress.
(3) Washout at culvert locations at CH.0+450 along Kaduna
Western Bypass Road – In progress.
(4) Reinstatement of submerged box culvert and
approaches at Ch. 29+500 along Asaba – Ebu – Ilushi
Road, Delta state – In progress.
Photographs in subsequent slides.
31
FERMA EMERGENCY INTERVENTION WORKS ON ROAD WASHOUTS & BRIDGES
(5) Washout Bridge Approach and Embankment at CH.0+100 (Shendam
Bridge) along Shendam – Yelwa – Ibi road in Plateau state.
(6) Washout Bridge Embankment at CH15+025 (Lalin Bridge) along
Langtang – Lalin – Tunkus – Shendam Road in Plateau state.
(7) Reinstatement of Embankment washout at CH.39+050 along Zaria –
Pambegua road in Kaduna state.
(8) Provision of RC Pile bridge (75m long) & 1km road access across Kolo
creek at Kolo town, Bayelsa state – In progress.
(9) Reinstatement of failed embankment and vandalised handrails at
Njaba Bridge, along Owerri –Orlu road, Imo state.
(10)Reinstatement of washout & collapsed triple cell culvert atKM10+500 (4th Interchange) Enugu – PortHarcourt Dual Carriageway.
Completed.
FERMA EMERGENCY INTERVENTION WORKS ON ROAD WASHOUTS & BRIDGES
32
REINSTATEMENT OF COLLAPSED 7-CELL BOX CULVERT AT CH.11+850 &
CH.12+850 ALONG KANO – KATSINA HIGHWAY
33
REINSTATEMENT OF EMBANKMENT WASHOUT AND COLLAPSED 3-CELL
CULVERT AT KM.34+200 ALONG GOMBE – BAUCHI HIGHWAY – IN PROGRESS
34
REINSTATEMENT OF SUBMERGED BOX CULVERT AND APPROACHES AT CH.29+500
ALONG ASABA – ILLAH – ILLUSHI ROAD, DELTA STATE – IN PROGRESS
35
WASHOUT BRIDGE APPROACH REPAIRS AND EMBANKMENT REINSTATEMENT
AT CH0+100 (SHENDAM BRIDGE) ALONG SHENDAM – YELWA – IBI ROAD IN
PLATEAU STATE
36
EMERGENCY REINSTATEMENT OF WASHOUT BRIDGE APPROACH AND
EMBANKMENT ALONG LANGTANG – LALIN – TUNKUS – SHENDAM ROAD
CH 15 + 025 IN PLATEAU STATE
37
REINSTATEMENT OF EMBANKMENT WASHOUT AT CH 39+050 ALONG ZARIA -PAMBEGUA ROAD IN KADUNA STATE
38
PROVISION OF REINFORCED CONCRETE PILE BRIDGE (75m LONG) AND 1KM
LINK ROAD ACROSS KOLO CREEK AT KOLO TOWN IN BAYELSA STATE – IN
PROGRESS
39
NJABA BRIDGE, ALONG OWERRI – ORLU ROAD, IMO STATE
40
REINSTATEMENT OF WASHOUT AND COLLAPSED OF TRIPLE CELL CULVERT AT KM 10+500 (4TH
INTERCHANGE) ENUGU – PORT HARCOURT DUAL CARRIAGEWAY
41
Table Showing Conditions of Federal Roads in 2011 & 2013
Condition 2011(%KM) 2013(%KM)
Good 52%(17,742KM)Over
75%(25,600KM)
Bad 48%(16,378KM) 25%(8,520KM)
42
MOVEMENT OF GAS TURBINE FROM ONNE PORT TO KADUNA POWER PLANT
43TAKE OFF POINT FOR THE TURBINE MOVEMENT FROM ONNE PORT, PH TO KADUNA
MOVEMENT OF GAS TURBINE FROM ONNE PORT TO KADUNA POWER PLANT
44ARRIVAL OF THE FINAL TRIP AT KADUNA
FEDERAL ROAD COMMITTEE ON SURVEILLANCE AND ACTION AGAINST ROAD ABUSE (FERCSARA)
45
In response to an urgent need to address the abuses
and bad behavior exhibited on the road network the
Agency has recently inaugurated a Federal Roads
Committee on Surveillance and Action Against Road
Abuse(FERCSARA). The membership comprises of ;
FERMA Headquaters and Zonal officers,
Federal Ministry of Works(Highways) officers,
Nigerian Army Engineers,
Nigerian Police Force (NPF),
Federal Roads Safety Corps (FRSC),
National Union of Road Transport Workers (NUTRW),
National Security and Civil Defense Corps, and
Local Government works officials
FEDERAL ROAD COMMITTEE ON SURVEILLANCE AND ACTION AGAINST ROAD ABUSE (FERCSARA)
46
The Committee is responsible for;
identifying major abuses and proffering solutions
monitoring occurrences of road abuse and carry out
corrective measures
liaising with law enforcement agencies to ensure the
reinstatement and replacement of damaged carriageway
and road furniture
collaborating with appropriate law enforcement agencies
for the enforcement of relevant extant rules and regulations
on willful damage to government properties in the road
infrastructure sub sector.
liaising with relevant stakeholders to stop further abuses
and ensure sustenance of good road usage by motorists.
cause arrest to be made where necessary.
discourage major haulage companies from deliberate
overloading and indiscriminate parking.
FEDERAL ROAD COMMITTEE ON SURVEILLANCE AND ACTION AGAINST ROAD ABUSE (FERCSARA)
47REMOVAL OF SHOULDER ENCHROACHMENT IN PROGRESS
OTHER INTERVENTION WORKS
48
REINSTATEMENT OF EMBANKMENT WASHOUT/COLLAPSED WING WALLS AND APRON AT CH.44+350 ALONG ZARIA-PAMBEGUA ROAD IN KADUNA STATE
49
KM.29+788 – KM.29+020 ALONG MBIAMA – YENAGOA ROAD (DUAL CARRIAGEWAY)
50
REINSTATEMENT OF WASHOUTED ROAD EMBANKMENT AT CH.124+500 (AUCHI TOWNSHIP) ALONG BENIN – AUCHI – OKENE ROAD IN EDO STATE
51
CONSTRUCTED RC LINED DRAIN AT KM13+800 AT CH.4+300 – CH.4+800(LHS) ALONG DIKKO – MAJEROAD IN NIGER STATE
52
ROAD SUPPORT SERVICES
53
Equipment
Observation & Service camps
State Field Offices construction
Highway & Bridges Illumination
MOBILE POTHOLE PATCHER
54BERGKAMP FP5 MOBILE POTHOLE PATCHERS
MOBILE POTHOLE PATCHER IN OPERATION AT THIRD MAINLAND
BRIDGE, LAGOS
MOBILE POTHOLE PATCHERS AT WORK
MOBILE POTHOLE PATCHER IN OPERATION ALONG ABUJA – KADUNA
DUAL CARRIAGEWAY
55
MOBILE POTHOLE PATCHERS AT WORK
MOBILE POTHOLE PATCHER IN OPERATION ALONG ABUJA – KEFFI DUAL CARRIAGEWAY
56
80TPH ASPHALT PLANT INSTALLED AT ABUJA, LAGOS, OSOGBO WHILE 4 OTHERS ARE AT VARIOUS STAGES OF INSTALLATIONS
40 MINI ASPHALT PLANT DEPLOYED TO VARIOUS FIELD OFFICES NATIONWIDE
57
COLD ASPHALT PRODUCTION Product of FERMA R&D for proactive intervention works
6 MONTH OLD COLDASPHALT
BAGGED COLD ASPHALTPRIMING & OVERLAY WITH COLD
ASPHALT
PRIMING & OVERLAY WITH COLD ASPHALT
AGGREGATE BLENDING FOR COLD
ASPHALT PRODUCTION
COLD ASPHALT PRODUCTION IN
PROGRESS
58
OBSERVATION & SERVICE CAMP Built by FERMA to provide emergency services to road users, utilised by the FERMA, Police,& FRSC
RECENTLY COMPLETED OBERVATION & SERVICE CAMP ALONG AKURE – ADO EKITI ROAD (KM.7+400) ITAOGBOLU, ONDO STATE
RECENTLY COMPLETED OBERVATION CAMP AT ODUKPANI, CROSS RIVER STATE
59
www.ferma.gov.ng
SOME PICTURES OF OBSERVATION & SERVICE CAMPS CONSTRUCTION
OBSERVATION CAMP AT ELELE, RIVERS STATE OBSERVATION & SERVICE CAMP AT AGO ARE, OYO STATE
OBSERVATION CAMP AT AKWANGA ,NASARAWA STATE OBSERVATION CAMP AT IGBO UKWU, ANAMBRA STATE60
www.ferma.gov.ng
SOME PICTURES OF TRAILER PARKS & FIELD OFFICES CONSTRUCTION
FENCING OF STATE FIELD OFFICE, AWKA, ANAMBRA STATE FENCING OF TRAILER PARK AT AKINYELE, OYO STATE
STATE FIELD OFFICE CONSTRUCTION AT LAFIA COMPLETED STATE FIELD OFFICE AT ZAMFARA
61
HIGHWAY /BRIDGE LIGHTING
LIGHTING OF THIRD MAINLAND BRIDGE
62
www.ferma.gov.ng
SOLAR POWERED LIGHTING AT KEFFI
INTERCHANGE, NASARAWA
SOME HIGHWAY/BRIDGE LIGHTING PROJECTS
PROCURED ALTEC L37 M STREETLIGHTS
PLAT FORM IN USE AT JOS
63
www.ferma.gov.ng
LIGHTING ON NIGER BRIDGE,
ONITSHA/ASABAHIGHWAY LIGHTING ALONG KADUNA
WESTERN BYPASS
SOME HIGHWAY/BRIDGE LIGHTING PROJECTS
64
SOME FERMA – SURE P ACTIVITIES
65
PREAMBLE:Over the years, huge investments have been made on roads &
bridges without adequate maintenance programmes put in place.
Rather, expensive corrective measures after failure was thepractice.
FERMA Preventive Roads Maintenance Operations under the SURE-P Public Works Programme involves the mobilization anddeployment of able and willing workforce for routine direct labourmaintenance works on critical federal roads close to their abode.
PROGRAMME CONCEPT
66
OBJECTIVES:
PROGRAMME CONCEPT
• Prolong the life span of selected roads of high economic impact
• Ensure that roads are made safe and motorable all year round
• Job creation/Poverty alleviation
• Enhance sustainable maintenance culture
• Engender community/public ownership and involvement in road
works
• Improve trust and goodwill between government and the people
• Reduce overall huge cost of corrective maintenance contracts
67
ROAD REPAIRS ALONG ABUJA-KEFFI BY SURE P - FERMA PUBLIC WORKS TEAM
68
PROVISION AND INSTALLATION OF HIGH-RESISTANT POLYMER NEW JERSEY
CRASH-BARRIERS TO REPLACE VANDALIZED/DAMAGED HANDRAILS AT TAFA
BRIDGE ALONG KADUNA-ABUJA DUAL CARRIAGEWAY
69
DESILTING OF BLOCKED DRAINS BY THE SURE P - FERMA PUBLIC WORKS TEAM
70
MEDIAN VEGETATION CONTROL ALONG ABUJA- KADUNA ROAD BY THE SURE P - FERMA PUBLIC WORKS TEAM
71
POTHOLE PATCHING USING FP5 BERGKAMP FLAMELESS PATCHER & PAINTING OF PARAPET WALLSAND BRIDGE RAILINGS ON 3RD MAINLAND BRIDGE BY THE SURE P - FERMA PUBLIC WORKS TEAM
72
ROAD MARKING ALONG ABUJA – KADUNA DUAL CARRIAGEWAY UNDER FERMA SURE-P
73
SOME OF THE KITS AND BASIC HANDTOOLS FOR PUBLIC WORKS
74
75
SOME ECONOMIC ROUTES MONITORED/MAINTAINED BY FERMA
S/N CONSIDERED ROUTES LENGTH (KM) STATES COVERED
1 Abuja-Kaduna- Dual 307.0 FCT - Kaduna
2 Kaduna-Kano - Dual 336.0 Kaduna-Kano
3 Benin-Asaba - Dual 266.0 Edo-Delta
4 Enugu-9th Mile-Otukpa 93.0 Enugu-Benue
5 Shagamu-Ore - Dual 98.0 Lagos-Ogun-Ondo
6 Owerri-Onitsha -Dual 88.0 Imo-Anambra
7 Jos-Bauchi 112.0 Plateau-Bauchi
8 Benin-Bypass-Warri-Dual 138.0 Edo-Delta
9 Parts of Benin-Auchi-Okene 176.0 Edo-Kogi
10 Parts of Lokoja-Okene 100.0 FCT-Kogi
11 Abuja-Keffi-Akwanga - (Abuja-Keffi -Dual) 107.0 FCT- Nasarawa
12 Ikot Ekpene-Odukpani-Calabar 90.0 Akwa Ibom-Cross River
76
SOME ECONOMIC ROUTES MONITORED/MAINTAINED BY FERMA
S/N CONSIDERED ROUTES LENGTH (KM)
STATES COVERED
13 Ibadan-Ilorin Dual 130.0 Oyo-Kwara
14 Primary Roads In Yenegoa 35.0 Bayelsa
15 Sokoto -Gusau 210.0 Zamfara-Sokoto
16 Katsina Ala-Zaki Biam-Wukari 95.0 Benue-Taraba
17 Ajaokuta - Itobe - Ayangba 56.0 Kogi
18 Ayangba - Ankpa - Ofu (Benue State Border) 94.0 Kogi
19 Apapa Oworonshoki-Old Toll Gate 32.0 Lagos
20 3rd Mailand Bridge 11.0 Lagos
21 Lagos-Badagry Seme Border Rroad 180.0 Lagos
22 Panyam -Shendam 85.0 Plateau
23 Abua-Ahoada-Omoke-Egbema 129.0 Rivers
77
SOME ECONOMIC ROUTES MONITORED/MAINTAINED BY FERMA
S/N CONSIDERED ROUTES LENGTH (KM) STATES COVERED
24 Okigwe-Afikpo 78.0 Ebonyi
25 Owerri-Aba road 43.0 Imo-Abia
26 Ibadan-Ife-Ilesha - Dual Carriageway 119.0 Oyo-Osun
27 Kotangora-Tegina 100.0 Niger
28 Sokoto-Shagari-Tambuwa-Kebbi S/B 96.0 Sokoto
29 Jalingo Jct. - Mutum Biu - Tella - Wukari Benue S/B 226.0 Taraba
30 Ewu-Uromi-Agbor-Sapele 197.0 Edo-Delta
31 Igede-Itawure-Efon Alaayee Road 30.0 Ekiti
32 Ifaki-Ikole-Omuo-Kogi S/B Road 90.0 Ekiti
33 Bauchi-Gombe Road 156.0 Bauchi-Gombe
34 Kano S/B-Birnin Kudu-Bauchi S/B Road 88.0 Jigawa
35 Katsina -Kano S/B 128.0 Katsina
36 Birnin Kebbi-Argungui Road 50.0 Kebbi
37 Yola-Song-Gombi road 42.0 Adamawa
Total4411
78
SELECTED COST SAVING PROJECTS
S/N PROJECT DESCRIPTIONPROPOSED
COST (N)EXECUTED COST (N)
SAVINGS (N)
1 Emergency Works Kano - Katsina Bridge 800M 556M 244M
2Emergency Works Mbiama - Yenegoa road & Bridge
Over 3Billion (S/C)
2.7Billion (D/C)
3.3Billion
3
Emergency Repairs and pavement strenghtening of sections along Onne Port -Kaduna route project for movement of Gas Turbines to Kaduna Power Plant (Enugu Bound)
4Billion 1.7Billion 2.3Billion
CURRENT EFFORTS & KEY PERFORMANCE EVALUATION
1Length of Road with good riding quality
17,742km (2011) 27,320km (2013) 77%
79
FERMA FUNDING SUMMARY FOR THE LAST 5 YEARS(2009 – 2014)
YEAR APPROPRIATION (N) RELEASES (N) SHORT FALL (N)
200943,969,689,656.42
43,852,651,223.72 -117,038,432.70
201062,616,065,053.00
51,611,527,557.80 -11,004,537,495.20
2011
29,655,265,155.00
32,818,510,794.00 3,163,245,639.00
2012
43,838,424,547.00
43,838,404,544.04 -20,002.96
201339,139,930,827.00
27,699,336,797.68 -11,440,594,029.32
80
Conclusion
Then, projects commenced but completion dates were most
unrealistic.
Now many projects are completed before due dates.
Then, massive clearing/earthworks were done and paid for, that
becomes only gullies after each rainy season.
Now payments are mainly for protected works.
Then, the cry was to declare a state of emergency on roads.
Now the remark is that the roads are better.
Then, you start your trip but never predict arrival time.
Now you can predict arrival time from origin to destination.
81Ministerial Briefing, September 2014
Conclusion
Then, passengers do not fall asleep while the drivers move, due
to potholes and discomfort..
Now, along several routes, passengers sleep while on tour.
A lot has been done
More is required to be done
But put together, transformation on road subsector is outstanding
and it shows all over.
We are however determined to move further and forward together
82Ministerial Briefing, September 2014
FERMA Emergency Contact lines
83Ministerial Briefing, September 2014
Emergency Call Lines:
Etisalat – 08092656666
Glo – 08155555889
Airtel – 08129999936
MTN – 07067779775
Conclusion
84Ministerial Briefing, September 2014
THANK YOU!!!